質問 # 77
What should the 'managing product delivery' process ensure?
1. That the planned products meet their quality criteria
2. That the stage plan is kept up to date
3. That the project board is provided with progress information
4. That the planned products are delivered within tolerance
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
正解:D
解説:
The 'managing product delivery' process in PRINCE2 ensures that the planned products meet their quality criteria (ensuring products are fit for purpose) and that these products are delivered within the agreed tolerances (ensuring delivery within time, cost, quality, scope, risk, and benefit tolerances). References:
PRINCE2 Foundation Handbook, Managing Product Delivery section.
質問 # 78
Which is a purpose of the Initiating a Project process?
- A. Establish solid foundations for a project
- B. Decide on the project approach
- C. Identify the number of Work Packages required
- D. Decide if it is worthwhile to initiate a project
正解:A
解説:
The purpose of the Initiating a Project process is to establish solid foundations for the project, ensuring that there is a clear understanding of the reasons for the project, the benefits expected, and how the delivery will be managed. This foundation is crucial for the successful management and delivery of the project.
References: PRINCE2 Foundation manual, PRINCE2 official resources
質問 # 79
Which is a minimum requirement when applying the business case theme?
- A. To define the management actions required to ensure the project's outcomes are achieved
- B. To specify the solution to be used to deliver the business option selected
- C. To integrate the benefits management approach with the project and stage plans
- D. To ensure the corporate business plan is updated with the project costs and benefits
正解:C
解説:
One of the minimum requirements when applying the Business Case theme in PRINCE2 is to integrate the Benefits Management Approach with the project's plans. This requirement ensures that there is a clear line of sight between the project's outputs, outcomes, and the expected benefits. It focuses on planning for the realization of benefits from the outset, which is essential for justifying the project throughout its life cycle.References: PRINCE2 Foundation Manual
質問 # 80
Which approach must be followed as a minimum requirement for applying the plans theme?
- A. Product-based planning
- B. Activity-based planning
- C. Risk management
- D. Agile
正解:A
解説:
The minimum requirement for applying the Plans Theme in PRINCE2 is following the product-based planning approach. This approach involves creating a product breakdown structure, writing product descriptions, and defining product dependencies before developing the schedule and resource plans. It ensures that plans are focused on the project's deliverables and their quality requirements. References: PRINCE27 Foundation Handbook and official training materials.
質問 # 81
The project manager needs to report to the project board on the status of the project's Issues.
- A. Project brief
- B. Change management approach
- C. Project log
- D. Lessons report
正解:C
質問 # 82
Which approach must be followed as a minimum requirement for applying the plans theme?
- A. Product-based planning
- B. Activity-based planning
- C. Risk management
- D. Agile
正解:A
解説:
Section: Volume B
質問 # 83
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
- A. product cost tolerance
- B. stage cost tolerance
- C. project cost tolerance
- D. Work Package cost tolerance
正解:D
質問 # 84
What is the minimum number of management stages required by PRINCE2?
- A. Three stages: to initiate, to deliver and to close the project
- B. Four stages: to start, to initiate, to deliver and to close the project
- C. One stage: to cover the whole project
- D. Two stages: to initiate and to deliver the project
正解:D
解説:
Section: Volume B
質問 # 85
Which statement applies to Stage Plans?
- A. Are produced at the same time as the Project Initiation Documentation
- B. Assist the Project Manager in the day-to-day running and control of the project
- C. Provide a baseline against which the Project Board monitor overall progress
- D. Always have the same duration as the Project Plan
正解:B
解説:
Stage Plans in PRINCE2 are essential tools for the Project Manager, assisting in the day-to-day management and control of the project. Each Stage Plan provides the detail needed for each management stage of the project, including what work will be done, when it will be delivered, and who will be involved, thus facilitating effective project governance on a stage-by-stage basis. They do not necessarily match the duration of the Project Plan or get produced simultaneously with the Project Initiation Documentation.References: PRINCE2 7 Foundation handbook and other official documents.
質問 # 86
Which two roles are linked by the Managing Product Delivery process?
- A. Project Manager and Team Manager
- B. Corporate or programme management and Project Board
- C. Team Manager and external supplier
- D. Project Board and Project Manager
正解:A
質問 # 87
Which is a responsibility of a risk owner?
- A. Identify risks to the project that might occur in their department
- B. Determine project risk appetite
- C. Manage, monitor and control all aspects of an assigned risk
- D. Own and authorize the use of the risk budget to fund risk responses
正解:C
質問 # 88
Which is a minimum requirement for applying the quality theme?
- A. To appoint external reviewers for quality reviews
- B. To provide administrative support for quality controls
- C. To define quality criteria in product descriptions
- D. To define the project's approach to quality assurance
正解:C
解説:
A minimum requirement for applying the quality theme in PRINCE2 is to define quality criteria within product descriptions. This includes specifying what the product must do, the standards it must meet, and how quality will be evaluated, ensuring that all project products deliver against the agreed-upon requirements and standards.
= PRINCE2 7 Foundation handbook and online resources
質問 # 89
Which is a benefit of using PRINCE2?
- A. Is a method specifically designed for technical projects
- B. Can be used to manage both projects and programmes
- C. Provides for the efficient and economic use of management time
- D. Includes many of the proven planning techniques, such as critical path analysis
正解:C
解説:
Section: Volume A
質問 # 90
Why is the 'learn from experience' principle applied to a project?
- A. To enable the project team to repeat successes from previous projects
- B. To allow the project to be divided into management stages
- C. To enable the project team to use tolerances to delegate authority
- D. To enable the project team to develop a business case for the project
正解:A
解説:
The 'learn from experience' principle in PRINCE2is applied to ensure that lessons are sought, recorded, and acted upon throughout the life of the project. This principle helps the project team to replicate successes and avoid repeating past mistakes, thereby improving the efficiency and effectiveness of the project. References:
PRINCE2Foundation Handbook, Learn from Experience section.
質問 # 91
Which is an assumption about the PRINCE2 customer/supplier environment?
- A. The supplier will pay for the project
- B. The supplier will tailor the project's application of PRINCE2
- C. The customer will provide the resources to deliver the products
- D. The customer will specify the desired result
正解:D
質問 # 92
Which are purposes of the 'directing a project' process?
1. To enable the project board to be accountable for a project's success by making key decisions
2. To enable the project board to authorize work packages
3. To enable the project board to prepare the communication management approach
4. To enable the project board to exercise overall control of a project
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
正解:D
質問 # 93
Which theme estimates the cost of delivering the project?
- A. Business case
- B. PROGEESS
- C. Plans
- D. Change
正解:A
解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case
質問 # 94
Which is a recommended quality review team role?
- A. Assurance
- B. Project Support
- C. Administrator
- D. Project Manager
正解:C
解説:
Section: Volume B
質問 # 95
Which is a purpose of the 'managing a stage boundary' process?
- A. To exercise overall control over the project while delegating day-to-day management
- B. To assign work to be controlled by the team manager
- C. To enable the project board to approve the continuation of the project
- D. To define the work that needs to be done to deliver the project product
正解:C
解説:
Reference http://prince2.wiki/Managing_a_Stage_Boundary#Objective
質問 # 96
......
最新のPRINCE2-Foundation問題集試験問題を取得:https://drive.google.com/open?id=12pY6JxX9-Hop2RZbjaipDHz5m8HneKCI
完全版PRINCE2-Foundation練習テスト474別格な問題と解釈が待ってます。:https://www.jpntest.com/shiken/PRINCE2-Foundation-mondaishu