Which of the following are uses of the Risk Register during the Controlling a Stage process?
1.Obtain details on risks to include in a Highlight Report
2.Obtain details of risks that may affect the Stage Plan for the next stage
3.Capture uncertainties identified when authorizing a Work Package
4.Obtain details of any potential impacts that may affect the Business Case while reviewing the stage status
1.Obtain details on risks to include in a Highlight Report
2.Obtain details of risks that may affect the Stage Plan for the next stage
3.Capture uncertainties identified when authorizing a Work Package
4.Obtain details of any potential impacts that may affect the Business Case while reviewing the stage status