Which three statements are true regarding simulation in Oracle Supply Planning Cloud?
- A. It is mandatory to associate simulation set in plan option while creating a supplyplan.
- B. A user can add data to simulation set from plan inputs and from a supply plan.
- C. A user can use one simulation set in multiple plans.
- D. Simulation sets are predefined.
- E. A user can use the same simulation set multiple times while editing the data in it.
正解:B、C、E
解説:
According to the Oracle Supply Planning Cloud User Guide1, simulation sets are used to create and compare different scenarios in a supply plan. A user can use one simulation set in multiple plans (A), use the same simulation set multiple times while editing the data in it ©, and add data to simulation set from plan inputs and from a supply plan (D). Simulation sets are not predefined (B), and it is not mandatory to associate simulation set in plan option while creating a supply plan (E).
質問 # 15
Which Cloud Application is NOT involved in back-to-back fulfillment of a make item in a sales order?
- A. Supply Chain Orchestration
- B. Manufacturing
- C. Purchasing
- D. Inventory
正解:C
解説:
According to the Oracle Supply Chain Management Cloud: Order to Cash training course3, back-to-back fulfillment of a make item in a sales order involves four Cloud Applications: Order Management, Supply Chain Orchestration, Manufacturing, and Inventory. Order Management captures and validates the sales order, Supply Chain Orchestration creates and manages the supply order, Manufacturing executes the production order, and Inventory receives and ships the finished goods. Purchasing (B) is not involved in back-to-back fulfillment of a make item in a sales order, but it is involved in back-to-back fulfillment of a buy item in a sales order.
質問 # 16
Which work order costs CANNOT be viewed and analysed by a cost accountant on the Review Work Order Cost page?
- A. Transfer Cost
- B. Scrap Costs
- C. Shipping Costs
- D. Output Costs
正解:C
解説:
According to the Business Process Training and Certification - Oracle University document2, shipping costs are not part of the work order costs that can be viewed and analysed by a cost accountant on the Review Work Order Cost page. Shipping costs are the costs associated with delivering finished goods to customers or transferring them between organizations. Shipping costs are not incurred during the production process and are not captured by the work order. The work order costs that can be viewed and analysed by a cost accountant on the Review Work Order Cost page are: input costs, output costs, scrap costs, variance costs, transfer costs, and resource costs.
質問 # 17
Which three pieces of demand information can be included as demand in an Oracle supply plan?
- A. Production Plan
- B. Build Plan
- C. Manual Forecast
- D. Demand Forecast
正解:A、C、D
解説:
According to the Oracle Supply Planning Cloud User Guide1, there are four types of demand information that can be included as demand in an Oracle supply plan: production plan (A), manual forecast ©, demand forecast (D), and sales orders. A production plan is a high-level plan that specifies the quantity and timing of finished goods to be produced. A manual forecast is a user-defined forecast that can be entered or imported into a supply plan. A demand forecast is a statistical forecast that is generated by Oracle Demand Management Cloud or another forecasting system. Sales orders are confirmed orders from customers that have been entered into Oracle Order Management Cloud or another order management system. A build plan (B) is not a type of demand information that can be included as demand in an Oracle supply plan, but rather an output of a supply plan that specifies the quantity and timing of production orders to be executed.
質問 # 18
Which three are key operational tasks associated with Material Reservation?
- A. Item Creation
- B. Manage Production
- C. Manage Inventory Transactions
- D. Execute Production
正解:B、C、D
解説:
According to the Oracle SCM Business Process Certified Foundations Associate Rel 2 document1, material reservation is the process of allocating material to a specific work order or operation. The key operational tasks associated with material reservation are: manage production, execute production, and manage inventory transactions. Manage production is the task of creating and releasing work orders, scheduling and rescheduling operations, and monitoring production progress. Execute production is the task of reporting material transactions, such as issuing, returning, transferring, and adjusting material. Manage inventory transactions is the task of performing inventory movements, such as receiving, delivering, transferring, and adjusting inventory.
質問 # 19
Based On what does the contract manufacturing (CM) Deliver Good to a customer ?
- A. Transfer Order
- B. Sales Order
- C. Purchase Order
- D. Shipment Request
正解:B
解説:
According to the Oracle Supply Chain Management Cloud: Plan to Produce training course3, contract manufacturing deliver good to a customer is the process of delivering the finished goods produced by a contract manufacturer to the end customer based on a sales order (D). A sales order is a document that captures and validates the customer's request for goods or services. A transfer order (A) is a document that initiates an internal material transfer between two inventory organizations. A purchase order (B) is a document that initiates a procurement transaction with an external supplier. A shipment request © is a document that initiates a shipment transaction from one location to another.
質問 # 20
What is the input required to reserve the components against a work order?
- A. Item Structure of the Finished Product
- B. Routing Information of the Finished Product
- C. Plant Parameters
- D. Manufacturing Master Data
正解:A
解説:
According to the Oracle Inventory Management Cloud User Guide, reserving components against a work order is the process of allocating materials from inventory to production based on availability and priority. Reserving components against a work order requires the item structure of the finished product © as an input, which defines the components and their quantities that are needed to produce an item. Routing information of the finished product (A), manufacturing master data (B), and plant parameters (D) are not inputs required to reserve components against a work order, but rather inputs required for other processes such as work definition creation, contract manufacturing setup, or plant configuration.
質問 # 21
While defining Supply Plan, Planning administrator can select any of the four forecast process options, which include?
- A. Sales Order Explosion
- B. Forecast Consumption
- C. Forecast Spreading
- D. Past Due Demands based on Supply Network Model
- E. Past Due Demands based on Plan Option Values
正解:A、B、C、E
解説:
According to the Oracle Supply Planning Cloud User Guide2, while defining a supply plan, a planning administrator can select any of the four forecast process options, which include forecast spreading (B), forecast consumption ©, sales order explosion (D), and past due demands based on plan option values (E). Forecast spreading is the option to spread forecast demand across time periods based on a predefined pattern. Forecast consumption is the option to consume forecast demand by sales orders or other sources of demand. Sales order explosion is the option to explode sales orders into their component demands based on the bill of materials. Past due demands based on plan option values is the option to include or exclude past due demands in a supply plan based on the plan option settings. Past due demands based on supply network model (A) is not a forecast process option, but rather a supply network model parameter that determines how past due demands are handled in a supply network model.
質問 # 22
Which two methods does Oracle Fusion Manufacturing NOT support for reporting the progress of an order on the shop floor?
- A. Complete with Details
- B. Quick Complete
- C. Schedule Complete
- D. Default Complete
正解:C、D
解説:
According to the Oracle SCM Business Process Certified Foundations Associate Rel 2 document1, Oracle Fusion Manufacturing supports four methods for reporting the progress of an order on the shop floor: Complete with Details, Quick Complete, Express Complete, and Manual Complete. Schedule Complete and Default Complete are not supported methods. Schedule Complete is a method that reports the completion of an operation based on the scheduled start and end dates. Default Complete is a method that reports the completion of an operation based on the default quantity and duration.
質問 # 23
Which three work order attributes are displayed on the History tab?
- A. Work Order Details
- B. Transaction History (
- C. Work Definition
- D. IoT Insights
正解:A、B、D
解説:
According to the Oracle SCM Business Process Certified Foundations Associate Rel 2 document1, work order details, transaction history, and IoT insights are three work order attributes that are displayed on the History tab. The History tab is a page in Oracle SCM Cloud that shows the historical information about a work order. Work order details are attributes that describe the basic information about a work order, such as status, priority, quantity, start date, end date, etc. Transaction history is a list of transactions that have been performed for a work order, such as material issues, returns, transfers, adjustments; resource charges; output completions; scrap reports; etc. IoT insights are analytics that provide insights into the performance of a work order based on data collected from Internet of Things (IoT) devices connected to machines or products.
質問 # 24
Which of the three statements are true While planning, the administrator defining the supply plan has the option to setup items included in the supply chain.
- A. Manufacturing Plan to include items that are MRP Planned items
- B. Production Plan to include both items that are MPS and MRP Planned items
- C. Manufacturing Plan to include both items that are MPS and MRP Planned items
- D. Production Plan to include items that are MPS Planned items
正解:A、B、D
解説:
According to the Business Process Training and Certification - Oracle University document2, while planning, the administrator defining the supply plan has the option to setup items included in the supply chain. There are three types of statements that are true in this context:
Production Plan to include items that are MPS Planned items
Production Plan to include both items that are MPS and MRP Planned items Manufacturing Plan to include items that are MRP Planned items MPS (Master Production Schedule) is a plan that specifies the quantity and timing of finished goods to be produced. MRP (Material Requirements Planning) is a plan that calculates the quantity and timing of raw materials and components needed to produce the finished goods. A Production Plan is a type of supply plan that focuses on the production of finished goods. A Manufacturing Plan is a type of supply plan that covers both the production of finished goods and the procurement of raw materials and components.
質問 # 25
Can a user configure and control the generation of full pegging information in the plan horizon of a supply plan?
- A. No, a user cannot control the generation of full pegging information within plan horizon against a supply plan.
- B. Yes, a user can control the generation of full pegging information within plan horizon against a supply plan.
正解:B
解説:
According to the Mock Exams: Oracle SCM Business Process Foundation Associate document3, a user can configure and control the generation of full pegging information in the plan horizon of a supply plan. Pegging information shows the relationship between supply and demand in a supply chain. Full pegging information provides detailed information about each supply and demand source, such as item, quantity, date, location, organization, etc. A user can control the generation of full pegging information by selecting or deselecting the Generate Full Pegging option in the Plan Options page.
質問 # 26
Exceptions are generated only against new planned orders in Oracle supply plans
- A. FALSE
- B. TRUE
正解:A
解説:
According to the Mock Exams: Oracle SCM Business Process Foundation Associate document3, exceptions are generated not only against new planned orders but also against existing supply and demand in Oracle supply plans. Exceptions are messages that alert the user about potential issues or opportunities in a supply plan, such as excess inventory, late orders, unmet demand, etc. Exceptions are generated based on predefined or user-defined rules that compare the supply and demand data with certain thresholds or criteria. Exceptions can be generated against any type of supply or demand source, such as planned orders, purchase orders, sales orders, transfer orders, work orders, etc.
質問 # 27
Which four tasks are required to be set up to execute contract manufacturing process inan organization?
- A. Define contract manufacturing organization
- B. Define work definition of the finished good item
- C. Define contract manufacturer supplier
- D. Define contract manufacturing items
- E. Define contract manufacturer customer
正解:A、B、C、D
解説:
According to the Oracle Supply Chain Management Cloud: Plan to Produce training course3, contract manufacturing is the process of outsourcing the production of goods or services to a third-party supplier. Contract manufacturing process in an organization requires four tasks to be set up: define contract manufacturing organization (A), define contract manufacturer supplier ©, define contract manufacturing items (D), and define work definition of the finished good item (E). A contract manufacturing organization is an inventory organization that represents the location where the contract manufacturer performs the production activities. A contract manufacturer supplier is a supplier that provides contract manufacturing services to the buying organization. A contract manufacturing item is an item that is produced by a contract manufacturer based on a work definition provided by the buying organization. A work definition is a document that defines the operations, resources, materials, and output for producing an item. Define contract manufacturer customer (B) is not a task that is required to be set up to execute contract manufacturing process in an organization, as it is not relevant to the buying organization.
質問 # 28
A demand planner wants to simulate demand by making certain changes in holidays. Which forecasting profile option should the planner use?
- A. Forecasting methods
- B. Forecasting Parameters
- C. Simulation output
- D. Decomposition Groups
正解:D
解説:
According to the Oracle Demand Management Cloud User Guide1, decomposition groups are used to simulate demand by making certain changes in holidays, events, or other factors that affect demand patterns. A demand planner can use decomposition groups to create different scenarios and compare them with the base forecast. Forecasting methods (A), forecasting parameters ©, and simulation output (D) are not forecasting profile options that can be used to simulate demand by making changes in holidays.
質問 # 29
Which measure is required to import data from an external source?
- A. Approved Final Shipments Forecast
- B. Final Bookings Forecast
- C. Sales Forecast
- D. Final Shipments Forecast
正解:C
解説:
According to the Mock Exams: Oracle SCM Business Process Foundation Associate document3, sales forecast is the measure that is required to import data from an external source. Sales forecast is an estimate of future sales based on historical data, market trends, customer demand, etc. Sales forecast can be imported from an external source, such as a spreadsheet, a database, or a third-party application, using the Load Planning Data from Files task in Oracle SCM Cloud.
質問 # 30
Which two types of analysis can you use to compare forecast accuracy of a plan in a given time period?
- A. MAD
- B. Trend analysis D BIAS
- C. Waterfall analysis
- D. MAPE
正解:B、C
解説:
According to the Business Process Training and Certification - Oracle University document2, forecast accuracy is a measure of how closely the forecast matches the actual demand. Two types of analysis that can be used to compare forecast accuracy of a plan in a given time period are: waterfall analysis and trend analysis. Waterfall analysis is a graphical representation of how forecast accuracy changes over time due to various factors, such as demand changes, forecast updates, plan adjustments, etc. Trend analysis is a statistical method of identifying patterns or trends in historical data and projecting them into the future.
質問 # 31
Three correct statements with respect to Demand fulfillment view in supply plan are?
- A. User can take actions on the demand fulfilment recommendations by accepting recommendations
- B. View prioritized at-risk demands based on order values weighted by the numberof associated recommendations
- C. The recommendation summary graph shows the cumulative at-risk demand value and the related number of recommendations associated with that value
- D. Users need to define the criteria and layout in the view
正解:A、B、C
解説:
According to the Oracle Supply Planning Cloud User Guide2, demand fulfillment view in supply plan is a feature that helps users to identify and resolve at-risk demands in a supply plan. Demand fulfillment view in supply plan has three correct statements: view prioritized at-risk demands based on order values weighted by the number of associated recommendations (B), user can take actions on the demand fulfillment recommendations by accepting recommendations ©, and the recommendation summary graph shows the cumulative at-risk demand value and the related number of recommendations associated with that value (D). Users do not need to define the criteria and layout in the view (A), as they are predefined by Oracle.
質問 # 32
What is the purpose of defining the ABC Classification?
- A. To decide the frequency to review inventory balances
- B. To decide the frequency to perform inventory accuracy review
- C. To decide the frequency to perform inventory replenishment
- D. To decide the frequency to perform inventory transactions
正解:B
解説:
According to the Oracle SCM Business Process Certified Foundations Associate Rel 2 document1, the purpose of defining the ABC Classification is to decide the frequency to perform inventory accuracy review. ABC Classification is a method of categorizing inventory items based on their value and usage. Items are classified into three groups: A, B, and C. A items are the most valuable and frequently used items, B items are moderately valuable and used items, and C items are the least valuable and rarely used items. The ABC Classification helps to prioritize the inventory management activities, such as cycle counting, physical counting, replenishment, etc.
質問 # 33
Which supply type enables a Production Supervisor to manually issue material to a work order?
- A. Assembly Pull
- B. Bulk
- C. Operation Pull
- D. Push
正解:D
解説:
According to the Oracle SCM Business Process Certified Foundations Associate Rel 2 document1, push is the supply type that enables a Production Supervisor to manually issue material to a work order. Push supply type means that material is issued to a work order before it is consumed by an operation. The Production Supervisor can use the Issue Material page or a mobile device to issue material to a work order.
質問 # 34
Which three features are offered by product genealogy in Manufacturing Cloud?
- A. Production Cost
- B. Information
- C. Genealogy Details
- D. Transaction History
正解:B、C、D
解説:
According to the Oracle Manufacturing Cloud User Guide3, product genealogy is a feature that provides visibility into the history and composition of products throughout their lifecycle. Product genealogy offers three features: genealogy details (A), transaction history (B), and information ©. Genealogy details show the structure and relationships of products and their components at any point in time. Transaction history shows the chronological sequence of transactions that affected products and their components. Information shows additional attributes and attachments related to products and their components. Production cost (D) is not a feature offered by product genealogy in Manufacturing Cloud, but rather a separate feature that calculates and reports the cost of production orders and work orders.
質問 # 35
Which Job Role is required to create a Contract Manufacturing Production Request?
- A. Manufacturing Engineer
- B. Production Supervisor
- C. Cost Accountant
- D. Production Operator
正解:A
解説:
According to the Oracle Manufacturing Cloud User Guide3, a contract manufacturing production request is a document that specifies the details of a production order that is executed by a contract manufacturer. A contract manufacturing production request is created by a manufacturing engineer (B) who defines the work definition, routing, and operations for the production order. A production operator (A), a cost accountant ©, or a production supervisor (D) are not job roles that are required to create a contract manufacturing production request, but rather job roles that are involved in other aspects of contract manufacturing such as production execution, cost accounting, or production monitoring.