質問 16
For what production type are production orders used?
- A. Process manufacturing processes
- B. Period and quantity-oriented production
- C. Replenishment controlled by control cycles
- D. Discrete manufacturing processes
正解: D
質問 17
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
- A. Scheduling margin key
- B. Production scheduling profile
- C. Operation control key
- D. Confirmation profile
正解: B,C
質問 18
How can you achieve a feasible production plan in case of capacity constraints? Note: There are 3 correct answers to this question.
- A. Execute a new production planning run.
- B. Adjust the available capacity.
- C. Select an alternative mode on a resource.
- D. Form optimum sequences to reduce setup times.
- E. Reduce the planning window.
正解: B,C,D
質問 19
What is the equivalent in SAP S/4HANA of the Production Data Structure in PP/DS?
There are 3 correct answers to this question.
Response:
- A. Engineering Change Record
- B. Production Version
- C. Bill of Material
- D. Routing
正解: B,C,D
質問 20
What does it mean for the production planner when MRP works with infinite capacities?
- A. MRP creates capacity requirements only if the work center has sufficient capacity.
- B. MRP assigns capacity requirements automatically after the last scheduled order on a work center.
- C. MRP creates capacity requirements without checking the capacity of a work center.
- D. MRP assigns capacity requirements automatically to work center is with the earliest available capacity.
正解: C
質問 21
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a positive offset time in the strategy profile.
- B. Specify a negative planning horizon in the strategy profile.
- C. Specify a positive planning horizon in the strategy profile.
- D. Specify a negative offset time in the strategy profile.
正解: D
質問 22
Which SAP solutions are part of the Digital Value Network portfolio?
There are 3 correct answers to this question.
Response:
- A. SAP Hybris
- B. SAP Fieldglass
- C. Concur
- D. SAP Visual Enterprise
- E. SAP Human Capital Management
正解: A,B,C
質問 23
Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.
- A. In the bill of materials (BOM)
- B. In the production version
- C. In the production order type
- D. In the MRP controller
- E. In the routing
正解: C,D,E
質問 24
In order to use strategy 70 - Planning At Assembly Level, what order field must be set besides the planning strategy?
Please choose the correct answer.
Response:
- A. Dependent Requirements indicator
- B. Mixed MRP indicator
- C. Storage Location MRP Indicator
- D. Individual/Collective Indicator
正解: B
質問 25
For which data objects do you have to set up CIF integration models in S/4HANA to use them in advanced planning?
There are 2 correct answers to this question.
Response:
- A. Contract
- B. Work center
- C. Material master
- D. Production plant
正解: A,D
質問 26
In which data objects do you maintain the production line as the work center for repetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Production version
- B. Routing
- C. Repetitive manufacturing profile
- D. Production cost collector
正解: A,B
質問 27
Which chart types does the tabular planning table provide in SAP S/4HANA? Note: There are 2 correct answers to this question.
- A. Orders (dispatched) chart
- B. Capacity requirements chart
- C. Work center capacities chart
- D. Order (pool) chart
正解: B,C
質問 28
In the Manage Shortage view of the new SAP Fiori app "Monitor Material Coverage", what do the stars indicate?
Please choose the correct answer.
Response:
- A. The presence of firmed planned orders
- B. The presence of production orders
- C. The viability of the proposed solution
- D. The priority of the proposed solution
正解: C
質問 29
Which of the following business processes are controlled by parameters that are dependent on production order type? Note: There are 2 correct answers to this question.
- A. Planning
- B. Inspection during production
- C. Engineering change management
- D. Implementation
正解: A,D
質問 30
Which process order function uses a resource network?
Please choose the correct answer.
Response:
- A. Capacity planning
- B. Capacity leveling
- C. Resource scheduling
- D. Resource selection
正解: D
質問 31
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand. Which planning strategy do you use?
- A. Make-to-stock production (10)
- B. Make-to-order production (20)
- C. Planning without final assembly (50)
- D. Planning with final assembly (40)
正解: D
質問 32
In a first step you have created master recipes. In which sequence are the additional objects created?
Please choose the correct answer.
Response:
- A. Process order
Control recipe
Process message
PI sheet - B. Process message
Control recipe
Process order
Process message
PI sheet - C. Control recipe
Process order
PI sheet - D. Process order
Control recipe
PI sheet
Process message
正解: D
質問 33
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Rate routing
- B. Control cycle
- C. Replenishment strategy
- D. Production supply area
正解: B
質問 34
What are some of the SAP Fiori user types?
There are 3 correct answers to this question.
Response:
- A. Expert
- B. Employee
- C. Business partner
- D. Developer
- E. Occasional
正解: A,D,E