質問 # 133
You have an SAP production landscape that uses SAP HANA databases.
You configure a metric alert for the primary HANA server as shown in the following exhibit.

正解:
解説:
Explanation
Graphical user interface, text, application, email Description automatically generated
Box 1: No
The period is 15 minutes. Only alerts or emails will be sent.
Box 2: Yes
Box 3: Yes
質問 # 134
You have an on-premises SAP environment. Application servers run on SUSE Linux Enterprise Server (SLES) servers. Databases run on SLES servers that have Oracle installed.
You need to recommend a solution to migrate the environment to Azure. The solution must use currently deployed technologies whenever possible and support high availability.
What should you include in the recommendation? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:
解説:
Explanation:
質問 # 135
This question requires that you evaluate the underlined BOLD text to determine if it is correct.
You are planning for the administration of resources in Azure.
To meet the technical requirements, you must first implement Active Directory Federation Services (AD FS).
Instructions: Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
- A. No change is needed
- B. Azure AD join
- C. Azure AD Connect
- D. Enterprise State Roaming
正解:C
解説:
Explanation
AD connect, it's not mandatory to have AD FS, you can use Password HAsh Synch or Passthrough Authentication, but AD Connect is mandatory to synch you on-promises accounts to Azure AD References:
https://docs.microsoft.com/en-us/azure/active-directory/saas-apps/sap-hana-cloud-platform-identity-authenticatio
Topic 1, Contoso Ltd Case Study
Case Study
This is a case study. Case studies are not timed separately. You can use as much exam time as you would like to complete each case. However, there may be additional case studies and sections on this exam. You must manage your time to ensure that you are able to complete all questions included on this exam in the time provided.
To answer the questions included in a case study, you will need to reference information that is provided in the case study. Case studies might contain exhibits and other resources that provide more information about the scenario that is described in the case study. Each question is independent of the other questions in this case study.
At the end of this case study, a review screen will appear. This screen allows you to review your answers and to make changes before you move to the next section of the exam. After you begin a new section, you cannot return to this section.
To start the case study
To display the first question in this case study, click the button. Use the buttons in the left pane to explore the content of the case study before you answer the questions. Clicking these buttons displays information such as business requirements, existing environment, and problem statements. If the case study has an All Information tab, note that the information displayed is identical to the information displayed on the subsequent tabs. When you are ready to answer a question, click the button to return to the question.
Overview
Contoso, Ltd. is a manufacturing company that has 15,000 employees.
The company uses SAP for sales and manufacturing.
Contoso has sales offices in New York and London and manufacturing facilities in Boston and Seattle.
Existing Environment
Active Directory
The network contains an on-premises Active Directory domain named ad.contoso.com. User email addresses use a domain name of contoso.com.
SAP Environment
The current SAP environment contains the following components:
* SAP Solution Manager
* SAP ERP Central Component (SAP ECC)
* SAP Supply Chain Management (SAP SCM)
* SAP application servers that run Windows Server 2008 R2
* SAP HANA database servers that run SUSE Linux Enterprise Server 12 (SLES 12) Problem Statements Contoso identifies the following issues in its current environment:
* The SAP HANA environment lacks adequate resources.
* The Windows servers are nearing the end of support.
* The datacenters are at maximum capacity.
Requirements
Planned Changes
Contoso identifies the following planned changes:
* Deploy Azure Virtual WAN.
* Migrate the application servers to Windows Server 2016.
* Deploy ExpressRoute connections to all of the offices and manufacturing facilities.
* Deploy SAP landscapes to Azure for development, quality assurance, and production.
All resources for the production landscape will be in a resource group named SAPProduction.
Business goals
Contoso identifies the following business goals:
* Minimize costs whenever possible.
* Migrate SAP to Azure without causing downtime.
* Ensure that all SAP deployments to Azure are supported by SAP.
* Ensure that all the production databases can withstand the failure of an Azure region.
* Ensure that all the production application servers can restore daily backups from the last 21 days.
Technical Requirements
Contoso identifies the following technical requirements:
* Inspect all web queries.
* Deploy an SAP HANA cluster to two datacenters.
* Minimize the bandwidth used for database synchronization.
* Use Active Directory accounts to administer Azure resources.
* Ensure that each production application server has four 1-TB data disks.
* Ensure that an application server can be restored from a backup created during the last five days within
15 minutes.
* Implement an approval process to ensure that an SAP administrator is notified before another administrator attempts to make changes to the Azure virtual machines that host SAP.
It is estimated that during the migration, the bandwidth required between Azure and the New York office will be 1 Gbps. After the migration, a traffic burst of up to 3 Gbps will occur.
Proposed Backup Policy
An Azure administrator proposes the backup policy shown in the following exhibit.
Azure Resource Manager Template
An Azure administrator provides you with the Azure Resource Manager template that will be used to provision the production application servers.

質問 # 136
You are evaluating which migration method Litware can implement based on the current environment and the business goals.
Which migration method will cause the least amount of downtime?
- A. Use the Database migration Option (DMO) to migrate to SAP HANA and Azure During the same maintenance window.
- B. Migrate SAP to Azure, and then migrate SAP ECC to SAP Business Suite on HANA.
- C. Use Near-Zero Downtime (NZDT) to migrate to SAP HANA and Azure during the same maintenance window.
- D. Migrate SAP ECC to SAP Business Suite on HANA an the migrate SAP to Azure.
正解:A
解説:
Explanation
The SAP Database Migration Option (DMO) with System Move option of SUM, used as part of the migration allows customer the options to perform the migration in a single step, from source system on-premises, or to the target system residing in Microsoft Azure, minimizing overall downtime.
References:
https://blogs.sap.com/2017/10/05/your-sap-on-azure-part-2-dmo-with-system-move/
質問 # 137
You are planning the deployment of a three-tier SAP landscape on Azure that will use SAP HANA. The solution must meet the following requirements:
Network latency between SAP NetWeaver and HANA must be minimized.
An SAP production landscape on Azure must be supported.
Network performance must be validated regularly.
What should you include in the solution? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:
解説:
Reference:
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/sap-proximity-placement-scenarios
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/dbms_guide_general
https://techcommunity.microsoft.com/t5/running-sap-applications-on-the/sap-on-azure-general-update-march-2019/ba-p/377456
質問 # 138
You are evaluating the migration plan.
Licensing for which SAP product can be affected by changing the size of the virtual machines?
- A. SAP Solution Manager
- B. SAP SCM
- C. PI
- D. SAP ECC
正解:D
解説:
Explanation
Scenario: Increase the performance of SAP ECC applications by moving to SAP HANA.
References:
https://azure.microsoft.com/en-us/pricing/details/virtual-machines/rhel-sap-hana/
質問 # 139
You deploy SAP HANA by using SAP HANA on Azure (Large Instances).
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.
正解:
解説:
Reference:
http://www.deployazure.com/compute/virtual-machines/sap-azure-enhanced-monitoring-extension/
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/azure-monitor-overview
質問 # 140
You have an Azure alert rule and action group as shown in the following exhibit.
Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic.
NOTE: Each correct selection is worth one point.
正解:
解説:
Explanation
Graphical user interface, text, application Description automatically generated
Box 1: five minutes
Window Size is 5 minutes.
Box 2: admins action group will be emailed
The admins1 actiongroup will be executed.
Reference:
https://docs.microsoft.com/en-us/azure/azure-monitor/alerts/alerts-metric-overview
質問 # 141
You migrate SAP ERP Central Component (SAP ECC) production and non-production landscapes to Azure.
You are licensed for SAP Landscape Management (LaMa).
You need to refresh from the production landscape to the non-production landscape.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:
解説:
Explanation
Step 1: From the Azure portal, create a service principal
The Azure connector can use a Service Principal to authorize against Microsoft Azure. Follow these steps to create a Service Principal for SAP Landscape Management (LaMa).
Step 2: Add permissions to the service principal
The Service Principal does not have permissions to access your Azure resources by default. You need to give the Service Principal permissions to access them.
Step 3: From the Cloud Managers tab in LaMa, add an adapter
Create a new connector in SAP LaMa
Open the SAP LaMa website and navigate to Infrastructure. Go to tab Cloud Managers and click on Add.
Select the Microsoft Azure Cloud Adapter
Step 4: Install and configure LaMA on an SAP NetWeater instance
Provision a new adaptive SAP system
You can manually deploy a new virtual machine or use one of the Azure templates in the quickstart repository.
It contains templates for SAP NetWeaver ASCS, SAP NetWeaver application servers, and the database. You can also use these templates to provision new hosts as part of a system copy/clone etc.
Note: To support customers on their journey into a cloud model (hybrid or entirely public cloud), SAP and Microsoft partnered to create an adapter that integrates the SAP management capabilities of LaMa with the IaaS advantages of Microsoft Azure.
References:
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/lama-installation
https://docs.microsoft.com/en-us/learn/modules/maintain-azure-sap-workloads/2-set-up-remote-management
質問 # 142
HOTSPOT
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.
Hot Area:
正解:
解説:
Explanation:
Box 1: Yes
The SAP Azure Enhanced Monitoring Extension builds on top of the Azure Diagnostic extension, which stores its data in an Azure Storage account that you specify.
Box 2: Yes
The Set-AzVMAEMExtension cmdlet updates the configuration of a virtual machine to enable or update the support for monitoring for SAP systems that are installed on the virtual machine. The cmdlet installs the Azure Enhanced Monitoring (AEM) extension that collects the performance data and makes it discoverable for the SAP system.
The -OSType specifies the OS. Either Windows or Linux.
Box 3: Yes
Reference:
https://docs.microsoft.com/en-us/azure/azure-monitor/platform/diagnostics-extension-overview
https://docs.microsoft.com/en-us/powershell/module/az.compute/set-azvmaemextension
質問 # 143
You have an Azure Active Directory (Azure AD) tenant and an SAP Cloud Platform Identity Authentication Service tenant.
You need to ensure that users can use their Azure AD credentials to authenticate to SAP applications and services that trust the SAP Cloud Platform Identity Authentication Service tenant.
In which order should you perform the actions? To answer, move all actions from the list of actions to the answer area and arrange them in the correct order.
正解:
解説:
Explanation
Table Description automatically generated
Step 1: Create and configure an enterprise application in the Azure AD tentant To configure the integration of SAP Cloud Platform Identity Authentication into Azure AD, you need to add SAP Cloud Platform Identity Authentication from the gallery to your list of managed SaaS apps.
* Sign in to the Azure portal using either a work or school account, or a personal Microsoft account.
* On the left navigation pane, select the Azure Active Directory service.
* Navigate to Enterprise Applications and then select All Applications.
* To add new application, select New application.
* In the Add from the gallery section, type SAP Cloud Platform Identity Authentication in the search box.
* Select SAP Cloud Platform Identity Authentication from results panel and then add the app. Wait a few seconds while the app is added to your tenant.
Graphical user interface, text, application Description automatically generated
Step 2: Download the single sign-on (SSO) metadata from the Azure AD tenant.
Download single sign-on metadata from Azure Active Directory.
Step 3: Create and configure a corporate identity provider.
Create corporate identity provider.
Step 4: Download the SAP Cloud Platform Identity Authentication Service tenant metadata.
Download Identity Authentication service tenant metadata.
Step 5: Upload the SAP Cloud Platform Identity Authentication Service tenant metadata to Azure AD tenant.
Upload Identity Authentication service tenant metadata to Azure Active Directory.
You have already uploaded the metadata file from Azure Active Directory to Identity Authentication service.
It's time to do it the other way round now and upload the metadata of Identity Authentication service to Azure Active Directory.
Reference:
https://developers.sap.com/tutorials/cp-ias-azure-ad.html
質問 # 144
You plan to migrate an SAP environment to Azure.
You need to create a design to facilitate end-user access to SAP applications over the Internet, while restricting user access to the virtual machines of the SAP application servers.
What should you include in the design?
- A. Configure a public IP address for each SAP application server
- B. Configure point-to-site VPN connections for each user
- C. Deploy an internal Azure Standard Load Balancer for incoming connections
- D. Use an SAP Web Dispatcher to route all incoming connections
正解:D
解説:
Explanation
* A public internet user can reach the SAP Web-Dispatcher over port 443
* The SAP Web-Dispatcher can reach the SAP Application server over port 443
* The App Subnet accepts traffic on port 443 from 10.0.0.0/24
* The SAP Application server sends traffic on port 30015 to the SAP DB server
* The DB subnet accepts traffic on port 30015 from 10.0.1.0/24.
* Public Internet Access is blocked on both App Subnet and DB Subnet.
References:
https://azure.microsoft.com/en-in/blog/sap-on-azure-architecture-designing-for-security/
質問 # 145
You have an SAP development landscape on Azure.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.
正解:
解説:
質問 # 146
You are implementing a highly available deployment of SAP HANA on Azure virtual machines. You need to ensure that the deployment meets the following requirements:
* Supports host auto-failover
* Minimizes cost
How should you configure the highly available components of the deployment? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:
解説:
see the explanation for below image:
Explanation
Answer selected as in image below.
質問 # 147
This question requires that you evaluate the underlined text to determine if it is correct.
When deploying SAP HANA to an Azure virtual machine, you can enable Write Accelerator to reduce the latency between the SAP application servers and the database layer.
Instructions: Review the underlined text. If it makes the statement correct, select "No change is needed". If the statement is incorrect, select the answer choice that makes the statement correct.
- A. No change is needed
- B. start the NIPING service
- C. enable Accelerated Networking
- D. install the Mellanox driver
正解:C
解説:
To further reduce network latency between Azure VMs, we [Microsoft] recommend that you choose Azure Accelerated Networking. Use it when you deploy Azure VMs for an SAP workload, especially for the SAP application layer and the SAP DBMS layer.
Incorrect Answers:
A: Write Accelerator is a disk capability for M-Series Virtual Machines (VMs) on Premium Storage with Azure Managed Disks exclusively. As the name states, the purpose of the functionality is to improve the I/O latency of writes against Azure Premium Storage.
B: Mellanox offers a robust and full set of protocol software and driver for Linux with the ConnectX EN family cards. Designed to provide a high performance support for Enhanced Ethernet with fabric consolidation over TCP/IP based LAN applications. The driver and software in conjunction with the Industry's leading ConnectX family of cards achieve full line rate, full duplex of up to 100Gbps performance per port.
C: To analyze network issue or measure network metrics you can test the connection using SAP's NIPING program. You can use NIPING to analyze the network connection between any two machines running SAP software.
References:
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/dbms_guide_general
質問 # 148
Your on-premises network contains an Active Directory domain.
You are deploying a new SAP environment on Azure.
You need to configure SAP Single Sign-On to ensure that users can authenticate lo SAP GUI and SAP WebGUI.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
正解:
解説:
質問 # 149
You have an SAP environment that contains the following components:
* Enhancement Package 6 for SAP ERP Central Component 6.0 (SAP ECC 6.0)
* Servers that runs SUSE Linux Enterprise Server 12 (SIES 12)
* Databases on IBM D82 10.5
* SAP Solution Manager 7.1
You plan to migrate the SAP environment to Azure.
For each of the following statements, select Yes if the statement is true. Otherwise, select No.
NOTE: Each correct selection is worth one point.
正解:
解説:
Explanation:
Box 1: Yes
Box 2: No
Upgrade to ECC 7.01 or later.
Box 3: No
With Microsoft Azure, you can migrate your existing SAP application running on IBM Db2 for Linux, UNIX, and Windows (LUW) to Azure virtual machines. With SAP on IBM Db2 for LUW, administrators and developers can still use the same development and administration tools, which are available on-premises.
Reference:
https://docs.microsoft.com/en-us/azure/data-factory/connector-sap-table
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/dbms_guide_ibm
質問 # 150
You plan to implement a highly available, three-tier deployment of an SAP NetWeaver landscape on Azure.
The landscape will use SUSE Linux Enterprise Server (SLES).
You need to implement the SAP NetWeaver central services (ASCS/SCS) tier.
What should you do? To answer, select the appropriate options in the answer area.
NOTE Each correct selection is worth one point.
正解:
解説:
Explanation
質問 # 151
You plan to deploy an SAP environment on Azure that will use Azure Availability Zones.
Which load balancing solution supports the deployment?
- A. Azure Application Gateway v1 SKU
- B. Azure Standard Load Balancer
- C. Azure Basic Load Balancer
正解:B
解説:
When you deploy Azure VMs across Availability Zones and establish failover solutions within the same Azure region, some restrictions apply:
You can't use an Azure Basic Load Balancer to create failover cluster solutions based on Windows Server Failover Clustering or Linux Pacemaker. Instead, you need to use the Azure Standard Load Balancer SKU.
Reference:
https://docs.microsoft.com/en-us/azure/virtual-machines/workloads/sap/sap-ha-availability-zones
質問 # 152
A company named Contoso, Ltd. has users across the globe. Contoso is evaluating whether to migrate SAP to Azure.
The SAP environment runs on SUSE Linux Enterprise Server (SLES) servers and SAP HANA databases. The Suite on HANA database is 4 TB.
You need to recommend a migration solution to migrate SAP application servers and the SAP HANA databases. The solution must minimize downtime.
Which migration solutions should you recommend? To answer, select the appropriate options in the answer area.
NOTE: Each correct selection is worth one point.
正解:
解説:
Explanation:
Box 1: Azure Site Recovery
Microsoft Azure Site Recovery (ASR) now supports SUSE Linux Enterprise Server 11 SP3/SP4 and SUSE Linux Enterprise Server 12 SP1/SP2/SP3. This is great for customers that are planning to migrate systems to Microsoft Azure or customers who need to have a business continuity strategy for their Azure deployments.
Azure Site Recovery enables SUSE customers to migrate their non-Azure virtual machines or physical servers to Microsoft Azure virtual machines.
Box 2: System Copy for SAP Systems
In order to migrate an existing SAP HANA system into Azure, a SAP homogeneous system copy can be performed.
Reference:
https://www.suse.com/c/asr_supports_suse/
https://www.netapp.com/us/media/tr-4746.pdf
質問 # 153
......
Microsoft AZ-120認定試験は、SAPワークロードのMicrosoft Azureの計画と管理の知識とスキルを強化したいITプロフェッショナルにとって素晴らしい機会です。この認定は、専門家が業界で認識を得るのに役立つだけでなく、AzureのSAPワークロードを効果的に管理するために必要なスキルを提供します。
この試験は、SAPワークロード、Azure Administration、および一般的なクラウドコンピューティングの概念の経験がある専門家向けに設計されています。 SAPワークロードのAzureインフラストラクチャの計画と展開、Azure仮想マシンの構成、AzureのSAPワークロードの監視と最適化、SAPワークロードの災害復旧の実装など、幅広いトピックをカバーしています。
最新AZ-120試験問題にはリアルなAZ-120問題集があります:https://www.jpntest.com/shiken/AZ-120-mondaishu
最新AZ-120認証有効な試験問題集解答を試そう!:https://drive.google.com/open?id=1gAOuHHTHRVLpU9LJ5ntuYSOY_37XaJWG