質問 # 83
What is the output of the Cross-Team Refinement event?
- A. Refined Product Backlog
- B. Refined Sprint Backlog
- C. Nexus Sprint Goal
- D. Updated team structure
正解:A
質問 # 84
Nexus Sprint Goal replaces the Individual Teams' Sprint Goal. True or False?
- A. TRUE
- B. FALSE
正解:B
質問 # 85
Select two correct statements about Scrum of Scrums and Nexus Daily Scrum?
- A. Scrum of Scrums is held before the individual teams' Daily Scrum
- B. Scrum of Scrums is held after the individual teams' Daily Scrum
- C. Nexus Daily Scrum is held prior to the individual teams' Daily Scrum
- D. Nexus Daily Scrum is held after the individual teams' Daily Scrum
正解:B、C
質問 # 86
Why would a Nexus choose to have different Sprint length for the teams in a Sprint?
- A. All teams in Nexus must have same Sprint length
- B. When there are inexperienced members in one team
- C. When there is risk and uncertainty in the items worked by certain teams
- D. When the increment is low risk
正解:C
質問 # 87
Who do the developers report the Daily Scrum status to?
- A. Nexus Integration Team
- B. Product Owner
- C. None of the listed options
- D. Scrum Master
正解:C
質問 # 88
Product Owner is responsible for Definition of Done in Nexus. True or False?
- A. TRUE
- B. FALSE
正解:B
質問 # 89
What is demonstrated during the Sprint Review in Nexus? Choose the BEST answer.
- A. Each team demonstrates the increment they built during the Sprint
- B. Only the key features of the integrated Increment
- C. There is no Sprint Review in Nexus
正解:C
質問 # 90
A five team Nexus is developing a purchase order application. There are several dependencies and Nexus faced a lot of challenges in managing them.
How should they conduct their Nexus Sprint Planning to minimize such difficulties due to the dependencies?
- A. Utilize refinement sessions to highlight the dependencies and visualize them for all the developers to see during the Nexus Sprint Planning
- B. Nexus Integration Team should assign the work since they are accountable for managing the dependencies
- C. Nexus should hold separate Sprint Planning for each team
- D. Bring in specialists from outside Nexus to guide the Developers
正解:A
質問 # 91
Select all the true statements about Nexus.
- A. There is always one Product backlog in a Nexus
- B. There is always one Product Owner in a Nexus
- C. There is always one Scrum Master in a Nexus
- D. There should be separate Product Owner per team
正解:A、B
質問 # 92
Which event follows after Nexus Daily Scrum?
- A. Individual team Daily Scrum
- B. Nexus Sprint Backlog adjustment
- C. Nexus Sprint Planning
- D. Refinement
正解:A
質問 # 93
Adding additional resources to Nexus will result in the value that is being delivered. True or False?
- A. TRUE
- B. FALSE
正解:B
質問 # 94
Who is an appropriate person to represent an individual team in Nexus Daily Scrum?
- A. Customer
- B. A developer working on an item which has cross team dependencies
- C. Product Owner
- D. Scrum Master
正解:B
質問 # 95
Who is responsible for clearing the technical debt?
- A. Nexus Integration Team
- B. Developers
- C. Product Owner
- D. Stakeholders
- E. Scrum Master
正解:B
質問 # 96
As part of the Nexus Sprint Retrospective, the team should address if there is technical debt in the product. True or False?
- A. FALSE
- B. TRUE
正解:B
質問 # 97
Nexus Daily Scrum replaces the individual team's Daily Scrum. True or False?
- A. TRUE
- B. FALSE
正解:B
質問 # 98
What is the purpose of Nexus Sprint Backlog? Select two best answers
- A. To make the dependencies transparent
- B. To provide a view of work that is not part of the product backlog
- C. To list all the work that is being performed by the Nexus Integration Team
- D. To highlight the flow of work during the Sprint
正解:A、D
質問 # 99
The Scrum teams in Nexus are struggling to create a DONE increment every Sprint. The scope is being adjusted often due to newly discovered dependencies and complications.
What could they do to increase the probability of producing an integrated increment for the next Sprint? Select two best answers
- A. Ask the Product Owner to extend the Sprint
- B. Reduce the number of Scrum Teams to reduce complexity
- C. Adjust the Definition of Done to make the increment releasable
- D. Increase the Cross-Team refinement activity duration
正解:B、D
質問 # 100
You are working in a Nexus with 3 teams. During the Nexus Sprint Planning, teams ran out of refined product backlog items. The items selected so far can only consume half of the Sprint.
What should the Nexus team do?
- A. Pause the Sprint Planning and initiate the Cross-Team Refinement meeting so that more items are available for teams to pick up the work
- B. Conclude the Sprint Planning meeting
- C. Cancel the Sprint
正解:B
質問 # 101
Who are the members of Nexus Integration Team? Select all that apply.
- A. Customer
- B. Scrum Master
- C. Project Manager
- D. Scrum Team members
- E. Product Owner
正解:B、D、E
質問 # 102
What is Nexus?
- A. Philosophy
- B. Methodology
- C. Framework
- D. Prescriptive approach
正解:C
質問 # 103
Who is accountable for managing Product Backlog in Nexus?
- A. Development Teams
- B. Nexus Integration Team
- C. Product Owner
- D. Scrum Master
正解:C
質問 # 104
During the first 2 Sprints of a product development, Team A's velocity is 10 points whereas Team B's velocity is 20 points.
Which team is performing better?
- A. Team B is performing better
- B. Team A is performing better
- C. Team's performance cannot be determined by comparing the velocity of another team
正解:C
質問 # 105
One of the key stakeholders sends an email to NIT Scrum Master. He is requesting the Nexus Sprint Review to be planned for 5 hours instead of 4, because the team is unable to demonstrate all the developed features.
What should the Nexus team do next?
- A. Disagree, because Nexus framework does not allow the Nexus Sprint Review to be longer than 4 hours
- B. Agree, because stakeholders have a right to see every feature developed
- C. Discuss internally to evaluate if indeed 5 hours are necessary before responding to stakeholder
正解:C
質問 # 106
......
合格保証付きのScaled Professional Scrum SPS試験問題集:https://www.jpntest.com/shiken/SPS-mondaishu
SPS練習テストエンジンで今すぐ使おう164試験問題:https://drive.google.com/open?id=1mPPFaZx7QNsxb6Xvs04Nndo932Z4F6Y0