質問 22
During planning you are facing an overload situation on a resource. Which activities do you consider to create a feasible production plan?
There are 3 correct answers to this question.
Response:
- A. Use DS heuristic "Schedule Sequence"
- B. Use multilevel MRP run for the products on the resource
- C. Use rescheduling with an alternative mode
- D. Use optimization with respect to set-up times
- E. Use a bucket-oriented capacity check
正解: A,C,D
質問 23
Which time elements can be reduced by a reduction strategy? Note: There are 3 correct answers to this question.
- A. Move time
- B. Goods receipt processing time
- C. Float after production
- D. Queue time
- E. Wait time
正解: A,C,D
質問 24
Which of the following are capabilities of multidimensional reporting in SAP S/4HANA embedded analytics?
There are 3 correct answers to this question.
Response:
- A. Scheduling
- B. Filters
- C. Forecast
- D. Drilldown
- E. Sort
正解: B,D,E
質問 25
How can SAP S/4HANA support a GMP compliant production process? Note: There are 3 correct answers to this question.
- A. Predefined GMP compliant process order types to meet audit requirements
- B. Use of the digital signature function to check and run business processes
- C. Use of the GMP compliant flag in relevant master data applications
- D. Documentation of quality data with Quality Management
- E. Recipe approval (with Engineering Change Management)
正解: B,D,E
質問 26
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a positive offset time in the strategy profile.
- B. Specify a negative planning horizon in the strategy profile.
- C. Specify a negative offset time in the strategy profile.
- D. Specify a positive planning horizon in the strategy profile.
正解: C
質問 27
During production order creation, several valid production versions are found. How does the system choose the product conversion?
- A. Validity period or sales order
- B. Planned order or material number
- C. Lot size or material cost
- D. Alphanumeric or quota arrangement
正解: D
質問 28
A customer is considering switching from order-related settlement to product-related settlement. What are capabilities of cost collectors?
There are 2 correct answers to this question.
Response:
- A. They can be created automatically during month end process.
- B. They can be used for repetitive manufacturing.
- C. They can be used for manufacturing with collective orders.
- D. They can be applied to make-to-stock production order.
正解: B,D
質問 29
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP creates capacity requirements without checking the capacity of a work center.
- D. MRP creates capacity requirements only if the work center has sufficient capacity.
正解: C
質問 30
You want to procure your material components based on a forecast for the finished material derived from historical sales. When customers order, you produce the finished product and reserve it for that particular order.
Which is the appropriate planning strategy to use?
Please choose the correct answer.
Response:
- A. Planning with final assembly (40)
- B. Make-to-order production (20)
- C. Production by lot size (30)
- D. Planning without final assembly (50)
正解: D
質問 31
How Is the bill of material (BOM) exploded when you use a BOM explosion number?
Please choose the correct answer.
Response:
- A. With respect to defined separate key dates for product and each assembly
- B. With respect to a defined separate change status for product and each assembly
- C. With respect to a common change status for product and each assembly
- D. With respect to a common key date for product and each assembly
正解: A
質問 32
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
- A. Planning file entries
- B. WIP list
- C. Production list
- D. Operation list
- E. Production overview
正解: B,D,E
質問 33
In a production process, you need a certain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Kanban
- B. Picking list
- C. Backflushing
- D. Transfer Order
正解: B
質問 34
When would you use reporting point backflush in repetitive manufacturing?
There are 2 correct answers to this question.
Response:
- A. You require an up-to-date inventory for components
- B. For production lines with short lead times
- C. When you need to determine the work in progress
- D. When goods issues can wait for final confirmation
正解: C,D
質問 35
Which of the following objects can you release so that the business transactions for process order execution and process management can be executed?
There are 2 correct answers to this question.
Response:
- A. Individual phases
- B. Individual operations
- C. Individual process instructions
- D. Individual control recipes
正解: A,B
質問 36
You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?
- A. Top of Yellow
- B. Top of Red Base
- C. Top of Green
- D. Top of Red
正解: C
質問 37
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Orders (dispatched) chart
- B. Work center capacities chart
- C. Order (pool) chart
- D. Capacity requirements chart
正解: B,D
質問 38
Which automotive-specific functionality is embedded in SAP S/4HANA?
There are 3 correct answers to this question.
Response:
- A. Parts interchangeability
- B. Packaging Logistics
- C. Enhanced Kanban Processing
- D. Enhanced characteristics based processes
- E. Equipment and Tools Management
正解: A,B,C
質問 39
What data can you maintain in the sub items of a bill of material (BOM)? Note: There are 2 correct answers to this question.
- A. Installation point
- B. Item type
- C. Scrap percentage
- D. Quantity
正解: A,D