質問 # 92
What must be produced to meet the minimum requirements when applying the change theme?

  • A. A change budget for the analysis of change
  • B. Status reports on all products being produced
  • C. Records of the decisions made on all issues
  • D. Documents recording the version of each product

正解:C

解説:
To meet the minimum requirements when applying the change theme in PRINCE2, it is necessary to maintain records of the decisions made on all issues. This includes documenting how each issue was addressed and any subsequent changes made to project plans or products. This record-keeping is crucial for traceability, accountability, and ensuring that decisions are aligned with project objectives and governance.
PRINCE2 Foundation Manual


質問 # 93
What is a purpose of the communication management approach?

  • A. To define how the project team intends to obtain responses from stakeholders
  • B. To describe the techniques required to make the project product acceptable to stakeholders
  • C. To describe the target organizational state and how the business will move to that new state
  • D. To describe the processes used to engage with stakeholders in identifying uncertainties

正解:A

解説:
The purpose of the Communication Management Approach is to define how the project team will engage with and manage communications with stakeholders throughout the project. This includes planning the means and frequency of communication to ensure all stakeholders are appropriately informed and can provide necessary feedback on project progress and issues. References: PRINCE2 Foundation Guide, "Communication Management Approach" section


質問 # 94
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities

  • A. project budget
  • B. project's risk tolerance
  • C. change budget
  • D. project's cost tolerance

正解:A


質問 # 95
Which role does NOT set tolerances?

  • A. Project Board
  • B. Corporate or programme management
  • C. Project Manager
  • D. Change Authority

正解:D


質問 # 96
Which is NOT a purpose of a Benefits Review Plan?

  • A. Describe how to measure and confirm any benefits that are to be realised after the project is closed
  • B. Describe how to measure the performance of the project's products in operational use
  • C. Define the scope, timing and ownership of the benefit reviews required
  • D. Define the period over which the cost-benefit analysis will be based

正解:D

解説:
This answer remains the same as question 3. The Benefits Review Plan's purpose does not typically include defining the period for the cost-benefit analysis. Instead, it focuses on outlining how the benefits of the project are to be reviewed and measured after the project's closure. References: PRINCE2 Foundation official guide and study material.
These answers are derived from the official PRINCE2 documentation and study materials available for the PRINCE2 Foundation certification.


質問 # 97
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk response
  • B. Risk category
  • C. Risk status
  • D. Risk description

正解:A

解説:
Risk response refers to the actions identified and implemented to bring the risk exposure to an acceptable level. These actions are part of the risk management process and aim to reduce, avoid, transfer, or accept risks depending on their potential impact on the project. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


質問 # 98
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

  • A. Only 2 is true
  • B. Neither 1 or 2 are true
  • C. Both 1 and 2 are true
  • D. Only 1 is true

正解:C

解説:
Section: Volume A


質問 # 99
Which is a purpose of the Plans theme?

  • A. Assess and control uncertainty
  • B. Understand whether the targets are achievable
  • C. Establish the project's structure of accountability
  • D. Identify, assess and control any potential changes to the baseline

正解:B


質問 # 100
Which is a purpose of the Risk theme?

  • A. Provide the Project Board with a time-driven control to capture all project risks
  • B. Establish a method for the implementation of continuous improvement during the project
  • C. Identify, assess and control problems that have occurred
  • D. Establish a cost-effective procedure to identify, assess and control risks

正解:D

解説:
The purpose of the Risk theme in PRINCE2 is to establish a cost-effective procedure to identify, assess, and control uncertainties or risks. This ensures that the project can cope with risks effectively. The Risk theme supports decision-making by improving the understanding of risks and their likely impact on achieving the project's objectives.References: PRINCE2 7 Foundation resources and study materials.


質問 # 101
According to PRINCE2, why might there be more than one business case for a project?

  • A. The project may be in a programme environment
  • B. There may be more than one management stage in the project
  • C. There may be more than one work package being delivered in the project
  • D. The project may be in a commercial environment with a number of suppliers

正解:D

解説:
Explanation
Reference https://www.prince2primer.com/prince2-practitioner-questions-answers-business-case/


質問 # 102
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. project management team
  • B. controls
  • C. stages
  • D. products

正解:D


質問 # 103
Which describes risk probability?

  • A. Timeframe within which the risk may occur
  • B. A measure of the likelihood of the risk occurring
  • C. Probable effect on the project delivering its objectives
  • D. Level of risks which the project can tolerate before escalating to the Project Board

正解:B

解説:
Risk probability in PRINCE2 refers to the measure of the likelihood that a particular risk will occur. It is a fundamental aspect of risk assessment, influencing the prioritization and management of risks within the project. References: PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


質問 # 104
What is described as an organization's unique attitude towards risk taking

  • A. Risk tolerance
  • B. Risk evaluation
  • C. Risk management
  • D. Risk appetite

正解:D


質問 # 105
Which statement defines a risk?

  • A. An uncertain event, or set of events that, should it or they occur, will have an effect on the achievement of objectives
  • B. An event that has already occurred that the Project Manager must deal with immediately
  • C. An uncertain event, or set of events that, should it or they occur, will be automatically escalated to the Project Board for a response
  • D. A certain event occurring in the future that will have a negative impact on the project's objectives

正解:A


質問 # 106
Identify the missing word in the following sentence. The [?] theme defines that the Project
Board is responsible for the overall direction and management of the project,

  • A. Organization
  • B. Business Case
  • C. Progress
  • D. Plans

正解:A


質問 # 107
Which is a responsibility of a risk owner?

  • A. Determine project risk appetite
  • B. Manage, monitor and control all aspects of an assigned risk
  • C. Identify risks to the project that might occur in their department
  • D. Own and authorize theuse of the risk budget to fund risk responses

正解:B


質問 # 108
Which is NOT a requirement of a Stage Plan?

  • A. Produced to an appropriate level of detail to enable day-to-day control
  • B. Approved at the end of a management stage
  • C. Approved and signed-off by Project Assurance
  • D. Produced near to the end of the previous management stage

正解:C


質問 # 109
Which is a purpose of the 'directing a project' process?

  • A. To do the minimum in order to decide whether the project is feasible
  • B. To exercise overall control over the project
  • C. To take corrective action to control risks and issues
  • D. To update the project plan before the next stage

正解:B

解説:
Reference http://prince2.wiki/Directing_a_Project#Purpose


質問 # 110
Who represents the three project interests on a project?

  • A. Project support
  • B. External project stakeholders
  • C. Project board
  • D. Project manager

正解:C

解説:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Organization#Three_Project_Interests


質問 # 111
The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the 'issue management technique should the change authority request this information?

  • A. Assessing issues
  • B. Capturing issues
  • C. Deciding on changes
  • D. Implementing changes

正解:A

解説:
When the change authority asks for more information regarding a proposed change, this occurs during the
'Assessing issues' step of the 'issue management technique' in PRINCE2. This step involves evaluating the impact and implications of issues or changes, including requesting additional information necessary to make informed decisions.References: PRINCE27 Foundation resources on issue and change management.


質問 # 112
According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

  • A. Six
  • B. One
  • C. Three
  • D. Two

正解:C

解説:
Section: Volume B
Explanation/Reference: https://p2.tech-academy.co.uk/organisation/


質問 # 113
Which is NOT considered when defining risk tolerance?

  • A. The amount of risk a Project Board considers acceptable
  • B. An organization's risk appetite
  • C. The allocated risk budget
  • D. A Project Board's attitude towards risk taking

正解:C


質問 # 114
......


Prince2 Foundation認定試験は、Prince2方法論の主要な原則、テーマ、プロセス、役割、および管理製品に関する候補者の知識をテストします。この試験は60の複数選択の質問で構成されており、候補者は試験を完了するために60分を持っています。認定を獲得するには、55%の合格スコアが必要です。

 

無料PRINCE2-Foundation別格な問題集をダウンロード:https://www.jpntest.com/shiken/PRINCE2-Foundation-mondaishu

PRINCE2-Foundation合格保証がつく問題集で合格できるPRINCE2-Foundation試験:https://drive.google.com/open?id=13Rhr_FYCCl-C6fUpEDUqvroquEFadCm_

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡