試験ISO-22301-Lead-Implementer トピック2 問題20 スレッド

PECB ISO-22301-Lead-Implementerのリアル試験問題集
問題 #: 20
トピック #: 2
Scenario:
Prebank is a multinational financial institution. Its services include banking and investing through banking centers, ATMs, and mobile banking platforms. With millions of clients, Prebank's database systems record vast amounts of data and transactions daily. Its main activities depend on the ability of its employees to access clients' data through its database system at any time.
Recently, Prebank's database system stopped working unexpectedly. Soon after, it was discovered that this disruption was caused by the maintenance work on the road outside the company's office building. During the road repair, the workers had unintentionally damaged a water pipe that leaked into Prebank's basement. This leakage affected the company's electrical infrastructure, resulting in a loss of power, which shut down equipment and computers in the server room. Consequently, employees were unable to access Prebank's database system.
After this incident, the employees immediately notified Prebank's IT team. Subsequently, the IT team informed both the maintenance company responsible for the roadworks and the insurance company. The company responsible for maintenance told Prebank's IT team that the maintenanceteam was not available for the day. Since Prebank did not have a plan for responding to similar disruptions, they had to stop working and go home. Thankfully, the maintenance team arrived at the scene on the next day and made all the necessary repairs, allowing Prebank to resume all its operations.
Following these events, Prebank decided to change its strategy and procedures to prioritize business continuity planning within the company. Its main focus was to address the root cause of disruptions to improve business continuity. As such, the top management decided to implement a Business Continuity Management System (BCMS) based on ISO 22301.
After setting the company's business continuity objectives, the company established a project team, including a project manager and four additional team members. The BCM team was responsible for managing the BCMS implementation process, whereas the top management was responsible for the effectiveness of the BCMS. Through analyzing potential risk scenarios, the team defined Prebank's business continuity strategy as well as the resources for supporting business continuity within the company. This enabled the team to predict the impact of disruptions caused by various incidents, such as power outages. Following these actions, the company established a business continuity plan to manage disruptions effectively without impacting the workflow.
The effective implementation of the BCMS helped Prebank not only minimize losses and ensure continuity in its services but also absorb and adapt to a changing environment.
As stated in Scenario 1, Prebank's IT team was not briefed on how to handle a power outage. What does this indicate?

おすすめの解答:A 解答を投票する

Context of Prebank's Situation:The scenario describes a critical service disruption due to a power outage caused by external factors, coupled with the inability of the IT team to respond effectively. This reflects a fundamental gap in preparedness and response mechanisms.
Requirement for a Business Continuity Plan (BCP):According to ISO 22301:2019, clause 8.4.4 mandates that organizations must establish, implement, and maintain documentedBusiness Continuity Plans (BCPs).
These plans should outline responses to various disruptions, including system outages, infrastructure damage, and external incidents.
Evidence of Non-Conformance:
* The IT team was unprepared to manage the incident, highlighting an absence of predefined procedures or training on handling power outages.
* No contingency plans were in place to maintain critical operations during the outage.
* The lack of immediate recovery or fallback measures indicates the absence of a robust BCP, as stipulated inISO 22301:2019 Clause 8.4.3.
Violation of BCMS Framework Requirements:A comprehensive BCMS includes Business Impact Analysis (BIA) and Risk Assessments (RA) to anticipate disruptions and plan appropriate strategies (Clauses 8.2.2 and
8.3). Prebank's lack of a prepared response indicates these components were either inadequate or missing.
Clarification of Incorrect Options:
* Option B (Violation of business continuity principles): While principles may have been overlooked, the root issue is the non-existence of a documented and actionable BCP, which is a core deliverable under ISO 22301.
* Option C (Inadequate segregation of duties): There is no evidence in the scenario to suggest a failure related to duties allocation or role responsibilities.
Action Plan for Compliance:
* Immediate: Establish a documented BCP addressing power outages, including clear roles, fallback solutions, and communication protocols.
* Training and Awareness: Train IT staff on incident management and ensure alignment with BCP objectives (Clause 7.3).
* Ongoing Improvement: Use management reviews (Clause 9.3) and audits (Clause 9.2) to evaluate the BCMS and incorporate lessons learned from this incident.

Midorikawa 2025-06-27 09:35:29

コメント

正解:
?」こちらは投票コメントになっております。普通のコメントに切り替えます。
ニックネーム: 送信 キャンセル
投票コメントをあげるごとに、選択した解答の投票数を1つ増やすことができます。

他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡