質問 # 51
Using the Scenario, answer the following questions about scoping the proposal and preparing the Strategic Outline Case for the Pittville project.
Decide whether the approach is appropriate for stage 1, and select the response that supports your decision.
There is a risk that the local planning authority may reject proposals for development of the Old Fire Station Headquarters site. This will cause delays to the project.
Should this risk be recorded as an external non-systemic risk within the Strategic Outline Case?
- A. No, because risks should be identified in the Outline Business Case.
- B. No, because this is a service risk associated with the design and build phases of the project.
- C. Yes, because the local planning authority is an external organization.
- D. Yes, because changes to the Old Fire Station Headquarters site will affect the environment.
正解:C
質問 # 52
Spending objectives, existing arrangements and business needs are now being considered for the Pittville project.
Which entry is NOT a business need?
- A. The Consortium wants to see improvements in the levels of basic skills and overall learner success rates.
- B. The participations of 16-18-year-olds in education and training in Pittville is slightly below the average for the country. It has fallen over the last few years.
- C. Address the limitations of some further education units to offer choice and an appropriate learning environment.
- D. At least a 15% increase in the participation of 16-18-year-olds in education and training within the next three years.
正解:D
質問 # 53
Answer the following question about the costs identified when preparing the Economic Appraisal for the short list options for the Pittville project.
Column 1 contains a list of the costs identified. For each cost in Column 1, decide if the cost should be included in the Economic Appraisal and select from Column 2 the type of cost it represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1
1) The additional on-going cost of electricity for the Pittville
University development.
2) The money spent to date on the Old Fire Station
Headquarters site feasibility study and legal advice.
3) The cost of a stand-alone technology cabin with a
separate contract for specialist call-out support, paid on
an as-needed basis.
4) The Highways Department will have to upgrade the
access road to the Old Fire Station Headquarters site.
However, this cost will NOT count against the Pittville
project budget.
The Old Fire Station Headquarters site was to be sold
but will now be used for the new campus. It is owned by
the Council so there is no cost.
6) The car park at Pittville University will need to be
expanded if over 1,500 students attend the university.
Column 2
A) NOT included in the Economic Appraisal
B) Fixed cost
C) Variable cost
D) Semi-variable cost
E) Step cost
正解:
解説:
質問 # 54
Which 2 attributes demonstrate that this option supports the key CSF Potential affordability?
- A. The addition of a new campus will be matched by plans to downsize elsewhere.
- B. The option provides an increase in the progression to higher-level learning.
- C. The 3 local government authorities have formed a partnership known as the Western Area Learning Consortium.
- D. The cost of maintaining and adapting Pittville High School will be removed by closing the school.
- E. Constant prices have been used to estimate lifecycle costs in the value for money appraisal.
正解:A、D
質問 # 55
The best and final offers have been returned for the delivery of the new campus. The preferred supplier was Piaffeco, which was the same supplier that delivered the neighbouring Marshgate High School.
Should Economic Appraisals be prepared for the best and final offers for the discarded service providers on the short list?
- A. Yes, because the FBC should provide Economic Appraisals for all options.
- B. Yes, because the reasons for rejecting potential service providers from the long list to the short list stage should be provided.
- C. No, because updating the FBC with best and final offers should be done as part of the Commercial Case.
- D. No, because only the public sector comparator (PSC) should be updated in light of knowledge gained from the procurement.
正解:C
質問 # 56
Using the extract below from the Capital Profile for the new campus, answer the following questions.
(Note. The figures entered are correct).



正解:
解説:
質問 # 57
Answer the following question about scoping the proposal and preparing the Strategic Outline Case (SOC) for the Pittville project.
Column 1 is a list of information gathered about the Pittville project. For each entry in Column 1, select from Column 2 the option that best describes it. Each selection from Column 2 can be used once, more than once or not at all.

正解:
解説:
References:
These associations are made with the context of scoping the proposal and preparing the Strategic Outline Case (SOC) for the Pittville project, where it is crucial to align gathered
質問 # 58
Service Solution 1: 'Do minimum - introduce learning network to
existing schools and universities only'.
Which 2 statements are correct about this entry in the Options
Framework?
- A. Should be rejected as over-ambitious.
- B. Incorrectly identified as a Scoping Solution.
- C. Supports one or more of the Spending Objectives.
- D. Will represent a benchmark for Value For Money throughout the appraisal process.
- E. Delivers against one or more of the critical success factors.
正解:C、E
質問 # 59
Answer the following questions about the actions taken when preparing the Economic Case within the Full Business Case (FBC).
Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response that supports your decision.
Since approval of the OBC, there has been an attractive bid for the Old Fire Station Headquarters site by a supermarket company.
The bid is 15% higher than the original amount that the site was valued at.
Should the FBC production be delayed while the ranking of the options in the OBC is reassessed?
- A. No, because the anticipated benefits will remain the same.
- B. Yes, because the FBC must be re-submitted for re-approval if the costs vary significantly.
- C. Yes, because the FBC should be based on accurate Economic Appraisals for all options.
- D. No, because the sale price of the site is an opportunity cost which is irrelevant to the Economic Appraisal.
正解:C
質問 # 60
Springbank School has been hugely oversubscribed so has decided to expand its further education unit. It is working formally with Battledown School to reduce course duplication and to potentially offer a greater range of education courses. The Governors from Springbank School feel that these scheduled changes need to be reflected in the Pittville project FBC, even though Springbank was not a shortlisted option.
Should the FBC be updated with the Springbank changes?
- A. No, because the FBC should NOT be updated for best and final offers.
- B. Yes, because the preferred way forward for the Pittville project must offer better Value For Money than the other options.
- C. No, because this new scheme should be considered in the next iteration of the programme business case.
- D. Yes, because the public sector comparator (PSC) should be updated.
正解:B
質問 # 61
Answer the following questions about the actions taken when preparing the Economic Case within the Full Business Case (FBC).
The Outline Business Case (OBC) was based on the following preferred way forward:
Decide whether the action taken represents an appropriate application of the Five Case Model for this project and select the response that supports your decision.
Since the OBC, the Government has established that students from the country do not have to pay university tuition fees. There has been a further 15% increase in interest for taking a Welsh language course at Pittville University.
Should the service scope and underlying assumptions be amended?
- A. No, because an increase in interest will NOT reduce the support for the preferred option from the Local Education Authority.
- B. Yes, because students are Pittville project stakeholders.
- C. No, because the underlying business need of falling 16-18-year-olds participation in education remains the same.
- D. Yes, because any changes to service requirements may require following-up throughout the whole case.
正解:D
質問 # 62
Which statement should be recorded under the Risk Management heading?
- A. The sports facilities at the new campus are to be hired out to external organizations and groups.
- B. A project management special advisor has been appointed from a consultancy specializing in the PRINCE2 methodology.
- C. Schools and universities affected by the Pittville project are to escalate any risks to the Project Manager.
- D. The redefinition of jobs is to be communicated to teaching unions before any communications with staff can be issued.
正解:C
質問 # 63
The Benefits Realization Framework section states:
1. It was identified in the OBC that existing schools and universities play a major role in the success or otherwise of the Pittville project. A strategy for Learning Provider engagement is to be prepared.
2. A senior manager within the Local Education Authority is ultimately responsible for benefits realization.
Which 2 statements apply to these entries?
- A. No change to entry 1, because the strategy for the realization of benefits should be revisited and re-affirmed within the FBC.
- B. Amend entry 1, because the strategy for the realization of benefits should be confirmed within the OBC.
- C. Delete entry 1, because schools and universities will be responsible for the delivery of the benefits.
- D. No change to entry 2, because this is appropriate to this section.
- E. Amend entry 2, because the project manager is responsible for benefits realization.
正解:A、C
質問 # 64
The Local Education Authority Director has agreed to be the Senior Responsible Owner. Therefore, they are ultimately responsible for the realization of benefits resulting from the Pittville project.
Should the responsibilities for the benefits realization arrangements be documented in the Economic Case?
- A. Yes, because changes to the benefits should be identified before the FBC Economic Appraisals.
- B. Yes, because the plan for the delivery of benefits should be documented within the benefits register and attached to the FBC.
- C. No, because the benefits realization arrangements are finalized in the Management Case.
- D. No, because the benefits realization takes place during the implementation and operational phases of the project.
正解:C
質問 # 65
Which 2 statements should be recorded under the Proposed key contractual clauses heading?
- A. The parties shall attempt to resolve any dispute through negotiations between senior executives of the parties, who have authority to settle the same.
- B. The new campus building is to be listed as an asset on the Local Education Authority balance sheet.
- C. The contract period for development of the new campus is three years.
- D. Staff at the new campus will automatically become employees of Pittville University with the same terms and conditions of employment.
- E. The return on the investment will repay the sum of the original investment over 10 years.
正解:A、D
質問 # 66
Which detail should be explained in the Financial Case?
- A. Type of contract used and key contractual issues.
- B. Allocation of risk negotiated between the organization and the preferred service provider.
- C. Underpinning method of payment for services and outputs.
- D. Written confirmation of funding arrangements for the deal from the
organization's commissioners.
正解:D
質問 # 67
The following has been recorded as a dependency: 'Rationalization of the 11-16-year-old education and training provision'.
Is this an appropriate application of the Five Case Model for this project?
- A. No, because the objective is to increase the rate of participation in education and training by at least 15%.
- B. No, because the Pittville project is planned to be delivered ahead of the rationalization of 11-16-year-old education and training provision.
- C. Yes, because the physical element of the favoured option must be implemented at the earliest opportunity.
- D. Yes, because there is currently a surplus of places for this group.
正解:B
質問 # 68
......
APMG-International Better-Business-Cases-Practitioner 認定試験の出題範囲:
| トピック | 出題範囲 |
|---|---|
| トピック 1 |
|
| トピック 2 |
|
| トピック 3 |
|
| トピック 4 |
|
今すぐ弊社のBetter Business Cases試験パッケージ使って試験準備してBetter-Business-Cases-Practitionerをパスせよ:https://www.jpntest.com/shiken/Better-Business-Cases-Practitioner-mondaishu
全幅的な更新されたトレーニング専門問題を使って2024年最新のBetter-Business-Cases-Practitioner試験問題集テスト合格:https://drive.google.com/open?id=125R_-Z7_2GC3Xo9DWAL8aYvjLfZo4Tsh