PRINCE2 無料問題集「PRINCE2 Foundation」
What factors need to be taken into consideration when identifying the number of management stages required?
1.Where key decisions points need to be
2.The amount of risk within the project
3.The number of technical stages
4.How confident the Project Board and Project Manager are with proceeding
1.Where key decisions points need to be
2.The amount of risk within the project
3.The number of technical stages
4.How confident the Project Board and Project Manager are with proceeding
正解:D
解答を投票する
The PRINCE2 principle 'continued business justification' states that a requirement for a project is that... There is justifiable reason to start the project and justification should remain valid throughout the life of the project. Which one of the following does PRINCE2 also state for this principle?
正解:A
解答を投票する