Small changes that bypass the organization's change control procedures are called ____.

You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?

June is the program manager for her organization. Management has asked June to create a visual mapping of the program scope so that all of the key stakeholders can see all of the elements of the program scope. June needs to create what kind of document to show all of the program deliverables based on the program scope?

A regional finance program is impacted by a new currency regulation issued by a country in the region. The new regulation requires changes to the financial statements of that country's branches by the end of the fiscal year. Failing to comply with the regulation may result in fines and/or closure of the branches. A branch general manager immediately meets with the program manager to select and secure a local fiscal expert to support the regulation, as these types of resources are in high demand. There is a high risk that the changes will not be completed on time if the resource is not secured.
What should the program manager do to address the risk?

A program sponsor needs more information to approve the latest additional projects for the current program. What supporting information should the program manager provide to obtain approval?

解説: (JPNTest メンバーにのみ表示されます)
A program manager is working on benefits. The program team created and updated a benefits register earlier in the program.
The benefits register should include which of the following?

The program manager leads a medical billing system integration program for company A, a health services provider. Company A acquires smaller company X, which delivers health services strategically aligned with company A.
Company X uses a different billing approach than company

Which of the following is used to build consensus through rounds of anonymous surveys?

A program manager wants to develop a benefits management plan after identifying the program benefits during the program's definition phase. What should the program manager to develop a program benefits management plan?

解説: (JPNTest メンバーにのみ表示されます)
Your program creates a byproduct that you could sell to a client. The cost of the byproduct would offset the cost of the program by nearly $7,500 per month. This is an example of which positive risk response?

A program manager has a multiple-project program that is scheduled to be completed by year's end. During the program delivery phases of the projects, several mandatory changes are identified that would extend the program's completion date.
What is the next step for the program manager?