PMP 無料問題集「PMI Project Management Professional (2024 Version)」
A project manager encounters a governance issue during the project execution phase. One of the team members complains about receiving assignments from multiple people and states they are not able to work effectively.
What should the project manager establish first in the project governance structure?
What should the project manager establish first in the project governance structure?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
During a project, the project manager finds an opportunity to reduce the project cost by completing a deliverable ahead of schedule with a minimal impact on project resources. However, the client has only been focused on the next milestone.
How should the project manager approach this situation?
How should the project manager approach this situation?
正解:D
解答を投票する
Drag and Drop Question
A few months into a project, several schedule issues have emerged. Drag the schedule problems on the left to the specific tools on the right that, if implemented during schedule development, could have prevented the issues.

A few months into a project, several schedule issues have emerged. Drag the schedule problems on the left to the specific tools on the right that, if implemented during schedule development, could have prevented the issues.

正解:

A new project manager is assigned to an ongoing agile innovation project that started 2 weeks ago. After reviewing the project, the new project manager discovered that the previous project manager was planning to use a predictive approach. The previous project manager planned to present the first major deliverable to the client when the project was completely finished in 8 months.
What should the new project manager do?
What should the new project manager do?
正解:A
解答を投票する
A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress (WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
What should the project manager have done to avoid this situation?
正解:B
解答を投票する
A project manager is managing a project in the execution phase, which was agreed upon with the sponsor. However, the sponsor is constantly micromanaging and requesting iterations that are affecting the team's effectiveness. The sponsor indicates that as long as the project scope is not affected, these iterations are needed to simplify the project.
How should the project manager handle the situation?
How should the project manager handle the situation?
正解:D
解答を投票する
Drag and Drop Question
A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved. Drag the scenario on the left to the correct risk response strategy on the right.

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved. Drag the scenario on the left to the correct risk response strategy on the right.

正解:

During project execution, the risk owner is monitoring the critical speed rate of a power engine to eventually trigger the defined risk-response strategy. During the risk assessment and management process phase, it was defined that the power engine has the following characteristics:
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1,500 rpm (rate-per-minute) -> warns of max rate allowed
1,400 rpm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
1,600 rpm (rate-per-minute) -> stops working and crashes the system
1,500 rpm (rate-per-minute) -> warns of max rate allowed
1,400 rpm (rate-per-minute) -> reduces the power and brakes the engine
Which of the following statements is correct?
正解:C
解答を投票する
A project stakeholder complained that they did not receive an important delivery that was stated in the schedule. The team member responsible for this deliverable explained that they sent an email to the stakeholder, advising them that the deliverable would not be delivered on time.
What should the project manager have done to avoid this situation?
What should the project manager have done to avoid this situation?
正解:C
解答を投票する
A new major project is starting that consists of two interconnected subprojects. One of the subprojects was assigned to a contractor who commits to submitting biweekly status reports and attending weekly integration meetings. Halfway through the project, the contractor stops participating in the meetings and does not submit the reports. Their excuse is that these activities are consuming too much time.
How should the project manager handle this situation?
How should the project manager handle this situation?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
There is an upcoming merger between a functional organization and an agile organization. The merger has necessitated that team members from both organizations brainstorm the effect this merger will have on critical compliance standards and the previous regulations for a project.
What should the project manager do in order to achieve this objective?
What should the project manager do in order to achieve this objective?
正解:D
解答を投票する
A project is in the start-up phase of the project life cycle. The project team consists of 20 people from five different countries. The project team is scheduled to have quarterly face-to-face meetings. However, due to unforeseen circumstances, no face-to-face meetings can occur. The project manager is concerned that the team may not be able to fulfill their individual roles without face-to-face meetings.
What should the project manager do in this situation?
What should the project manager do in this situation?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)