The Product Owners (POs) on an ART held a brainstorming session to gather more detail on an upcoming Feature. They created many Stories but are still deciding which ones to do first because they seem necessary. Which technique would help organize the Stories and understand which are critical to implementing the Feature?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The Lean Portfolio Management team is reviewing new work moving through the Portfolio Kanban. Request 1 is incremental innovation and can likely be done by one ART in one PI. Request 2 is a major opportunity impacting multiple stages of the Value Stream, likely requiring the participation of two ARTs over multiple PIs. Which backlog should each request be added?
正解:D