質問 # 16
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when producing an Outline Business Case to support the Feasibility Assessment?

  • A. During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
  • B. The Outline Business Case should demonstrate the mitigation of all business risks associated with the refurbishment.
  • C. The Feasibility Assessment should contain a detailed description of costs and benefits associated with the refurbishment.
  • D. The Outline Business Case should describe the full team structures to be engaged for the later phases of the project.
  • E. Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed.

正解:A、E

解説:
In applying Agile Project Management to the creation of an Outline Business Case in support of the Feasibility Assessment, the following two statements are most appropriate:
B: Enough description of the required refurbishment work should be provided to enable the Architecture Angels' Finance Director to decide whether the project should proceed.
Agile approaches favor providing just enough detail to make informed decisions without going into unnecessary depth at early stages. This allows for flexibility and adaptation as more information becomes available.
C; During Feasibility, potential beneficiaries of the project should be involved when the Outline Business Case for the refurbishment is created.
Agile methodologies emphasize stakeholder engagement and user involvement early and throughout the project. This ensures that the project delivers value and meets the needs of those it is intended to benefit.


質問 # 17
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.

Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution
* Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.

正解:

解説:

Explanation:
Here are the appropriate options for each assertion and reason combination:
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
* C. True (Assertion) False (Reason)
* Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
* The Procurement Manager is an appropriate representative of the end user of the solution.
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
* D. False (Assertion) True (Reason)
* Rationale: While the Business Ambassador should ensure that business needs are analyzed, the
'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.


質問 # 18
How should the lack of provision of a fire escape from the upstairs of the building in Timebox B initially be dealt with?

  • A. The Solution Development Team should revise the Timebox Plans for Timeboxes B and C.
  • B. The Solution Development Team should commence understanding and delivering the new requirement.
  • C. The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.
  • D. The Project Manager should escalate the issue to the Marketing Director, who is in the role of Business Visionary.

正解:C

解説:
The initial action to deal with the lack of provision of a fire escape from the upstairs of the building in Timebox B should be:
*C. The Architect, in the role of Technical Co-ordinator, should escalate the issue to Architecture Angels' Senior Management Team.
This is because the lack of a fire escape is a significant safety concern that could have legal and regulatory implications. It's important that the Senior Management Team is aware of this issue so they can make informed decisions about how to address it. The Architect, in the role of Technical Co-ordinator, is well-positioned to understand the technical implications of this issue and communicate them to the Senior Management Team.
While revising the Timebox Plans (option A) or commencing understanding and delivering the new requirement (option B) could be part of the solution, these actions should be taken after the issue has been escalated and discussed with the Senior Management Team. Escalating the issue to the Marketing Director (option D) may not be the most effective course of action, as this is primarily a technical and safety issue, not a marketing one.


質問 # 19
How should the Project Manager encourage the contractors to turn up on time?

  • A. Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.
  • B. Place a penalty clause on all contractors for late arrival.
  • C. Encourage open and honest communication to re-establish an environment of trust.
  • D. Appoint Team Leaders to each of the electrical and plumbing teams.

正解:C

解説:
Topic 2, XAN Insurance Company Web Project
XAN Insurance Company Web Project
(Note:
Xan is a medium-sized insurance company with a worldwide
customer base and a strong presence on the internet. Its website
has been in operation for fifteen years. It operates from one location
- a large, open-plan office in the centre of a city. It is a friendly
company with no separate private offices for individual managers.
Staff members prefer to wander around the office space and have
one-to-one chats rather than use email or have lots of meetings.
The Marketing Director is considering a project to develop a new
area on the current web site to sell a new type of insurance directly
to the proprietors of coffee bars, insuring them against minor
accidents to staff and customers. The targeted coffee bars are
privately-owned franchises and are mostly situated in railway
stations, airports and shopping centres.
The Marketing Director has not yet decided whether the system will
just provide information about insurance policies online and give
quotations, the policies then being set up later by normal mailing
and telephone contact. Alternatively, it may be possible for the
system to provide the complete set-up and sale of an insurance
policy online. In this case the system would need to enable the
online capture and processing of credit card details and the issue of
an insurance policy.
The Finance Director has budgetary control over all projects in the
company and is reluctant to release finance for projects where the
outcome, timeframe and benefits are not clear.
Because of the uncertainty about the amount of development and
the length of time it may take, it is difficult to set a timeframe on this project. The Sales Manager, who reports to the Marketing Director, has insisted that the website extensions needed for this project must be operational within 12 weeks. The Sales Manager has a You have been brought in to give advice on how an Agile Project Management approach can be used to keep control of this project and to ensure that it delivers something useful to the business within 12 weeks.
After a brief feasibility assessment, conducted by the Sales
Manager, the Finance Director has decided to authorise a 12-week
project with the objective of producing a prototype system for
insurance for coffee bars, with a release at the end of that time. Six
selected coffee bars have agreed to complete an insurance
application form online, to trial the released website.


質問 # 20
How should the Project Manager encourage the contractors to turn up on time?

  • A. Hold a separate Daily Stand-up meeting early in the morning, for the contractors only.
  • B. Place a penalty clause on all contractors for late arrival.
  • C. Encourage open and honest communication to re-establish an environment of trust.
  • D. Appoint Team Leaders to each of the electrical and plumbing teams.

正解:C


質問 # 21
Using the Project Scenario answer the following question about the technical quality of the solution to be delivered. An assessment of the maintenance requirement for the new reservation system was made during Feasibility.
Column 1 describes a list of different types of hotel reservation systems considered. Column 2 lists the three DSDM maintainability objectives. For each description in Column 1, select from Column 2 the maintainability objective it would support.
Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1. Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
2. Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
3. All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
4. All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
5. A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
Column 2
* Maintainability is a required attribute of the initial delivered solution
* Deliver first, re-engineer later
* Short-term, tactical solution

正解:

解説:

Explanation:
For each of the descriptions in Column 1, the maintainability objective from Column 2 that each would support is as follows:
* Off-the-shelf software with ready-to-use templates that will need to be customised to fully meet Hoy Hall requirements, after deployment.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: Customizing off-the-shelf software indicates a need for the solution to be maintainable from the onset to allow for these adjustments.
* Developing a fully functioning in-house system, developed and hosted by Architecture Angels IT Operations team.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: In-house developed systems need to be maintainable to facilitate future changes and enhancements by the team that created them.
* All-in-one web-based reservation and accommodation management system built to Hoy Hall's specification.
* A. Maintainability is a required attribute of the initial delivered solution
* Rationale: A system built to specific requirements will require the ability to maintain and adjust the system as needs evolve, making maintainability a key initial attribute.
* All bookings for Hoy Hall to be scheduled by one of the other two hotels within the group, until a suitable system can be implemented at the site.
* C. Short-term, tactical solution
* Rationale: This is clearly a temporary measure until a proper system is in place, indicative of a tactical solution to address immediate needs.
* A spreadsheet is used to capture customer details manually. Data will then be exported into a fully functional system at a later date.
* C. Short-term, tactical solution
* Rationale: Using a spreadsheet is a stop-gap solution to manage information in the short term, emphasizing the tactical nature rather than long-term maintainability.
Option B is not selected for any of the descriptions as none of them imply an approach of delivering first with the intention to re-engineer later. They all suggest a need for immediate maintainability or a short-term fix, not a re-engineering approach.


質問 # 22
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.


Assertion
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co- ordinating the project.
* The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside the Solution Development Team.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs are properly analysed.
* The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to all interested parties.

正解:

解説:

Explanation:
Here are the appropriate options for each assertion and reason combination:
* The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
* C. True (Assertion) False (Reason)
* Rationale: While the Business Visionary may have the authority to make strategic decisions that could overrule cost restrictions, the reason given relates to project-level roles directing the project, not to the authority to overrule cost-related advice.
* The Procurement Manager is an appropriate representative of the end user of the solution.
* B. True (Assertion) True (Reason) BUT the reason does not explain the assertion
* Rationale: The Procurement Manager, as part of the operational team, could represent the end user. However, the reason given talks about the empowerment of the Business Ambassador, which does not directly explain why the Procurement Manager is a representative of the end user.
* The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: Specialist gardening team members would be suitable as Solution Developers, providing support to the Lead Developer, which is a common practice in Agile teams.
* The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
* D. False (Assertion) True (Reason)
* Rationale: While the Business Ambassador should ensure that business needs are analyzed, the
'Hoy for Hoy Hall' Action Group members being assigned as Business Ambassadors is not necessarily true as they are external stakeholders and not necessarily equipped to represent the business internally on a project.
* The Project Manager should plan the communication needed between the Marketing Director, in the role
* of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
* A. True (Assertion) True (Reason) AND the reason explains the assertion
* Rationale: The Project Manager typically has the responsibility to plan and manage communication between the project team and external stakeholders, and the Business Visionary's role includes promoting the business vision to interested parties, which includes the 'Hoy for Hoy Hall' Action Group.


質問 # 23
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about applying controls to the end of Development Timebox C.
What action should the Project Manager take when considering the End of Timebox Review?

  • A. Encourage the Marketing Director to attend the End of Timebox Review.
  • B. Attend the next Daily Stand-up to raise an issue about the windows.
  • C. Ask the Team Leader to remove the windows from the Timebox Plan for Timebox C.
  • D. Prepare a summary of progress against plan, for presentation at the review.

正解:D


質問 # 24
Which 2 statements represent appropriate entries for the plan for Post-Project activities?

  • A. Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
  • B. The Project Manager will attend Daily Stand-up meetings to observe
    progress.
  • C. The Sales Manager will create a company-wide email showing the
    number of policies sold weekly by each of the sales assistants.
  • D. A report showing the number of application forms completed online
    through the website for coffee shop insurance policies will be produced weekly.
  • E. Before the product is deployed, the Sales Manager will circulate a copy of the revised sales procedure for processing coffee shop insurance sales.

正解:A、D

解説:
For the XAN Insurance Company Web Project, the plan for Post-Project activities should include actions and measures that will be undertaken after the project's deliverables have been implemented to ensure sustained benefits, monitor performance, and facilitate continuous improvement.
Selected Statements for the Plan for Post-Project Activities:
D: A report showing the number of application forms completed online through the website for coffee shop insurance policies will be produced weekly.
E: Once the new system has been deployed, the time it takes to process sales online will be compared with the time it takes to process new policies sold through telephone sales.
D: Producing a weekly report on the number of application forms completed online is a clear post-project activity. It provides ongoing monitoring of the project's impact and the effectiveness of the online system in attracting coffee shop insurance policies.
E; Comparing the processing times of online sales to telephone sales after the new system's deployment is an essential post-project activity. It evaluates the efficiency and effectiveness of the new online system, offering insights into improvements and adjustments that may be needed.
Why Other Statements Are Excluded:
A: Creating a company-wide email to show the number of policies sold by each sales assistant weekly is more related to internal sales performance monitoring and motivation rather than a specific post-project activity tied to the project's objectives.
B: Circulating a copy of the revised sales procedure before product deployment is a preparation step for the transition to the new system, rather than a post-project activity.
C: The Project Manager attending Daily Stand-up meetings is part of the ongoing project management and team coordination activities during the project, not a post-project activity.
Topic 2, Hoy Hall Hotel Refurbishment Project
Scenario:
Hoy Hall Hotel Refurbishment Project
(Note:
Hoy Hall, a historic, timber-framed building dating from the 17th century, was originally the residence of the Lords of the Manor of Hoytown. The building is registered as a Heritage Building of Special Interest and is subject to restrictions in terms of development. Used as a hotel for over a century, it has recently fallen into disrepair, and for two years it has been completely unused, accelerating its deterioration. The local community has formed the Action Group "Hoy for Hoy Hall" to save the building, and wants to be closely involved in its future success.
After much discussion Hoy Hall has been purchased by Architecture Angels (AA), a small company whose directors are experienced hoteliers. Five years ago they decided to move into the property renovation business and have recently restored two other similarly-endangered buildings for use as hotels.
Architecture Angels are keen to both support local businesses and to have local people run their hotels, giving them a significant amount of autonomy to do this.
To maintain core consistency, the hotels use Architecture Angels' Head Office services, such as IT operations, accounting, payroll, stocktaking, compliance, human resources and property management. The Head Office is based 80 miles from Hoy Hall.
Recently Architecture Angels commenced an Agile project to renovate Hoy Hall, which has a large downstairs hall and reception area, and 20 potential bedrooms upstairs. The roof requires extensive repairs and the electrical and plumbing installations require complete replacement. The 40 acres of land around the site are overgrown and need to be restored, and the driveway needs re-laying.
In the hotel industry, the trend for direct customer bookings via the internet has had a major impact on the growth of those hotels with this facility. Online booking now accounts for around 80% of room bookings, with only 20% being made via walk-in and telephone enquiries. Before Hoy Hall can open for business, a reservation system must be fully operational.
Architecture Angels use contractors to manage such work and have good
relationships with two local companies: Timber Tigers (TT) who will handle the internal works, and Earth Excavations (EE) who will handle the gardens.
A Project Manager, who has since left the company, started the Feasibility phase. This phase has been continued by the Senior Management Team, which consists of the Sales, Marketing, and Finance Directors and the Chief Executive.
This was scheduled to take a month and has almost been completed. A
Feasibility Assessment has been produced. An Outline Business Case has been completed which assessed the project as being viable.
The Architecture Angels Senior Management Team will be responsible for
Steering the project.
The table below shows the appointments planned for the project team and is subject to change.

Additional Information:
The project is approaching the end of Feasibility. The original Project Manager was involved in drafting a Delivery Plan for the project but not in the outline refurbishment options.
The Senior Management Team generated several options for the refurbishment.
All the options included a landscaping solution for the gardens and re-laying of the driveway, as the solution will not be acceptable without these. However, the best solution for the refurbishment is still under debate. The new Project Manager has suggested that a Feasibility Prototype could consist of paper-based drawings for each option. The "Hoy for Hoy Hall" Action Group thinks that a physically-built representation is mandatory for a prototype and wants a small-scale model of the recommendation for the building. The time available to produce this, however, is limited.
Contracts for resources have not yet been signed and will be postponed until the chosen outline solution has been agreed.


質問 # 25
Which 2 statements explain why the Architecture Angels' Chief Accountant would be an appropriate Business Ambassador?

  • A. Runs a personal refurbishment project in any spare time so will be able to interact with the technical staff.
  • B. Has three Accounts Clerks as staff.
  • C. Understands the financial realities about what can be afforded and what is needed.
  • D. Has been with the company for six months so is keen to make an impression.
  • E. Has been authorised by the Architecture Angels' Marketing Director to take decisions on behalf of the business areas.

正解:C、E


質問 # 26
The Solution Development Team are progressing through the first Structured Timebox.
What should the Project Manager do to lead the team at this time?

  • A. Maintain a tight control on progress, recording all discussions and making all decisions.
  • B. The Project Manager should do nothing during a Timebox.
  • C. Attend the Daily Stand-up and discuss any problems at the end.
  • D. Update the Team Board with a summary of team progress and the current status of work.

正解:C


質問 # 27
How should the Project Manager assist the electricians to deliver the wiring?

  • A. Encourage the Business Ambassador to be available to discuss location of electrical sockets.
  • B. Hold a weekly meeting for electricians so they can report on progress.
  • C. Provide separate electricians' rooms so they can focus on their work.
  • D. Produce a detailed design of all electrical socket locations, to be approved by the Technical Co-ordinator.

正解:A


質問 # 28
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?

  • A. Discuss the development interfaces and dependencies with the Solution Development Team to ensure the associated Timebox is appropriate.
  • B. Add the additional tasks required to create the financial transaction functionality to the Timebox Plan.
  • C. Source and hire a web developer with experience in developing online financial transaction functionality.
  • D. Agree to de-scope Should Have and/or Could Have requirements to allow for the new Must Have functionality.
  • E. Consolidate and circulate an agenda for the workshop.

正解:A、B


質問 # 29
Which 2 actions should the Business Visionary take to implement the new Must Have requirement?

  • A. Send a company-wide communication to explain the implications of the business change to all interested parties.
  • B. Source and hire a web developer with experience in developing online financial transaction functionality.
  • C. Ensure the marketing and sales teams are working together to deliver the most effective outcome.
  • D. Consolidate and circulate an agenda for the workshop.
  • E. Assess the impact of the new Must Have requirement on the original
    Business Case.

正解:A、C

解説:
To implement the new Must Have requirement for the coffee shop insurance product website with financial transaction functionality, the Business Visionary should focus on actions that align with their role in guiding the project's vision and ensuring it meets business needs. The following actions are most appropriate for the Business Visionary:
Selected Actions for the Business Visionary:
A; Send a company-wide communication to explain the implications of the business change to all interested parties.
D: Ensure the marketing and sales teams are working together to deliver the most effective outcome.
A: As a Business Visionary, communicating the implications of significant business changes, such as the introduction of a new financial transaction functionality, is crucial. This helps in aligning all parts of the organization with the project's objectives and the strategic direction, ensuring everyone understands the change and its benefits.
D: The Business Visionary plays a key role in ensuring that different departments, such as marketing and sales, collaborate effectively to support the project's objectives. By ensuring these teams work together, the Business Visionary helps in maximizing the project's impact and effectiveness in meeting business goals.
Why Other Actions Are Less Suitable:
B: Assessing the impact of new requirements on the Business Case is important, but it's typically a responsibility shared with the Business Sponsor, who has a more direct role in managing the project's financial and strategic alignment.
C: Sourcing and hiring technical expertise is generally a task for the Project Manager or technical leads. The Business Visionary's role is more focused on strategic oversight rather than operational tasks.
E: Organizing and managing workshop details, such as circulating an agenda, might be supported by the Business Visionary, but it's often a task handled by the Project Manager or a designated coordinator to ensure efficient planning and execution of project activities.


質問 # 30
Time is running short and the Must Have requirements for the data entry screen of the web page, as recorded in the Prioritised Requirements List, are not going to be completed on time.
What action should the Project Manager take?

  • A. Amend the end date in the Delivery Plan.
  • B. Change the end date of the Timebox.
  • C. Ensure that this issue is escalated to the project level roles.
  • D. Accept that the Must Have requirements will not be delivered on time.

正解:C


質問 # 31
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation

正解:

解説:

Explanation:
For each action in Column 1, here is the iterative development activity that the action represents from Column
2:
* The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
* B. Action
* The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
* A. Thought
* Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
* C. Conversation
* The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
* C. Conversation
* The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
* B. Action


質問 # 32
......

完全版は2025年最新のAgilePM-Practitioner試験問題集テストガイドはトレーニング専門JPNTest:https://www.jpntest.com/shiken/AgilePM-Practitioner-mondaishu

合格準備AgilePM-PractitionerにはJPNTestが提供するあなたをAgile Project Management (AgilePM) Practitioner Exam試験合格させます顕著練習問題:https://drive.google.com/open?id=1K4IyN6U3vhJOMQ0fQ32DlPmWbWusYJ0U

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡