2026年最新のSMRP CMRP問題集と試験テストエンジン [Q17-Q32]

Share

2026年最新のJPNTest SMRP CMRP問題集と試験テストエンジン

SMRP CMRP問題集にはリアル試験問題解答

質問 # 17
Determining the optimal replacement time for spares (spare parts) with an unacceptable interval, needs to account for:

  • A. The interest charges for capital expenditures.
  • B. The depreciated value of the equipment.
  • C. The value of money changing over time.
  • D. The cost of borrowing versus interest lost on operating funds.

正解:C


質問 # 18
(%) = [Business Benefits ($) ÷ Training Cost ($)] × 100

  • A. Maintenance Training ROI Formula
  • B. Maintenance Training Cost
  • C. Maintenance training ROI
  • D. Corrective Maintenance Cost Formula

正解:A


質問 # 19
The number of units produced during a designated time period. → Availability Formula

  • A. True
  • B. False

正解:B


質問 # 20
This metric is the maintenance cost that is used to measure, trend and compare equipment conditions against known standards to detect, analyze and correct problems before they cause functional failures

  • A. Overall Equipment Effectiveness (OEE)
  • B. Condition Based Maintenance Cost
  • C. Systems Covered by Criticality Analysis
  • D. Maintenance Training Return on Investment (ROI)

正解:B


質問 # 21
When would a strategic plan for Maintenance and Reliability be most appropriately required?

  • A. Fixed costs need to be reduced by 20% within the next year.
  • B. Improved plant (facility) throughput is required to allow the business to commit to the requirements of a new customer.
  • C. The markets that the company operates in are changing on a weekly basis.
  • D. Planning and scheduling are not being property implemented at that plant (facility).

正解:B


質問 # 22
Design Phase

  • A. The biggest benefit of failure modes and effects analysis occurs during:
  • B. The inventory turnover ratio for MRO store should be:
  • C. The best method of measuring the reliability of an asset is by?
  • D. The 6th S in 6S (also called 5S plus) stands for safety. (T/F)

正解:A


質問 # 23
Surveys have shown that plants (facilities) with good planning and scheduling systems and good predictive and preventive programs have which ratios of maintenance tasks? (Does not include service to operations or capital projects or turnarounds)

  • A. 50% of all work is preventive and predictive. 80% of work is planned and scheduled at least one week before execution, 5% of all work is emergency
  • B. 30% of all work is preventive and predictive. 40% of work is planned and scheduled at least one week before execution, 20% of all work is emergency
  • C. 95% of all work is preventive and predictive. 90% of work is planned and scheduled at least one week before execution, 5% of all work is emergency
  • D. 25% of all work is preventive and predictive. 60% of work is planned and scheduled at least one week before execution, 15% of all work is emergency

正解:C


質問 # 24
A typical quantity produced as output. The output has acceptable quality and consistent means to quantify. Examples would include gallons, liters, pounds, kilograms or other standard units of measures. → Standard Units Produced

  • A. True
  • B. False

正解:A


質問 # 25
Less than 20%

  • A. What percentage of your assets should be ranked critical based on the risk to business?
  • B. The biggest benefit of failure modes and effects analysis occurs during:
  • C. Best practices would indicate that 90% or more of all maintenance work is planned.
    (T/F)
  • D. Total Maintenance Cost As a Percent of Replacement Asset Value (RAV)

正解:A


質問 # 26
Which list of elements below are the most important to be evaluated and coordinated during the planning phase of a major shutdown of your operating area (i.e. annual turnaround)?

  • A. Heavy lifting equipment availability, labor cost and availability, operations requested down-days
  • B. Historical turnaround maintenance days, operations desired work list, prior turnaround work lists
  • C. Condition and remaining life of critical equipment, value of production throughput, labor and materials availability and cost
  • D. Available turnaround budget, equipment condition, budgeted down-days

正解:B


質問 # 27
What is a high level metric used to evaluate the overall effectiveness of a Safety Program?

  • A. Number of job hazard analyses completed
  • B. First aid case frequency
  • C. Lost time injury frequency
  • D. Near miss report submissions

正解:C


質問 # 28
Aa = MTBM / (MTBM + MDTM) Where MTBM = Mean Time Between Maintenance And MDTM = Mean Downtime for Maintenance

  • A. Achieved Availability Formula
  • B. Corrective Maintenance Hours
  • C. Inherent Availability Formula
  • D. Achieved Availability

正解:A


質問 # 29
During design

  • A. Which of the following is not a primary objective for implementing a planning process?
  • B. The objective of RCM is to preserve functions. (T/F)
  • C. RCM provides best results when used during what phase?
  • D. Most of the maintenance costs become fixed at what phase?

正解:D


質問 # 30
Replacement Asset Value (RAV) of the assets being maintained at the plant divided by the craft-wage employee headcount

  • A. Ratio of Replacement Asset Value (RAV) to Craft-Wage Headcount
  • B. Mean Time to Failure (MTTF)
  • C. Systems Covered by Criticality Analysis
  • D. Maintenance Training Return on Investment (ROI)

正解:A


質問 # 31
Which of the following manufacturing improvement tools uses statistical process control techniques and design of experiments as a primary method?

  • A. Supply chain management
  • B. Six Sigma
  • C. Predictive maintenance
  • D. Root Cause Analysis

正解:B


質問 # 32
......

2026年最新のJPNTest CMRPのPDFで最近更新された問題です:https://www.jpntest.com/shiken/CMRP-mondaishu

CMRP試験には保証が付きます。更新されたのは192問があります:https://drive.google.com/open?id=1FBCqVS3vFXORKA0BTmNWyQGo4io3lJNC

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡