L4M8 無料問題集「CIPS Procurement and Supply in Practice」

Describe a situation where amendment or an addendum would need to be created
正解:
After all the due diligence is carried out, before awarding contract to the best supplier, sometimes procurement professionals find themselves in some problem solving situation; this might have been emanated from supplier facing a financial challenge or problems from external environment. Responding to this might require an amendment or an addendum, depending on the case in hand.
An amendment is for a physical change in the existing contract for example; if a contract contains a negotiated and agreed fixed price for the period of the contract but unexpected market forces such as an economic down turn or force majeure occur, the supplier may have to request an amendment order to continue to make a profit.
An addendum is when an additional document is added to the existing contract for example, If a contract have a schedule of rates and the market forces prices up, an addendum can be added to an existing contract with a revised schedule. Once accepted, the addendum becomes part of the con-tract. Addendum are physically used when the forecasted cost of a project rises and approval is needed to increase the contract spend.
What are the four stages of decommissioning?
正解:
When a fixed asset reaches the end of its life, it requires decommissioning before reconditioning or disposal.
Decommissioning is to observe all the safety measures and technical procedures and stop active machinery or an asset from operation (example gas plan, generator, transformer etc.
Decommissioning process include the following aspect
1) Preparation: Plan the process
2) Dismantle: Take the asset apart and remove hazardous waste
3) Processing: make safe any hazardous waste
4) Disposal: Ensure paper work is received to confirm removal and disposal
What are the reasons that a contract can legally be terminated?
正解:
A contract is written or verbal agreement, made between two or more parties that are legally en-forceable. For a contract to be legally binding it must include intention of parties entering into the contracts. All parties must have the capacity to contract or be contracted. They must be of a sound mind, there should be a promise (offer) for performance from the other party and an exchange (consideration) of one thing for another within an agreement for contract to be binding, there must be an acceptance of the offeror's offer by the offeree.
There are many reasons contract can legally be terminated, including non-performance by one or both parties, a significant change in the requirement.
There are several reasons contract can legally be terminated, including non-performance by one or both parties; breach of material, failure to meet service level agreement, ethical breaches, a significant change in the requirement of either party caused by ethical change in the market, change in Demand, obsolescence, contract completion. The procurement professionals should get an exit strategy that should encourage a stress free disengagement should incase there are no profitable reason to continue with the contract.
Describe four factors that could damage reputation within the supply chair
正解:
The reputation of all the organizations within a supply chain is linked. A Company's reputation is an intangible asset that can contribute to the failure of an organization if damaged. Factors that could damage organizational reputation within the supply chain are;
1. Quality: if the product or service quality is poor the organization may not satisfy it customers and this can lead to a loss of reputation in the market. For example, a residential building construction company contracting a supplier that would do a bad job which in three months may require home owners to reinstall new doors.
2. Sustainability: if the organization is not replenishing that which it is extracting, it will some day run out of business or probably loss loyal customers. For example a drilling company that spills hydrocarbon as it drills.
3. Fit for purpose: if an organization produce a product or carry out services that are not fit for purpose, it may run at loss for there will be so much rejection and rework. This can lead to customers switching to another organization which product or services are fit for their purpose.
4. Contract management: an organization will have to manage its suppliers and the contracts to ensure they are delivering what they were contracted to do. A poor contract management is a waste in the process of delivery that can lead to reputational loss.
What are the four quadrants in the Mendelow stakeholder matrix?
正解:
Stakeholder are individuals or organizations that can be affected directly or indirectly by any project or decision. For successful procurement activities to take place, stakeholders must be identified, engaged and managed. Not all stakeholders require the same level of engagement and management. To appropriately manage identified stakeholders, the Mendelow management matrix has categorized stakeholders in four quadrants, according to how low or high their power and interest in the project could be. The four categories are:
1) Minimum effort (low power-Low interest)
2) Keep satisfied (high power-Low interest)
3) Keep informed (Low power - high interest)
4) Manage closely (High power- High interest)
What matrix helps to define how to manage stakeholders?
正解:
Stakeholders are individuals or organizations who are directly affected by a decision for example, community, shareholders, employees, suppliers, distributors, customers etc. stakeholders can be internal (employers, staffs), connected (such as suppliers, shareholders, financers and customers) external (Government, pressure groups, and community).
The matrix that helps define how to manage stakeholders is mendelow's stakeholders manage-ment matrix. This matrix is based on the theory that the level of management stakeholders require depends on the level of their power and interest within the project or organization The matrix groups stakeholders in to four quadrants according to their power and interest and ad-vice how to manage them.
1) Low power - Low interest (minimum effort)
2) Low power - High interest (keep inform)
3) High power - Low interest (keep satisfied)
4) High power - high interest (manage closely)
Describe three types of fraud that could occur within the supply chain of an organization with which you are familiar.
正解:
Fraud occurs when a person acts deliberately to secure monies from another party through dishonest method. Within the supply chain of an organization, fraud can represent itself in the following ways:
1. Kickbacks: e.g. (commission given to a bribe taker for service perform)
2. Corrupt influence (e.g ordering more than what is required)
3. Collusion: (group of suppliers working together to submit multiple bids and split profit.
4. Bid Rigging (a contract is informally agreed with a chosen supplier prior to the official process
5. invoicing fraud
6. Substitution (submitting products that are below the required quality
7. False claims (files false document)
Case Study
A series of news stories reporting events such as the collapse of the Rana Plaza building in 2013 have drawn attention to the poor conditions in garment factories across India and South East Asi a. Human rights groups have long be critical of the excessive hours and poor wages workers are forced to endure, as well as the abuse they receive from supervisor. With consumers becoming increasingly aware of these conditions, more pressure is being put on global brands and retailers to ensure their supply chains are fair and ethical.
Certain areas have been notorious for the mistreatment of workers. In India's textile valley', young women are been bound into contracts where they work for two to three years, in exchange for a lump sum of money that they can then put towards a dowry. This is known as the 'Sumangali [a married woman] Thittam' scheme. These women are forced to live in hostels under restrictions that prevent them from moving, and are denied the opportunity to improve their living conditions. Retailers including Walmart and H&M are known to source garments from factories in the 'textile valley'.
Reports by organizations including the Asia Floor Wage Alliance (AFWA), Central Combodia, Global Labor Justice, Sedane Labour Resource Centre (LIPS) Indonesia, and Society for Labour and Development (SLD) India have exposed unethically run factories that supply garments to H&M, Gap and Walmart. However, retailers will continue to benefit from expensive labour until mounting customers pressure causes them to change.
Which four procurement cycle stages happen after the award of the contract?
正解:
The procurement cycle is the heart of purchasing, sourcing and supplying and should be followed in day-to-day practice in the industry. The procurement cycle has thirteen stages. Contract award is stage 9, and the stages after the contract award are; Stage 10: ware house, logistic and receipt Stage 11: Contract performance review and continuous improvement Stage 12: SRM/SCM and contract management Stage 13: Asset management, lessons learned, end of life.
The supplier is responsible for delivering the goods to a named port or destination (such as an air-port or warehouse), as well as unloading them from the terminal from this point, risk passes to the buyer.

Think of a supply chain with which you are familiar and distinguish between the primary, second-ary and tertiary sector organization within it.
正解:
Supply chain involves a network of individuals, organizations, technology activities and resources to make sure goods or services flow along the chain. If one point fails, every part further along the chain fails.
Fullpower projects (a flour manufacturer) supply chain begins with producers (raw materials, wheat farmers), suppliers, manufactures, distributors, retailers and end users (customer).
Fullpower projects supply chain falls within the primary sector (producers of wheat), the secondary sector include the manufacturing (those that converts the wheat the suppliers brings into flour) and tertiary sector (the distributor those that takes the wheat to the end users).

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡