試験PMP-JPN トピック1 問題1714 スレッド

PMI PMP-JPNのリアル試験問題集
問題 #: 1714
トピック #: 1
プロジェクトは最終段階にあり、主要な関係者が製品機能の変更を要求しているため、クリティカル パスに 2 週間の時間が追加されます。プロジェクトマネージャーは何をすべきでしょうか?

おすすめの解答:B 解答を投票する

Explanation
According to the PMBOK Guide 7th Edition, a change request is any request to modify the agreed-upon project scope, schedule, cost, quality, or other project baselines. A change request can be initiated by any stakeholder at any stage of the project, and it should be evaluated for its impact on the project objectives and constraints. Therefore, the project manager should perform a detailed assessment to analyze the impact of the change request on the product feature, the critical path, and other project aspects, such as risk, quality, and stakeholder satisfaction. This will help the project manager to determine the feasibility, desirability, and priority of the change request, and to propose the best course of action to the change control board. Rejecting the change request, using schedule compression methods, or initiating a risk response strategy are not appropriate actions, as they do not address the root cause of the change request, the needs and expectations of the key stakeholder, or the potential benefits or drawbacks of the change request for the project outcome. References: PMBOK Guide 7th Edition, page 141-142.

Yamamoto 2026-03-30 09:19:40

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡