An agile project is running activities to define the minimum viable product (MVP). During the session, the project manager identifies some mandatory regulations, but there is no consensus to include these regulations in the MVP because it may extend the duration of the project.
What should the project manager do?
What should the project manager do?
正解:A
解答を投票する
Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.
What should the project manager do next?
What should the project manager do next?
正解:C
解答を投票する
A project manager is implementing a new software system. Some department staff members are questioning the necessity of the change and feel the new system will impede their current processes.
What should the project manager have done at the start of the project to prevent this resistance'?
What should the project manager have done at the start of the project to prevent this resistance'?
正解:D
解答を投票する
A system migration project is in its closing stage. The project manager is being pressured to close the project. The project manager communicated to all stakeholders; however, the last department to migrate indicated that they have not received the notification.
What should the project manager do?
What should the project manager do?
正解:C