質問 # 179
What product should be used to confirm the version number of ail products in a particular stage?

  • A. Configuration Item Record
  • B. Issue Register
  • C. Product Status Account
  • D. Product Description

正解:C


質問 # 180
Which of the following describes a use of a Configuration Item Record?

  • A. To provide information on the approval procedure for the Work Package
  • B. To record how changes to a product will be controlled
  • C. To pass responsibility for the delivery of a product to a Team Manager
  • D. To record the history of a product

正解:D


質問 # 181
Which is a purpose of the Closing a Project process?

  • A. Confirm that all benefits defined in the Business Case have been achieved
  • B. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
  • C. Authorize the final stage of the project
  • D. Delegate day-to-day management of the end of the project to the Project Manager

正解:B


質問 # 182
Which is a typical core activity within configuration management?

  • A. Quality assurance
  • B. Verification and audit
  • C. Progress reporting
  • D. Risk management

正解:B


質問 # 183
Which is NOT a type of issue?

  • A. A constraint
  • B. A problem/concern
  • C. An off-specification
  • D. A request for change

正解:A


質問 # 184
Why can PRINCE2 be applied to any type of project?

  • A. Because it allows each member of the project management team to fully understand their role and responsibilities
  • B. Because it separates the management of the project from the specialist work needed to deliver the products
  • C. Because it provides the project manager with a planning procedure to plan the project more effectively
  • D. Because it provides the project manager with procedures for managing project risks and issues

正解:A

解説:
Explanation
Reference https://www.prince2.com/uk/prince2-methodology


質問 # 185
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  • A. Those who will specify the desired outputs of the project
  • B. Those with a financial interest in the project
  • C. Those who will manage the project on a day-to-day basis
  • D. Those who will create the project's outputs

正解:C

解説:
Section: Volume A


質問 # 186
Which is one of the six aspects of project performance that needs to be managed?

  • A. Risk
  • B. Security
  • C. Progress
  • D. Change

正解:A


質問 # 187
What is the project manager role responsible for?

  • A. Approving the completion of each management stage
  • B. Defining the project-level tolerances
  • C. Verifying that the project gives value for money
  • D. Ensuring that the project produces the required products

正解:D

解説:
Explanation/Reference:
Reference http://prince2.wiki/Project_Manager


質問 # 188
Which is a purpose of the Directing a Project process?

  • A. Create and authorize the project mandate
  • B. Control the day-to-day running of the project
  • C. Ensure that work on products allocated to the team is authorized and agreed
  • D. Delegate day-to-day management of the project to the Project Manager

正解:D


質問 # 189
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?

  • A. Continued business justification
  • B. Learn from experience
  • C. Manage by exception
  • D. Manage by stages

正解:D

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-plans.php


質問 # 190
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

  • A. Corporate/programme management
  • B. Senior Supplier
  • C. Executive
  • D. Senior User

正解:A


質問 # 191
Which is a benefit of applying the 'tailor to suit the project' principle?

  • A. The capability of leadership is strengthened
  • B. The number of outputs is reduced
  • C. Project management becomes less bureaucratic
  • D. The project environment complexity is reduced

正解:D


質問 # 192
Which is an objective of the 'initiating a project' process?

  • A. To ensure that the planned products are delivered within tolerances
  • B. To ensure that user acceptance of the products is confirmed
  • C. To ensure that the business case is kept under review
  • D. To ensure that baselines are established and controlled

正解:A

解説:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective


質問 # 193
Which is a valid statement about the Project Support role?

  • A. Produces Checkpoint Reports for the Project Manager
  • B. Can be performed by the Project Manager
  • C. Is an optional role for a PRINCE2 project
  • D. Can be combined with the Project Assurance role

正解:B


質問 # 194
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.

  • A. Both 1 and 2 are true
  • B. Only 2 is true
  • C. Only 1 is true
  • D. Neither 1 or 2 are true

正解:A


質問 # 195
Which statement about the Directing a Project process is true?

  • A. Ensures there are regular progress meetings
  • B. Begins on completion of the Initiating a Project process
  • C. Provides a mechanism for the Project Board to assure that there is continued business justification
  • D. Covers the day-to-day activities of the Project Manager

正解:C


質問 # 196
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

  • A. a corporate
  • B. a temporary
  • C. a technical
  • D. an external

正解:B


質問 # 197
......

あなたを余裕でPRINCE2-Foundationは100%試験合格率保証:https://www.jpntest.com/shiken/PRINCE2-Foundation-mondaishu

PRINCE2-Foundation問題集本日限定!無料アクセスが可能に!:https://drive.google.com/open?id=12pY6JxX9-Hop2RZbjaipDHz5m8HneKCI

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡