質問 # 11
Which of the following supports the need to govern Enterprise Architecture?

  • A. The Architecture Project mandates the governance of the target architecture
  • B. The TOGAF standard cannot be used without executive governance
  • C. The Stakeholders preferences may go beyond the architecture project scope and needs control
  • D. Best practice governance enables the organization to control value realization

正解:D

解説:
This statement best supports the need to govern Enterprise Architecture. Best practice governance enables the organization to control value realization by ensuring that architectures are aligned with the enterprise's strategy and objectives, meet the quality and performance requirements, and deliver the expected benefits and outcomes. The Architecture Project does not mandate the governance of the target architecture, but rather follows the governance framework established by the enterprise. The TOGAF standard can be used without executive governance, but it is recommended that executive sponsorship and support are obtained for successful architecture development and transition. The Stakeholders preferences may go beyond the architecture project scope and need control, but this is not the primary reason for governing Enterprise Architecture. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.6 Architecture Governance.


質問 # 12
Complete the sentence When considering agile development Architecture to Support Project will identify what products the Enterprise needs the boundary of the products and what constraints a product owner has. this defines the Enterprise's___________.

  • A. operations
  • B. workflow management
  • C. backlog
  • D. lifecycle economics

正解:C

解説:
When considering agile development, Architecture to Support Project will identify what products the enterprise needs, the boundary of the products, and what constraints a product owner has. This defines the enterprise's backlog. A backlog is a list of features or tasks that need to be done to deliver a product or service. It is prioritized by the product owner based on the value and urgency of each item. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.5 Architecture to Support Project.


質問 # 13
Which of the following are interests important to the stakeholders in a system?

  • A. Principles
  • B. Concerns
  • C. Architecture views
  • D. Requirements

正解:B

解説:
Concerns are interests important to the stakeholders in a system. They are used to identify and classify the system's stakeholders and to guide the selection of viewpoints for the architecture description. Reference: The TOGAF Standard | The Open Group Website, Section 3.2.1 Architecture Viewpoints


質問 # 14
Complete the sentence The purpose of Enterprise Architecture is to_______________.

  • A. control the bigger changes
  • B. take major improvement decisions
  • C. govern the stakeholders
  • D. guide effective change

正解:D

解説:
The purpose of Enterprise Architecture is to guide effective change by providing a coherent and consistent view of the enterprise's current and future state, as well as the roadmap and principles for achieving it. Enterprise Architecture helps to align business and IT strategies, optimize resources and investments, reduce complexity and risks, enhance agility and innovation, and deliver value to stakeholders. Reference: The TOGAF Standard | The Open Group Website, Section 1.3 Executive Overview.


質問 # 15
Which of the following is the ability to develop use and sustain the architecture of a particular enterprise using architecture to govern change?

  • A. An EA Capability
  • B. An Enterprise Architecture
  • C. An EA repository
  • D. An EA framework

正解:A

解説:
The ability to develop, use, and sustain the architecture of a particular enterprise using architecture to govern change is an EA Capability. An EA Capability is a set of skills, processes, roles, responsibilities, tools, and techniques that enable an enterprise to successfully develop and maintain its Enterprise Architecture and achieve its desired outcomes. An EA Capability is part of an enterprise's overall capability portfolio and should be aligned with its strategy and objectives. Reference: The TOGAF Standard | The Open Group Website, Section 3.2 Preliminary Phase.


質問 # 16
Complete the sentence Business Transformation Readiness Assessment is_________________.

  • A. a joint effort between corporate staff lines of business and IT planners
  • B. to ensure the active support of powerful stakeholders
  • C. a way to put building blocks into context thereby supporting re-usable solutions
  • D. widely used to validate an architecture that is being developed

正解:A

解説:
Business Transformation Readiness Assessment is a joint effort between corporate staff lines of business and IT planners to evaluate the readiness of the organization to undergo change. It involves assessing factors such as vision, commitment, capacity, capability, culture, and motivation that may influence the success of a business transformation initiative. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.2 Business Transformation Readiness Assessment.


質問 # 17
Consider the following descriptions of deliverables consumed and produced across the TOGAF ADM cycle.

Which deliverables match these descriptions?

  • A. 1 Architecture Principles - 2 Architecture Requirements Specification - 3 Request for Architecture Work - 4 Statement of Architecture Work
  • B. 1 Request for Architecture Work - 2 Statement of Architecture Work - 3 Architecture Principles - 4 Architecture Requirements Specification
  • C. 1 Statement of Architecture Work - 2 Architecture Principles - 3 Architecture Requirements Specification - 4 Request for Architecture Work
  • D. 1 Architecture Requirements Specification - 2 Request for Architecture Work - 3 Statement of Architecture Work - 4 Architecture Principles

正解:B

解説:
The Request for Architecture Work is a deliverable that is sent from the sponsor and triggers the start of an architecture development cycle. It defines the scope, budget, schedule, and deliverables for a specific architecture project. The Statement of Architecture Work is a deliverable that is produced by the architect and defines the approach and resources needed to complete an architecture project. It forms the basis of a contractual agreement between the sponsor and the architecture organization. The Architecture Principles are a deliverable that is produced by the architect and defines the general rules and guidelines for the architecture work. They reflect the business principles, business goals, and business drivers of the organization. The Architecture Requirements Specification is a deliverable that is produced by the architect and defines the requirements that govern the architecture work. It covers both functional and non-functional requirements as well as constraints and assumptions.


質問 # 18
What are the four dimensions used to scope an architecture?

  • A. Business Data Application Technology
  • B. Breadth Depth Time Period Architecture Domains
  • C. Strategy Segment Capability Budget
  • D. Strategy Portfolio Project Solution Delivery

正解:B

解説:
The four dimensions used to scope an architecture are Breadth, Depth, Time Period, and Architecture Domains. Breadth refers to the extent of the enterprise covered by the architecture. Depth refers to the level of detail and completeness of the architecture. Time Period refers to the planning horizon and the number of Transition Architectures required to achieve the Target Architecture. Architecture Domains refer to the four domains of Business, Data, Application, and Technology that constitute an enterprise's architecture. Reference: The TOGAF Standard | The Open Group Website, Section 3.2.1 Phase A: Architecture Vision.


質問 # 19
Which of the following best describes a purpose of the Gap Analysis technique?

  • A. To determine service levels for the architecture
  • B. To establish quality metrics for the architecture
  • C. To identify missing functions
  • D. To validate non-functional requirements

正解:C

解説:
Gap analysis is a technique that is used to validate an architecture by highlighting the shortfall between the Baseline Architecture and the Target Architecture. One of the purposes of gap analysis is to identify missing functions that are either deliberately omitted, accidentally left out, or not yet defined in the Target Architecture. Missing functions are marked as gaps that need to be filled by developing or procuring the building blocks.


質問 # 20
What are the following activities part or?
* Initial risk assessment
* Risk mitigation and residual risk assessment
* Risk monitoring

  • A. Security Architecture
  • B. Risk Management
  • C. Phase A
  • D. Phase C

正解:B

解説:
The following activities are part of Risk Management:
Initial risk assessment
Risk mitigation and residual risk assessment
Risk monitoring
Risk Management is the process of identifying, assessing, and responding to risks that may affect the achievement of the enterprise's objectives. Risk Management involves balancing positive and negative outcomes resulting from the realization of either opportunities or threats. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.3 Risk Management.


質問 # 21
Complete the sentence The TOGAF standard covers the development of four architecture domains. Business. Data, Technology and__________________.

  • A. Transition
  • B. Capability
  • C. Segment
  • D. Application

正解:D

解説:
The TOGAF standard covers the development of four architecture domains: Business, Data, Technology and Application. These domains represent different aspects of an enterprise's architecture and provide a consistent way of describing, analyzing, and designing them. Reference: The TOGAF Standard | The Open Group Website, Section 2.2 Architecture Development Method (ADM).


質問 # 22
Consider the following ADM phases objectives.

Which phase does each objective match?

  • A. 1G-2H-3H-4F
  • B. 1H-2F-3F-4G
  • C. 1F-2G-3G-4H
  • D. 1F-2G-3H-4H

正解:C

解説:
1F: To define an Implementation and Migration Strategy that will achieve an orderly transition from the Baseline to Target Architectures 2G: To perform appropriate governance functions while the solution is being implemented 3G: To ensure conformance with the Target Architecture by implementation projects 4H: To establish procedures for continual monitoring and assessment of the performance of the solution in operation


質問 # 23
Consider the following statements
1 A whole corporation or a division of a corporation
2 A government agency or a single government department
3 Partnerships and alliances of businesses working together such as a consortium or supply chain What are those examples of according to the TOGAF Standard?

  • A. Business Units
  • B. Enterprises
  • C. Architectures Scopes
  • D. Organizations

正解:B

解説:
Enterprises are examples of the scope of an architecture according to the TOGAF Standard. An enterprise is defined as any collection of organizations that has a common set of goals and/or a single bottom line. Enterprises can be whole corporations or divisions of a corporation, government agencies or single government departments, partnerships and alliances of businesses working together, etc. Reference: The TOGAF Standard | The Open Group Website, Section 2.1 Core Concepts.


質問 # 24
Which of the following are the four purposes that typically frame the planning horizon, depth and breadth of an Architecture Project, and the contents of the EA Repository-?

  • A. Avant-Garde Big-Bang, Discreet and Cohesive
  • B. Segment, Capability. Enterprise and End-to-end Target Architecture
  • C. Strategy Portfolio Project Solution Delivery
  • D. General Foundational Subordinate and Superior Architecture

正解:C

解説:
Strategy Portfolio Project Solution Delivery are the four purposes that typically frame the planning horizon, depth and breadth of an Architecture Project, and the contents of the EA Repository. They correspond to different levels of abstraction and granularity in the architecture development process. Reference: The TOGAF Standard, Version 9.2 - The Open Group, Section 2.4 Architecture Repository.


質問 # 25
Consider the following ADM phases objectives.

Which phase does each objective match?

  • A. 1E-2F-3E-4G
  • B. 1G-2E-3F-4E
  • C. 1F-2G-3F-4F
  • D. 1F-2F-3E-4G

正解:A

解説:
1E: To identify delivery vehicles (projects programs portfolios) that will deliver the Target Architecture 2F: To confirm readiness and ability to undergo change 3E: To determine whether an incremental approach is required and if so identify Transition Architectures that will deliver continuous business value 4G: To perform appropriate governance functions while the solution is being implemented


質問 # 26
Consider the following statement:
According to the TOGAF Standard a governed approach of a particular deliverable will ensure a system of continuous monitoring to check integrity changes decision-making and audit of all architecture-related activities Which deliverable is being referred to?

  • A. The Architecture Vision
  • B. The Architecture Definition Document
  • C. An Architecture Contract
  • D. The Statement of Architecture Work

正解:C

解説:
An Architecture Contract is a deliverable that specifies the responsibilities and obligations of the parties involved in the implementation and governance of an architecture. It ensures a system of continuous monitoring to check integrity changes decision-making and audit of all architecture-related activities. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.4 Architecture Contracts.


質問 # 27
Complete the sentence A set of architecture principles that cover every situation perceived meets the recommended criteria of_______________

  • A. consistency
  • B. stability
  • C. completeness
  • D. robustness

正解:C

解説:
A set of architecture principles that cover every situation perceived meets the recommended criteria of completeness. Completeness is one of the six criteria that should be applied when developing or assessing architecture principles. Completeness means that there are no gaps or overlaps in the coverage of principles across all relevant aspects of the enterprise's architecture. Reference: The TOGAF Standard | The Open Group Website, Section 3.3.7 Architecture Principles.


質問 # 28
......

OGEA-103試験解答問題集:https://www.jpntest.com/shiken/OGEA-103-mondaishu(42問題と解答)

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡