問題 #: 2162
トピック #: 1
あるプロジェクトチームがフルタイムのリモートワークに移行しました。プロジェクトマネージャーは、毎週のチームミーティングでリマインダーを発していたにもかかわらず、一部のチームメンバーが予定期日までに割り当てられたタスクを完了していないことに気づき始めました。これは、プロジェクトの納期遅延につながる可能性があります。
プロジェクトマネージャーはこの状況をどのように解決すべきでしょうか?

おすすめの解答:B 解答を投票する

The project manager should use the monitor and control project work process to track, review, and report the progress and performance of the project. This process involves collecting, measuring, and analyzing project data to identify variances from the baseline and take corrective actions if needed. One of the tools and techniques for this process is data analysis, which includes root cause analysis. Root cause analysis is a technique to identify the underlying factors that cause a problem or a deviation from the expected outcome.
By conducting root cause analysis, the project manager can understand why some team members are not completing their tasks on time and address the issues accordingly. This could involve providing feedback, coaching, training, or other support to the team members. Communicating the delivery dates more frequently (option A) may not be effective if the team members are facing other challenges or obstacles that prevent them from meeting the deadlines. Mentoring the team members to work in a remote environment (option C) may be helpful, but it is not the best option to resolve the current situation. The project manager should first identify the specific causes of the delays and then provide the appropriate guidance or assistance. Talking to the resource managers and requesting additional resources (option D) may not be feasible or necessary, as it may increase the project cost and complexity. Moreover, adding more resources may not solve the problem if the existing team members are not performing well or have other issues that affect their productivity. References: (Professional in Business Analysis Reference Materials source and documents) PMBOK Guide, 6th edition, pages 119-120, 4.4 Monitor and Control Project Work PMI, PMP Exam Content Outline, 2021, page 9, Domain II: Process, Task 7: Monitor project artifacts and resolve any deviations from the project management plan PMP Practice Questions #60 - iZenBridge

Obara 2026-04-09 06:46:29

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡