最新のCIPS L5M8認定の練習テスト問題

質問 # 103
During _____ processes for a new project, the organization recognizes that a new project exists, and completes a project charter as part of this recognition.

  • A. planning
  • B. controlling
  • C. opening
  • D. initiating

正解:B


質問 # 104
A(n) _____ on a project is a significant event that normally has no duration.

  • A. schedule baseline
  • B. milestone
  • C. activity attribute
  • D. activity sequence

正解:B


質問 # 105
The first step in deining the NPV is to _____.

  • A. deine the estimated costs and benefits for the life of the project and the products it produces
  • B. deine the discount rate
  • C. deine the cash flow
  • D. calculate the net present value

正解:A


質問 # 106
_____ processes include devising and maintaining a workable scheme to ensure that the project addresses the organization's needs.

  • A. planning
  • B. monitoring and controlling
  • C. executing
  • D. initiating

正解:B


質問 # 107
The project cost management knowledge area maps to the _____ process group through the activities of estimating costs and budget deination.

  • A. monitoring and controlling
  • B. planning
  • C. executing
  • D. initiating

正解:B


質問 # 108
Which of the following is true of low-end tools of the project management software?

  • A. they are referred to as an enterprise project management software
  • B. they provide basic project management features
  • C. their main advantage is that they have unlimited functionality
  • D. they are designed for especially large projects with multiple users

正解:B


質問 # 109
When an organization needs a new direction, the _____ leadership style is appropriate.

  • A. commanding
  • B. visionary
  • C. democratic
  • D. pacesetting

正解:B


質問 # 110
Which of the following is an output of schedule control?

  • A. Resource requirements
  • B. Milestones list
  • C. Lessons-learned reports
  • D. Activity attributes

正解:C


質問 # 111
_____ involves allocating the overall cost estimate to individual work items to establish a baseline for measuring performance.

  • A. Finalizing policies for project costs
  • B. Estimating costs
  • C. Deining the budget
  • D. Controlling costs

正解:C


質問 # 112
_____ involves doing whatever you can to make sure the positive risk happens.

  • A. Risk sharing
  • B. Risk acceptance
  • C. Risk exploitation
  • D. Risk enhancement

正解:C


質問 # 113
Key outputs of _____ process are project staff assignments, resource calendars, and project management plan updates.

  • A. planning the human resource plan
  • B. managing the project team
  • C. acquiring the project team
  • D. developing the project team

正解:C


質問 # 114
Scope refers to all the work involved in creating the products of the project and the processes used to create them.

  • A. False
  • B. True

正解:B


質問 # 115
_____ predict future project status and progress based on past information and trends.

  • A. Status reports
  • B. Project updates
  • C. Forecasts
  • D. Progress reports

正解:C


質問 # 116
The capacity to understand the motivations, intentions and desires of others is _____.

  • A. interpersonal intelligence
  • B. intrapersonal intelligence
  • C. human intelligence
  • D. emotional intelligence

正解:A


質問 # 117
Doctors who have been co-opted to actively participate in a project related to using information technology for chronic health problems would be examples of _____ stakeholders.

  • A. supportive
  • B. leading
  • C. resistant
  • D. neutral

正解:B


質問 # 118
Which of the following is one of Deming's 14 Points for Management?

  • A. Minimize total cost by working with multiple suppliers rather than a single supplier
  • B. Award business based on price tag alone rather than on other considerations
  • C. Eliminate the annual rating or merit system
  • D. An organization should increase dependence on inspection to achieve quality

正解:C


質問 # 119
A sprint review is a meeting in which the team demonstrates to the product owner what it has completed during the sprint.

  • A. False
  • B. True

正解:B


質問 # 120
In project time management, which of the following processes primarily involve identifying and documenting the relationships between project activities?

  • A. Estimating activity durations
  • B. Sequencing activities
  • C. Planning schedule management
  • D. Defining activities

正解:B


質問 # 121
Enterprise project management softwares are also known as _____ tools of project management software.

  • A. high-end
  • B. baseline
  • C. low-end
  • D. midrange

正解:A


質問 # 122
As the number of people involved in a project _____, the complexity of the communications _____.

  • A. increases, stays constant
  • B. increases, decreases
  • C. decreases, increases
  • D. increases, increases

正解:D


質問 # 123
In project procurement management, an output of the _____ monitoring and controlling process.

  • A. Selected sellers
  • B. Resource calendars
  • C. Change requests
  • D. Make-or-buy decisions

正解:D


質問 # 124
An example of pull communication is _____.

  • A. voice mails
  • B. meetings
  • C. blogs
  • D. video conferencing

正解:A


質問 # 125
NPV analysis is a method for making equal comparisons between cash flows for multi-year projects.

  • A. False
  • B. True

正解:B


質問 # 126
According to research by Albert Mehrabian, which of the following is NOT a way that information is communicated in a face-to-face interaction?

  • A. spoken content
  • B. body language
  • C. tone of voice
  • D. facial expression

正解:D


質問 # 127
_____ involves coordinating all planning efforts to create a consistent, coherent document.

  • A. developing the preliminary project scope statement
  • B. developing the organizational process assets updates
  • C. developing the project charter
  • D. developing the project management plan

正解:D


質問 # 128
......

検証済みのL5M8問題集と解答で一年間無料最速更新:https://www.jpntest.com/shiken/L5M8-mondaishu

今すぐ試そう2025年最新の無料更新されたCIPS L5M8試験問題と解答:https://drive.google.com/open?id=1D-HfyBN_-WCcXhxB9RRw2ctAX3MGbJsf

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡