[2025年最新] 高合格率なC_TS412_2021日本語テストアンサーかつSAP C_TS412_2021日本語テストPDF [Q10-Q28]

Share

[2025年最新] 高合格率なC_TS412_2021日本語テストアンサーかつSAP C_TS412_2021日本語テストPDF

完璧C_TS412_2021日本語問題集試験問題と解答でパス保証されます

質問 # 10
アクティビティの最も早い日付と最も遅い日付はどのようにスケジュールされますか?

  • A. 最も早い日付は順方向にスケジュールされ、最も遅い日付は逆方向にスケジュールされます
  • B. 最も早い日付と最も遅い日付はフォワードスケジュールでスケジュールされます
  • C. 最も早い日付は逆順にスケジュールされ、最も遅い日付は最も早い日付をコピーしてスケジュールされます。
  • D. 最も早い日付は逆方向スケジュールでスケジュールされ、最も遅い日付は順方向スケジュールでスケジュールされます

正解:A

解説:
Forward scheduling is a method of scheduling activities from the start date of the project to the end date. Backward scheduling is a method of scheduling activities from the end date of the project to the start date. The earliest dates are determined by forward scheduling and the latest dates are determined by backward scheduling. This ensures that the activities are scheduled within the project duration and that any slack time is distributed evenly. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html


質問 # 11
ネットワーク活動にはどのような組織構造が必要ですか? 注: この質問には3つの正解があります

  • A. 営業組織
  • B. 運用上の懸念
  • C. 植物
  • D. 会社コード
  • E. 制御エリア

正解:C、D、E

解説:
Controlling area, plant, and company code are some of the organizational structures required for network activities. Controlling area is an organizational unit that represents a closed system for cost accounting purposes. Plant is an organizational unit that represents a location where materials are produced or services are provided. Company code is an organizational unit that represents an independent accounting entity with its own balance sheet and profit and loss statement. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 12
顧客はネットワークアクティビティの容量要件を分析する必要があります。どのレポートをお勧めしますか? 注: この質問には 2 つの正解があります。

  • A. リソースレポート
  • B. 構造情報システムレポート
  • C. 原価要素レポート
  • D. 階層レポート

正解:A、D

解説:
Resource reports and hierarchical reports are some of the possible reports that you can use to analyze the capacity requirements of your network activities. Resource reports display capacity requirements and availability for work centers or resources over a period of time. Hierarchical reports display capacity requirements and availability for work centers or resources in a hierarchical structure, such as plant, MRP controller, or work center group. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 13
プロジェクトでネットワークと外部アクティビティを使用しています。購買依頼が作成されました。次のビジネス トランザクションとドキュメントの順序は何ですか?

  • A. . 与信限度額の確認 -> 実施されたサービスの承認 -> ベンダーの選択 -> 購買発注の処理 -> 購買発注の監視 -> 商品の受領 -> 請求書の受領
  • B. 仕入先選択 -> 購買発注処理 -> 購買発注監視 -> 入庫
  • C. ベンダー選択 -> 発注書作成 -> サービス入力シート作成 -> サービス入力シート承認
  • D. 仕入先選択 -> 発注処理 -> 請求書受領 - 発注監視 -> 入庫

正解:C

解説:
The sequence for the following business transactions and documents for external activities in a project is vendor selection -> purchase order creation -> service entry sheet creation -> service entry sheet approval. Vendor selection is a process that involves choosing a suitable vendor for providing external services for a project activity. Purchase order creation is an action that involves creating a document that contains the details of the service request and sending it to the vendor. Service entry sheet creation is an action that involves creating a document that records the delivery of services from the vendor and posting actual costs to the project. Service entry sheet approval is an action that involves checking and confirming the accuracy of the service entry sheet before paying the vendor. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 14
新しい作業分解構造 (WBS 要素) の作成に関する次の記述のうち正しいものはどれですか。
注: この質問には 3 つの正解があります。

  • A. 新しいプロジェクトの WBS 要素を別のプロジェクト定義に割り当てることができます。
  • B. WBS 要素は、計画要素、アカウント割り当て要素、および請求要素として同時に使用できます。
  • C. WBS構造には複数のレベル1のWBS要素を含めることができます。
  • D. 新しい作業分解構造には最大 10 レベルを含める必要があります。
  • E. レベルごとに複数の WBS 要素を作成できます。

正解:A、B、E

解説:
You can create several WBS elements per level." According to SAP Help Portal2, "You can assign a WBS element of the new project to a different project definition." According to SAP Help Portal3, "WBS elements can be planning elements, account assignment elements, and billing elements at the same time." Reference: 123


質問 # 15
ネットワークとWBS要素を扱っています。次の記述のうちどれが当てはまりますか?

  • A. アクティビティをあるネットワークから別のネットワークに再割り当てできます
  • B. ネットワークヘッダーを複数のWBS要素に割り当てることができます
  • C. プロジェクトプロファイルでネットワークプロファイルを管理する必要があります
  • D. アクティビティのある WBS 要素に対して、運用区分勘定割当要素を有効化する必要があります。

正解:C

解説:
One of the statements that applies to working with networks and WBS elements is that you have to maintain a network profile in the project profile. A network profile is a parameter that defines the basic properties of a network, such as its order type, number range, and scheduling parameters. A project profile is a parameter that defines the basic properties of a project, such as its project type, number range, and budget profile. You have to assign a network profile to a project profile in order to create networks within a project. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 16
ネットワークを保存し、割り当てられた品目コンポーネントで有効化しました。ネットワークをリリースするとすぐに、「ビジネストランザクションを実行できません」というエラー メッセージが表示されます。このエラー メッセージの原因は何でしょうか。

  • A. 材料の入手先がありません
  • B. 材料コンポーネントの予約がありません
  • C. 材料コンポーネントの予算が不足しています
  • D. 材料コンポーネントをリリースするための承認がありません

正解:D

解説:
One possible reason for the error message "Business transaction cannot be carried out" when releasing a network is missing authorizations to release material components. Material components are materials that are required for executing a network activity. To release material components, you need to have the authorization object C_AFKO_ATY with the activity 02 (change) for the order type of the network. Reference: https://answers.sap.com/questions/7530952/the-business-transaction-cannot-be-carried-out-mes.html


質問 # 17
2 月 1 日に開始し、2 月 28 日に終了するアクティビティを計画しています。このアクティビティでは、スケジュールによって変更されない 2 月 10 日のマイルストーンを定義します。マイルストーンの定義にはどのような方法をお勧めしますか?

  • A. 期間として10日間を入力します
  • B. アクティビティの開始日から10日間のオフセットを入力します
  • C. 固定日として2月10日を入力
  • D. アクティビティの終了日から -18 日のオフセットを入力します。

正解:C

解説:
To define a milestone for February 10 that should not be changed through scheduling, you should enter February 10 as fixed date for the milestone. A fixed date is a date that remains unchanged during scheduling, regardless of any changes in the dates of preceding or succeeding activities or milestones. A fixed date can be entered manually or automatically derived from a constraint. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 18
WBS要素のシステムステータスが作成されました(CRTD)。このNBS要素に許可されているビジネスプロセスはどれですか

  • A. 発注書に対する商品受領
  • B. アクティビティの割り当て
  • C. 実際の値の計算
  • D. 発注書の作成

正解:D

解説:
One business process that is allowed for a WBS element with system status created (CRTD) is creation of purchase orders. The system status is a parameter that indicates which business transactions are allowed or not allowed for a project object, such as a WBS element or a network. The system status created (CRTD) means that a WBS element has been created but not yet released. A WBS element with system status created (CRTD) can be used for planning purposes only and cannot be used for execution purposes. However, one exception is that you can create purchase orders for external services or materials with reference to a WBS element with system status created (CRTD). This allows you to start procurement processes early in the project lifecycle. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 19
間接費率を WBS 要素に割り当てたい場合、WBS 要素に何を割り当てる必要がありますか?

  • A. 投資プロファイル
  • B. 決済ルール
  • C. 原価計算シート
  • D. 結果分析キー

正解:C

解説:
To allocate overhead rates to a WBS element, you must assign a costing sheet to the WBS element. A costing sheet is a tool that allows you to define and calculate overhead costs based on various criteria, such as plant, company code, material origin, or order type. You can assign a costing sheet to a WBS element in the Control Data tab of the WBS element master data. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html


質問 # 20
SAP プロジェクト システムと Microsoft の間でデータを交換したいのですが、どのインターフェイスを使用しますか?

  • A. Microsoft Project へのインターフェイスは利用できません。
  • B. インターフェースは必要ありません。オブジェクトリンクを使用してデータを交換できます。
  • C. EPS インターフェース (外部プロジェクト ソフトウェア)。
  • D. カタログ インターフェース。

正解:C

解説:
"The EPS interface enables you to exchange data between SAP Project System and Microsoft Project." Reference: 2


質問 # 21
収益と支払い
顧客は、各会社コードに対して最上位の請求要素とその下の追加請求要素 (por debajo) を持つ会社コード間プロジェクトを使用しています。内部的には正しく行われていますが、結果分析ではすべての値が最上位の請求要素にまとめられています。どのようにして結果を異なる会社コードに分割できるのでしょうか。

  • A. 各会社コードに応じてプロジェクトを異なるプロジェクトに分割します。
  • B. 結果分析を行う前に、WBS 要素を最も高い請求要素に決済します。
  • C. プロジェクト構造を会社の組織構造に合わせて変更します。
  • D. 定期的な結果分析のエキスパート モードでの評価方法のカスタマイズを適宜調整します。

正解:D

解説:
According to SAP Help Portal1, "You can use the expert mode to define valuation methods for periodic results analysis that are tailored to your specific requirements. You can use this mode to define valuation methods for cross-company-code projects." Reference: 1


質問 # 22
リソース
プロジェクトで外部タスクをどのように定義できますか。
注: この質問には 2 つの正解があります。

  • A. サービス マイルストーンを作成します。
  • B. ネットワーク内に外部アクティビティを作成します。
  • C. ネットワーク内にサービス アクティビティを作成します。
  • D. 外部処理の発注書をプロジェクト定義に割り当てます。

正解:B、C

解説:
"You can create external activities in a network to represent tasks that are performed by external service providers or vendors." According to SAP Press4, "You can create service activities in a network to represent tasks that are performed by internal service providers." Reference: 4


質問 # 23
ネットワークと保守オーダーを含む WBS プロジェクト構造を使用します。ネットワークと保守オーダーの両方をスケジュールします。
何を考慮する必要がありますか?

  • A. 保守オーダーはサブネットワークとして割り当てる必要があります。
  • B. 保守オーダーはネットワークと同じプラントに割り当てる必要があります。
  • C. 保守指示は WBS 要素に割り当てる必要があります。
  • D. 保守オーダーは、プロジェクト定義と同じ予算プロファイルに割り当てる必要があります。

正解:C

解説:
To schedule both the network and the maintenance orders, you have to consider that the maintenance orders must be assigned to WBS elements. This means that you have to link the maintenance orders to WBS elements in your project structure using assignment objects. This way, you can ensure that the dates of the maintenance orders are synchronized with the dates of the WBS elements and the network activities. You can also use overall network scheduling to schedule several networks and maintenance orders together. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1


質問 # 24
プロジェクト計画ボードに表示されるのは次のうちどれですか? 注: この質問には 2 つの正解があります。

  • A. 容量要件
  • B. アクティビティに割り当てられたメンテナンスオーダー
  • C. WBS要素に割り当てられた生産オーダー
  • D. プロジェクト関連の発注書

正解:A、B

解説:
The project planning board is a graphical tool that allows you to plan and monitor projects in a Gantt chart view. You can use the project planning board to display capacity requirements and maintenance orders that are related to project activities. You can also display other objects such as WBS elements, networks, activities, milestones, production orders, sales orders, purchase orders, and so on. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/1ad4b65334e6b54ce10000000a174cb4.html?locale=en-US&state=PRODUCTION&version=2020.002


質問 # 25
顧客はSAPプロジェクトシステムで要件グループ化を使用したいと考えています。品目の要件グループ化の前提条件は何ですか? 注: この質問には2つの正解があります

  • A. 正確なロットサイズの手順を使用する必要があります
  • B. MRPグループを割り当てる必要があります
  • C. 品目の調達タイプは内部調達である必要があります
  • D. 材料は販売注文またはプロジェクト在庫を許可する必要があります

正解:B、D

解説:
Requirements grouping of materials is a process that allows you to plan and procure materials jointly for several WBS elements within a project or across projects. To use requirements grouping of materials, the materials must allow sales order or project stock, which means they must have a special procurement type of E or Q in the material master. An MRP group must also be assigned to the materials, which defines the parameters for material requirements planning, such as lot size and planning strategy. Reference: https://help.sap.com/doc/78f5c353b677b44ce10000000a174cb4/700_SFIN20%20006/en-US/0814c353b677b44ce10000000a174cb4.html


質問 # 26
WBS 要素の計画収益と実際の収益について説明している記述はどれですか? 注: この質問には 2 つの正解があります。

  • A. 実際の収益は、WBS要素に割り当てられた請求計画を通じて投稿されます。
  • B. 計画収益にはWBS要素に割り当てられた販売注文が必要です
  • C. 計画収益は販売見積から転送できます
  • D. 実際の収益は、販売注文から作成された請求書を通じて投稿されます。

正解:B、D

解説:
Planned revenue and actual revenue are two types of revenue for WBS elements in SAP Project System. Planned revenue requires a sales order assigned to a WBS element, which means that the sales order item contains the data for revenue planning, such as quantity, price, and billing plan. Actual revenue is posted via a billing document created from a sales order, which means that the billing document records the delivery of goods or services to a customer and requests payment for them. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html


質問 # 27
カスタマイジングでクロスアプリケーションタイムシート (CATS) の項目選択を設定したいと考えています。どの影響項目を使用しますか?

  • A. プロジェクトプロファイル
  • B. データ入力プロファイル
  • C. ネットワークタイプ
  • D. ネットワークプロファイル

正解:B

解説:
To set up the field selection of the Cross-Application Time Sheet (CATS) in Customizing, you use the data entry profile as an influencing field. CATS is a tool that allows you to record working times and tasks for project activities. The data entry profile is a parameter that defines the layout and functions of the CATS user interface. You can use the data entry profile to determine which fields are displayed or hidden, mandatory or optional, modifiable or read-only, and so on. Reference: https://help.sap.com/doc/saphelp_scm700_ehp02/7.0.2/en-US/69/f3055130534338e10000000a154ce5/content.htm


質問 # 28
......