PMI-RMP 無料問題集「PMI Risk Management Professional」
A project has consistently been lagging in cost performance index (CPI) and schedule performance index (SPI) over the past few months. The risk manager realizes that some activities are taking longer than expected and more resources are needed.
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
Which project artifact should the risk manager analyze to mitigate the risk of further project overrun?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A risk manager completed risk response planning for a project that is currently in the execution phase. During a periodic review of the risk register, the project manager recognizes that some key secondary risks have not been considered.
Who should the project manager hold accountable for missing the risks?
Who should the project manager hold accountable for missing the risks?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager identified a risk of communication issues with the client which may impact the project schedule. A member of (he sales team advises that this client prefers face-to- face conversations.
What should the project manager do to avoid this risk?
What should the project manager do to avoid this risk?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
During the risk management planning, key stakeholders recommend adding more factors other than probability and the impact to refine the score of prioritized threats in subsequent iterations of the qualitative risk analysis. The stakeholders ask the risk manager to prepare a list to discuss this further.
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
Which three valid factors should the risk manager prepare on the list for discussion? (Choose 3)
正解:A、C、D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
One project in a program needs to be completed in 6 months because there is a large bonus for early completion. Consequently, the program manager transfers all resources to this project and arranges for employees to receive overtime pay.
Which risk response strategy is the program manager using in this scenario?
Which risk response strategy is the program manager using in this scenario?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
it typically takes 5 hours to perform a complete home inspection. If there are unforeseen risk factors, it can take up to 7 hours to finish the inspection. The earliest the project team has ever finished an inspection is in 3 hours.
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
Using the project evaluation and review technique (PERT) to estimate duration how many hours should the project manager plan to schedule the task taking into account all the positive and negative risk factors?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
Which risk identification technique should the risk manager use?
正解:A
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A project manager is working on a high priority and high profile project. The project team had identified three opportunities, and after analysis, risk responses were recorded. Although risk responses were adequate for the identified opportunities, two of those opportunities were not acted upon. During the risk audit, the project manager found out that several of the planned risk responses were not implemented.
What should the project manager have done to avoid this?
What should the project manager have done to avoid this?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
How should the risk manager proceed?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The project manager and the risk manager of a new project to develop an application to support autonomous driving are meeting with the sponsor and key stakeholders to discuss the project. During the meeting, it is identified that the transport authority is discussing new traffic regulations for the industry that could be in place before the project ends.
How should the project manager and the risk manager handle this situation?
How should the project manager and the risk manager handle this situation?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)