Which of the following characteristics are a requirement of a compliant water meter?
おすすめの解答:B 解答を投票する
Explanation
A compliant water meter is a device that measures and records the total potable water use of the building and associated grounds. According to the LEED v4 Reference Guide for Building Design and Construction, a compliant water meter must meet the following requirements1:
*It must be permanently installed and measure the total water use of the building and grounds.
*It must have a remote communication capability or be readable from a location that is accessible to building management.
*It must have a data storage capability of at least 18 months, or be connected to a system that can store data for at least 18 months.
*It must have a resolution of 0.5 gallons (2 liters) or less, or the smallest unit of measure that is appropriate for the expected water use of the building.
References:
*LEED v4 Reference Guide for Building Design and Construction, Water Efficiency Prerequisite:
Building-Level Water Metering, page 3781
*Water metering | U.S. Green Building Council
A compliant water meter is a device that measures and records the total potable water use of the building and associated grounds. According to the LEED v4 Reference Guide for Building Design and Construction, a compliant water meter must meet the following requirements1:
*It must be permanently installed and measure the total water use of the building and grounds.
*It must have a remote communication capability or be readable from a location that is accessible to building management.
*It must have a data storage capability of at least 18 months, or be connected to a system that can store data for at least 18 months.
*It must have a resolution of 0.5 gallons (2 liters) or less, or the smallest unit of measure that is appropriate for the expected water use of the building.
References:
*LEED v4 Reference Guide for Building Design and Construction, Water Efficiency Prerequisite:
Building-Level Water Metering, page 3781
*Water metering | U.S. Green Building Council
Toyama 2024-02-11 01:14:52
コメント
他人の解答コメントを賛成するのも、その解答に一票を入れることになります。したがって、すでに同じ意見の投票コメントが存在する場合、新規コメントをする代わりに賛成することもできます。
コメントを通報する
コメント中
今すぐ 新規登録 / ログイン (無料です)。