質問 # 45
Which functionality is available in Focused Build?
- A. Integration Monitoring
- B. Test Management
- C. User Experience Monitoring
- D. Custom Code Management
正解:B
解説:
B is correct because Focused Build provides a test management feature that supports the planning, execution, and reporting of test activities in SAP projects. It allows the creation and assignment of test cases, test packages, and test plans, as well as the tracking and monitoring of test results and defects. Verified :
: Focused Build for SAP Solution Manager
質問 # 46
When deploying a new implementation on-premise, which of the following is recommended when performing custom development?
- A. SAP Business Technology Platform
- B. SAP Best Practices
- C. SAP ABAP Workbench
- D. SAP API Business Hub
正解:C
質問 # 47
What criteria does the product owner use to sequence the backlog?Note: There are 2 correct answers to this question.
- A. Business priority
- B. Release planning schedule
- C. Technical dependencies
- D. Complexity of the story
正解:A、C
解説:
A is correct because technical dependencies are one of the criteria that the product owner uses to sequence the backlog. Technical dependencies are the relationships between user stories that affect their order of implementation. For example, some user stories may require other user stories to be completed first, or some user stories may have a common prerequisite or constraint.
C is correct because business priority are one of the criteria that the product owner uses to sequence the backlog. Business priority is the measure of how important and valuable a user story is for the customer and the stakeholders. The product owner decides which user stories are more urgent and beneficial, and places them higher in the backlog. Verified :
: Product Backlog
質問 # 48
Which value chains does SAP solution manager 7.2 deliver?
There are 3 correct answers to this question.
- A. Request-to-fulfil
- B. Requirements-to-deploy
- C. Hire-to-retire
- D. Detect-to-correct
- E. Cash-to-order
正解:A、B、D
質問 # 49
How do you set up Scrum teams?Note: There are 2 correct answers to this question.
- A. By type of work, like configuration Scrum, documentation Scrum, and testing Scrum
- B. Based on end-to-end processes like order-to-cash
- C. As a cross-functional team covering multiple functions, like configuration, data loads, and v u testing
- D. Based on group size, but a minimum of 12 people
正解:B、C
解説:
A is correct because based on end-to-end processes like order-to-cash is one of the ways to set up Scrum teams. This way, the Scrum teams are organized around the business value streams that they support, and they have a clear understanding of the customer needs and expectations. This also helps to reduce dependencies and handovers between teams, and to optimize the flow of work.
C is correct because as a cross-functional team covering multiple functions, like configuration, data loads, and testing is one of the ways to set up Scrum teams. This way, the Scrum teams have all the skills and competencies that they need to deliver a complete and working product increment in each Sprint. This also helps to increase collaboration and communication within the team, and to foster a sense of ownership and accountability.
質問 # 50
What solution operation framework can customers use to create a joint business and IT organisation that will secure transparency and efficiency of SAP implementation.
- A. SAP Activate
- B. Business transformation management methodology
- C. SAP operations control centre
- D. Customer centre of expertise
正解:C
質問 # 51
Which of the following is a key characteristic of the Agile project approach?
- A. Iterative build with frequent inspections
- B. Frequent and detailed project scheduling
- C. Frequent quality gates
- D. Formal and detailed documentation
正解:A
解説:
C is correct because Iterative build with frequent inspections is a key characteristic of the Agile project approach. The Agile project approach follows an iterative and incremental development process, where the solution is built and delivered in small increments called sprints. Each sprint consists of planning, designing, building, testing, and reviewing activities, where the team inspects the solution and adapts to changing requirements and feedback. Verified :
質問 # 52
What are the responsibilities of the product owner in release and sprint planning?
NOTE: There are 2 correct answers to this question.
- A. Analyse the functional and technical dependencies between user stories
- B. Estimate the backing user stories
- C. Define objectives for each release
- D. Prioritize backing user stories by business priority
正解:C、D
質問 # 53
When performing an SAP Readiness Check in system conversion, what areas are covered within the result?Note: There are 3 correct answers to this question
- A. SAP and third party interfaces
- B. Sizing for SAP S/4HANA
- C. Recommended SAP Fiori apps
- D. Active business functions
- E. Simplification database
正解:B、C、E
解説:
A is correct because SAP Readiness Check in system conversion covers the area of recommended SAP Fiori apps, which are apps that are suggested by SAP based on the customer's current usage of SAP GUI transactions.
C is correct because SAP Readiness Check in system conversion covers the area of sizing for SAP S/4HANA, which is an estimation of the hardware and software resources required to run SAP S/4HANA based on the customer's current system data.
E is correct because SAP Readiness Check in system conversion covers the area of simplification database, which is a collection of simplification items that describe the changes and adaptations required for SAP S/4HANA compared to the previous SAP ERP releases. Verified :
質問 # 54
What are the responsibilities of the product owner in release and sprint planning? Note: There are 2 correct answers to this question
- A. Estimate the backlog user stories.
- B. Prioritize backlog user stories by business priority.
- C. Analyze the functional and technical dependencies between user stories.
- D. Define objectives for each release
正解:B、D
質問 # 55
What can you find in the SAP Fiori apps reference library? Note: There are 3 correct answers to this question.
- A. Related app-specific SAP Fiori design guidelines
- B. Shortcut to the Maintenance Planner tool to establish the technical update path
- C. Installation and configuration requirements for selected apps
- D. Related app recommendations based on your usage profile
- E. Shortcut to the Quicksizer tool to estimate hardware requirements
正解:A、C、D
質問 # 56
When working with an Agile approach, what is the minimum planning requirement expected at the beginning of the Realize phase?
- A. Release plan and sprint ceremony guidelines should be finalized.
- B. Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
- C. Realize phase scope, planning, and budget should be completed and final.
- D. User stories on product backlog should be in ready state for the first 2 to 3 sprints.
正解:B
解説:
C is correct because in an Agile approach, the planning is done iteratively and incrementally, so the minimum requirement at the beginning of the Realize phase is to have sprint planning and sprint durations defined for the first 2 to 3 sprints. Verified :
質問 # 57
How do you achieve frequent checkpoints with the end user in an Agile delivery approach?
There are 2 correct answers to this question.
- A. User acceptance test
- B. Solution review for waves
- C. Demo the SAP model company
- D. Solution demo for sprints
正解:B、D
質問 # 58
Which of the following belong to the application design and configuration workstream for SAP S/4HANA cloud in the explore phase?
There are 2 correct answers to this question
- A. Kick-off workshop
- B. Integration prerequisites confirmation
- C. Configuration definition
- D. Fit-to-standard workshop
正解:C、D
質問 # 59
Which system tenants are the first to be provisioned when implementing SAP S/4HANA Cloud, public edition?
- A. SAP S/4HANA starter system
- B. SAP S/4HANA sandbox system
- C. Central Business Configuration System
- D. SAP Cloud Identity Services
正解:A
質問 # 60
......