A company has replicated their critical application VMs to a second data center in another region.
Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs. What needs to be configured in Veeam to prepare for a disaster recovery situation?
Their key application includes two database VMs and three application VMs. For proper operation, the database VMs need to start before the application VMs. What needs to be configured in Veeam to prepare for a disaster recovery situation?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
The administrator of a VMware environment backed up by Veeam Backup & Replication has a critical server that has crashed and will not reboot. They were able to bring it back online quickly using Instant VM Recovery so people could continue to work. What else is required to complete the recovery?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A corporation has the following requirements:
- Backups are configured with a retention to keep 30 daily backups /
five weekly backups / 12 monthly backups.
- Keep only 14 days of backups locally.
- All restore points should be stored in Amazon Simple Storage Service.
How should the Scale-out Backup Repository be configured?
- Backups are configured with a retention to keep 30 daily backups /
five weekly backups / 12 monthly backups.
- Keep only 14 days of backups locally.
- All restore points should be stored in Amazon Simple Storage Service.
How should the Scale-out Backup Repository be configured?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A photography company provides online purchase of photographs. The core of the business operates from an Oracle database that stores all company images. New photos are continuously added to the database at widely variable intervals. Company policy only requires the database to be protected. Which Veeam Feature will provide complete backup and recovery for this database?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A request to protect some new domain controllers has been submitted in the ticketing system.
The engineer creates a backup job with the following steps:
1. Right-clicks on the Jobs navigation item on the left
2. Selects VMware vSphere from the menu
3. Enters a name for the job.
4. Selects workloads to protect.
5. Defines a job schedule.
6. Clicks the Finish button.
When testing restores, the engineer finds that the backups are crash-consistent. Which set of steps should the engineer use to avoid crash-consistent backups for the domain controllers?
The engineer creates a backup job with the following steps:
1. Right-clicks on the Jobs navigation item on the left
2. Selects VMware vSphere from the menu
3. Enters a name for the job.
4. Selects workloads to protect.
5. Defines a job schedule.
6. Clicks the Finish button.
When testing restores, the engineer finds that the backups are crash-consistent. Which set of steps should the engineer use to avoid crash-consistent backups for the domain controllers?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A customer has a large VMware vSphere virtual machine with a custom operating system with intense I/O. The customer claims the backup process is causing the virtual machine to stun, despite a very performant production environment and Veeam proxies as powerful physical machines.
What is the correct solution to deploy?
What is the correct solution to deploy?
正解:B
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
A Scale-out Backup Repository with one local extent has been configured as follows.

A daily VMware backup job retention is 31 days, keeping weekly GFS full backups for 14 weeks.
It is Mar, 20. A file from a backup that occurred the week of Jan, 1 must be recovered. Where is the data?

A daily VMware backup job retention is 31 days, keeping weekly GFS full backups for 14 weeks.
It is Mar, 20. A file from a backup that occurred the week of Jan, 1 must be recovered. Where is the data?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
An administrator has configured a SureBackup job containing multiple Windows virtual machines.
The servers boot successfully and pass the heartbeat test but fail the ping test. The administrator logs into the console of the servers and can ping the default gateway, proving the network is functional.
Which next step must the administrator take to make the ping test succeed?
The servers boot successfully and pass the heartbeat test but fail the ping test. The administrator logs into the console of the servers and can ping the default gateway, proving the network is functional.
Which next step must the administrator take to make the ping test succeed?
正解:D
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)
Figure A shows the backup files on a Scale-out Backup Repository (SOBR) created by a single Veeam backup job. The SOBR is configured to offload to capacity tier in move mode. If the offload was completed successfully, what will remain on the performance extents for the files uploaded to the capacity tier?


正解:A
解答を投票する
The engineer configured Veeam Backup & Replications 3 years ago with an all-in-one physical server with one job backing up all VMs. The environment grew considerably and RPOs are no longer met.
The engineer checks the backup job and sees:
Load: Source 0% > Proxy 68% > Network 0% > Target 0%.
What should be done to decrease the backup processing time?
The engineer checks the backup job and sees:
Load: Source 0% > Proxy 68% > Network 0% > Target 0%.
What should be done to decrease the backup processing time?
正解:C
解答を投票する
解説: (JPNTest メンバーにのみ表示されます)