質問 47
Your costumer Project/planning Board to create/update Gant charts. Which the following are characteristics of the Project Planning Board.
Note : there are 3 correct answers for this question.

  • A. Display of project -relevant purchase order.
  • B. Display of project cost plan.
  • C. Display of production orders assigned to WBS element.
  • D. Display of plant maintenance orders for activities.
  • E. Using specific color management for Gantt Chart.

正解: B,C,D

 

質問 48
How can you record external service activities with service master data? Note: There are 2 correct Answers to this question.

  • A. Confirm the activities in the Cross-Application Time Sheet (CATS).
  • B. Post a goods receipt in the goods movement application (MIGO).
  • C. Create a service entry sheet.
  • D. Confirm the network activity for external services.

正解: A,C

 

質問 49
COST AND BUDGET
You have assigned a budget to WBS element with your project
What budget function could be used to check assigned values against the current budget?

  • A. Results analysis
  • B. Cost forecast
  • C. Easy cost planning
  • D. Availability control

正解: D

 

質問 50
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites?
Note: There are 3 correct answers to this question

  • A. Assignment between material and standard network
  • B. A bill of material with sales views
  • C. A material master with sales views
  • D. A production order
  • E. Standard network with activities

正解: A,C,E

 

質問 51
What are some of the possible functions in user status profiles? Note: There are 2 correct answers to this question.

  • A. Restrict setting user status for individual users
  • B. Allow business processes forbidden by SAP system status
  • C. Ensure user status must always be set manually
  • D. Utilize priorities for setting the user status

正解: A,C

 

質問 52
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.

  • A. The factory calendar in the work center used for the internal processing activity
  • B. Whether the work for the internal activity is greater than its duration
  • C. The relationships between activity elements
  • D. The unit (for example, hour, day) of the field Normal Duration field of the activity
  • E. An activated Scheduling indicator in the control key of the internal processing activity

正解: A,C,E

 

質問 53
In your project. You work with a network and external activities. You have created a purchase requisition. The corresponding purchase order is created as well. Now, you increase the quantity of the external activity. How does the system support this scenario?

  • A. A workflow can be triggered to inform the purchasing group.
  • B. The purchase order can be updated in Goods Receipt for Purchase Order (MIGO)
  • C. The purchase order is updated automatically to match the new quantity while saving the project.
  • D. The system automatically creates a new purchase requisition with the difference to the original quantity

正解: C

 

質問 54
Your customer has created networks with internal activities and generated capacity requirements. Now, they want to analyze the capacity requirements of their project. Which report do you recommend?

  • A. Individual overview capacity requirements
  • B. Extended capacity evaluation
  • C. Structure overview
  • D. Capacity load work center view

正解: D

 

質問 55
Dates
How are earliest dates and latest dates of activities schedule?

  • A. Earliest dates are scheduled by backward scheduling, and the latest dates by forward scheduling.
  • B. Earliest dates are scheduled by forward scheduling , and the latest dates by backward scheduling.
  • C. Earliest dates are scheduled by backward scheduling, and the lates dates by copying the earliest dates.
  • D. Earliest dates and latest dates are scheduled by forward scheduling.

正解: B

 

質問 56
You want to determine the planned costs for an internally processed activity. Which data do you need?
Note: There are 2 correct Answers to this question.

  • A. Profit center
  • B. Work
  • C. Duration
  • D. Activity type

正解: B,D

 

質問 57
Project Structure
Which statement regarding the creation of a new work breakdown structure (WBS element) are true?
Note : there are 3 correct answer for this question.

  • A. You can create several WBS elements per level.
  • B. The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)
  • C. A WBS element of the new project can be assigned to a different project definition.
  • D. A new work breakdown structure must contain up to 10 levels.
  • E. WBS element can be a planning element, an account assignment element, and a billing element at the same time.

正解: A,B,E

 

質問 58
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?

  • A. Network type
  • B. Project profile
  • C. Network profile
  • D. Parameters for the network type

正解: A

 

質問 59
You are using networks and external activities in your project The purchase requisition has been created. What is the sequence for the following business transactions and documents?

  • A. . Credit limit check -> Acceptance of performed services -> Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt -> invoice receipt
  • B. Vendor selection -> Purchase order handling -> Invoice receipt- Purchase order monitoring -> Goods receipt
  • C. Vendor selection -> Purchase order creation -> Service entry sheet creation -> Service entry sheet approval
  • D. Vendor selection -> Purchase order handling -> Purchase order monitoring -> Goods receipt

正解: D

 

質問 60
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?

  • A. Scheduling and distribution key
  • B. Scheduling and capacity category
  • C. Control key of an activity
  • D. Capacity planner group in the network header

正解: C

 

質問 61
Float time is calculated during scheduling. Which of the following statements about float time are correct? Note: There are 3 correct Answers to this question.

  • A. By default, critical activities have a float time, which is less than or equal to zero.
  • B. The float time of WBS elements is calculated by extrapolation.
  • C. Activities with the time constraint "Must start on" always have a negative float time.
  • D. The maximum size of a free float is as large as the total float of an activity.
  • E. Float time can be negative.

正解: A,C,E

 

質問 62
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.

  • A. Planned revenue can be transferred from a sales quotation.
  • B. Planned revenue requires a sales order assigned to a WBS element.
  • C. Actual revenue is posted via a billing document created from a sales order
  • D. Actual revenue is posted via a billing plan assigned to a WBS element.

正解: A,C

 

質問 63
Which orders or documents can be displayed in Project-Oriented Procurement (ProMan)? Note: There are 2 correct Answers to this question.

  • A. Internal orders
  • B. Sales order items
  • C. Reservations
  • D. Purchase order items

正解: C,D

 

質問 64
What functions are available for period end closing in SAP Project System? Note: There are 3 correct Answers to this question.

  • A. Settlement
  • B. Results analysis
  • C. Confirmations
  • D. Milestone trend analysis
  • E. Progress analysis

正解: A,B,E

 

質問 65
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.

  • A. The duration is missing in the activity.
  • B. Integrated planning for the network is active.
  • C. The activity output price for the activity type and cost center assigned to the work center is not maintained.
  • D. The formula for costing in the work center is incorrect.
  • E. The Determine Costs indicator in the network header rules out planned cost calculation.

正解: A,C,E

 

質問 66
......

確認済みC-TS412-2021試験問題集と解答で時間限定無料提供!C-TS412-2021には正解付き:https://www.jpntest.com/shiken/C-TS412-2021-mondaishu

C-TS412-2021試験問題、リアルC-TS412-2021練習問題集:https://drive.google.com/open?id=1LGICPtpEp9dV8atTvuxraT7D4gJlbNw7

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡