最新のPRINCE2-Foundation問題集PDFでPRINCE2-Foundationリアルで有効な正確な問題集は340問題と解答が待ってます!
100%無料PRINCE2-Foundation試験問題集リアルPRINCE2 Certification問題集を試そう
質問 # 179
What product should be used to confirm the version number of ail products in a particular stage?
- A. Configuration Item Record
- B. Issue Register
- C. Product Status Account
- D. Product Description
正解:C
質問 # 180
Which of the following describes a use of a Configuration Item Record?
- A. To provide information on the approval procedure for the Work Package
- B. To record how changes to a product will be controlled
- C. To pass responsibility for the delivery of a product to a Team Manager
- D. To record the history of a product
正解:D
質問 # 181
Which is a purpose of the Closing a Project process?
- A. Confirm that all benefits defined in the Business Case have been achieved
- B. Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
- C. Authorize the final stage of the project
- D. Delegate day-to-day management of the end of the project to the Project Manager
正解:B
質問 # 182
Which is a typical core activity within configuration management?
- A. Quality assurance
- B. Verification and audit
- C. Progress reporting
- D. Risk management
正解:B
質問 # 183
Which is NOT a type of issue?
- A. A constraint
- B. A problem/concern
- C. An off-specification
- D. A request for change
正解:A
質問 # 184
Why can PRINCE2 be applied to any type of project?
- A. Because it allows each member of the project management team to fully understand their role and responsibilities
- B. Because it separates the management of the project from the specialist work needed to deliver the products
- C. Because it provides the project manager with a planning procedure to plan the project more effectively
- D. Because it provides the project manager with procedures for managing project risks and issues
正解:A
解説:
Explanation
Reference https://www.prince2.com/uk/prince2-methodology
質問 # 185
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
- A. Those who will specify the desired outputs of the project
- B. Those with a financial interest in the project
- C. Those who will manage the project on a day-to-day basis
- D. Those who will create the project's outputs
正解:C
解説:
Section: Volume A
質問 # 186
Which is one of the six aspects of project performance that needs to be managed?
- A. Risk
- B. Security
- C. Progress
- D. Change
正解:A
質問 # 187
What is the project manager role responsible for?
- A. Approving the completion of each management stage
- B. Defining the project-level tolerances
- C. Verifying that the project gives value for money
- D. Ensuring that the project produces the required products
正解:D
解説:
Explanation/Reference:
Reference http://prince2.wiki/Project_Manager
質問 # 188
Which is a purpose of the Directing a Project process?
- A. Create and authorize the project mandate
- B. Control the day-to-day running of the project
- C. Ensure that work on products allocated to the team is authorized and agreed
- D. Delegate day-to-day management of the project to the Project Manager
正解:D
質問 # 189
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
- A. Continued business justification
- B. Learn from experience
- C. Manage by exception
- D. Manage by stages
正解:D
解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-plans.php
質問 # 190
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
- A. Corporate/programme management
- B. Senior Supplier
- C. Executive
- D. Senior User
正解:A
質問 # 191
Which is a benefit of applying the 'tailor to suit the project' principle?
- A. The capability of leadership is strengthened
- B. The number of outputs is reduced
- C. Project management becomes less bureaucratic
- D. The project environment complexity is reduced
正解:D
質問 # 192
Which is an objective of the 'initiating a project' process?
- A. To ensure that the planned products are delivered within tolerances
- B. To ensure that user acceptance of the products is confirmed
- C. To ensure that the business case is kept under review
- D. To ensure that baselines are established and controlled
正解:A
解説:
Explanation/Reference:
Reference http://prince2.wiki/Initiating_a_Project#Objective
質問 # 193
Which is a valid statement about the Project Support role?
- A. Produces Checkpoint Reports for the Project Manager
- B. Can be performed by the Project Manager
- C. Is an optional role for a PRINCE2 project
- D. Can be combined with the Project Assurance role
正解:B
質問 # 194
Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project.
2. Stakeholders may be internal or external to the corporate organization.
- A. Both 1 and 2 are true
- B. Only 2 is true
- C. Only 1 is true
- D. Neither 1 or 2 are true
正解:A
質問 # 195
Which statement about the Directing a Project process is true?
- A. Ensures there are regular progress meetings
- B. Begins on completion of the Initiating a Project process
- C. Provides a mechanism for the Project Board to assure that there is continued business justification
- D. Covers the day-to-day activities of the Project Manager
正解:C
質問 # 196
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
- A. a corporate
- B. a temporary
- C. a technical
- D. an external
正解:B
質問 # 197
......
あなたを余裕でPRINCE2-Foundationは100%試験合格率保証:https://www.jpntest.com/shiken/PRINCE2-Foundation-mondaishu
PRINCE2-Foundation問題集本日限定!無料アクセスが可能に!:https://drive.google.com/open?id=12pY6JxX9-Hop2RZbjaipDHz5m8HneKCI