質問 # 31
A valid concept of connectedness that allows an organization to maintain a high level of confidence in its distribution system is the:

  • A. Virtual warehouse
  • B. Implicit warehouse
  • C. Allocation warehouse
  • D. Commodity warehouse

正解:A


質問 # 32
What includes all activities that occur after a product is finished, including distribution selection, product order response and the return of goods?

  • A. Practical management
  • B. Logistics management
  • C. Core management
  • D. Operational management

正解:B


質問 # 33
A project manager is assigned to a project, either full-time or part-time, depending on the size of the project, and then must negotiate for the services of individual team members with each appropriate functional manager in:

  • A. Control Organization
  • B. Matrix Organization
  • C. Project Organization
  • D. Functional Organization

正解:B


質問 # 34
What is used to obtain general information about products, services or suppliers and is information request, not binding on either the supplier or the purchaser?

  • A. Procurement document
  • B. Target market
  • C. Qualified product description
  • D. Solicitation document

正解:D


質問 # 35
According to Project Management Institute,
which of the following is NOT the process group of project?

  • A. Organizing
  • B. Initiating
  • C. Closing
  • D. Executing

正解:A


質問 # 36
A term used to describe a 'one piece flow' business strategy that allows an organization to establish a continuous sequencing of product, within a flow process is known as:

  • A. Just-in-time scheduling
  • B. Inventory scheduling
  • C. Flow manufacturing
  • D. Online scheduling

正解:C


質問 # 37
What involves creating a visual depiction of a process, is the starting point to help understand each process and identify the sequencing of each process?

  • A. Process flowcharting
  • B. Process Planning
  • C. Process Equipment
  • D. Process mapping

正解:D


質問 # 38
A method of measuring an organization's activities in terms of its vision and strategies is the:

  • A. Balanced scoreboard
  • B. Hallucination process
  • C. Correlated action process
  • D. Business leaderships

正解:A


質問 # 39
Any material, component or product that is held for use at a later time is known as:

  • A. Cash
  • B. Asset
  • C. Inventory
  • D. Record

正解:C


質問 # 40
The process of accessing progress toward achieving predetermined goals is called:

  • A. Support center
  • B. Professional development
  • C. Efficiency evaluation
  • D. Performance measurement

正解:D


質問 # 41
A horizontal bar chart used in project management that is commonly used to plot the planned and actual progress of project activities is known as:

  • A. Gantt chart
  • B. Agreement chart
  • C. Progression chart
  • D. performance chart

正解:A


質問 # 42
What provides an illustration of the project's scope sand all tasks become the basic for monitoring the project's progress?

  • A. Work breakdown structure
  • B. Progress structure
  • C. Process flow structure
  • D. Project manual structure

正解:A


質問 # 43
Seasonality can be forecast using a multiplicative model to create a seasonal index.

  • A. True
  • B. False

正解:A


質問 # 44
Third parties who act as intermediaries between buyer and seller are known as:

  • A. Brokers
  • B. Dealer
  • C. Negotiator
  • D. Agent

正解:A


質問 # 45
The process of developing information systems through investigation, analysis, design,
implementation and maintenance is known as_ .

正解:

解説:
System Development Life Cycle


質問 # 46
A one-way system with incoming goods flowing to the left of the entry and into one of the three storage areas, depending on usage is the:

  • A. Cross-flow warehouse
  • B. Inverted T warehouse
  • C. Inverted U warehouse
  • D. Through-flow warehouse

正解:A


質問 # 47
Establishing an organization's consistent physical and functional characteristics for its materials is known as:

  • A. Regularity
  • B. Measurement
  • C. Standardization
  • D. Consistency

正解:C


質問 # 48
......