質問 # 122
What is the change authority role permitted to authorize?

  • A. Adjustments to the limits on the change budget
  • B. Changes to the project that do not exceed a defined budget
  • C. Risks to the project
  • D. Changes to stage tolerance

正解:B

解説:
Section: Volume B


質問 # 123
Which process defines the work to deliver the major products ensuring that an organization uses its resources effectively?

  • A. Starting up a project
  • B. Controlling a stage
  • C. Initiating a project
  • D. Managing product delivery

正解:D

解説:
The 'managing product delivery' process in PRINCE2 defines the work needed to deliver major products, ensuring effective use of organizational resources. This process focuses on the acceptance, execution, and delivery of project products according to agreed plans between the project manager and the team manager.References: PRINCE2 7 Foundation guide on the 'managing product delivery' process.


質問 # 124
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  • A. Only 1 is true
  • B. Both 1 and 2 are true
  • C. Only 2 is true
  • D. Neither 1 or 2 are true

正解:C

解説:
The statement that "The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved" is true. This process is crucial for ensuring that the project has met its objectives and that all remaining project deliverables are acceptable to stakeholders. The first statement is incorrect as the receipt of completed Work Packages is typically handled during the 'Managing a Stage Boundary' process rather than in the 'Closing a Project' process. References:
PRINCE2 Foundation manual, PRINCE2 official resources


質問 # 125
Which is 3 purpose of the 'plans! practice?

  • A. To enable an event that requires project management consideration to be controlled
  • B. To provide the standards against which the project products can be quality controlled
  • C. To enable control of opportunities and threats, that could Impact on delivery of the business objectives
  • D. To provide the basis of control against which a project's progress can be monitored

正解:D

解説:
The 'Plans' practice in PRINCE2 is essential for setting up the basis for project control. This includes monitoring, reporting, and responding to project progress in comparison to the planned objectives and outcomes. It ensures that the project stays on track in terms of scope, time, cost, quality, risk, and benefits, and provides a clear mechanism to gauge progress against the initial plan.References: = PRINCE2 7 Foundation Training Manual and official PRINCE2 website documentation


質問 # 126
Which is a minimum requirement for applying the organization theme?

  • A. To include external stakeholders on the project board
  • B. To define the experience required for each project role
  • C. To document the project management team structure
  • D. To train project team members in the use of PRINCE2

正解:C

解説:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Themes#Organization_Theme


質問 # 127
Which is a purpose of the 'initiating a project' process?

  • A. To establish a contract between the project management team and the commissioning organization
  • B. To ensure that prerequisites are in place before starting the project
  • C. To authorize the stage plan for the next management stage of the project
  • D. To ensure the project has a sound basis before asking the project board to authorize the project

正解:D

解説:
The purpose of the 'Initiating a Project' process in PRINCE2 is to ensure that the project has a sound basis before the project board is asked to make any major commitment to the project. This process is crucial for establishing a stable foundation for the project, detailing the necessary aspects such as scope, timescales, costs, risks, and benefits before full-scale implementation commences.References: PRINCE2 Foundation Manual


質問 # 128
Which is NOT a purpose of the Initiating a Project process?

  • A. Enable the Project Board to decide whether it is worthwhile to initiate a project
  • B. Enable a Project Board decision about the commitment of resources to a project
  • C. Establish solid foundations for a project
  • D. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved

正解:A


質問 # 129
Which is the BEST reason for a PRINCE? project to have at least two stages?

  • A. It enables the project board to approve the appointment of external contractors, when required
  • B. It enables the project team to change the scope of the project by agreeing the impact on the business case
  • C. It enables the project team to close the project in an orderly fashion
  • D. it enables the project board to decide whether to proceed with the delivery of the project product

正解:D

解説:
One of the best reasons for a PRINCE2 project to have at least two stages is that it provides structured decision points. At the end of each stage, the project board reviews progress and decides whether to proceed with the next stage, ensuring that the project remains viable and aligns with business objectives before committing further resources.References: PRINCE2 7 Foundation resources on stage management.


質問 # 130
When should the level of tailoring be defined?

  • A. As a response to issues and risks experienced
  • B. During the initiation stage
  • C. Before the project is triggered by the project mandate
  • D. When reviewing what has been learned to date

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.prince2primer.com/tailoring-prince2-methodology/


質問 # 131
Which process is used by the project board to respond to on exception report?

  • A. Managing product delivery
  • B. Directing a project
  • C. Managing a stage boundary
  • D. Controlling a stage

正解:B

解説:
The "Directing a Project" process is used by the project board to respond to an exception report. This process involves the project board making decisions on how to proceed when project tolerances are forecasted to be exceeded, which are typically communicated through an exception report.References: = PRINCE2 7 Foundation handbook and online resources


質問 # 132
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

  • A. Senior Supplier
  • B. Corporate/programme management
  • C. Executive
  • D. Senior User

正解:B


質問 # 133
Which is a purpose of the plans theme?

  • A. To establish the project's structure of accountability
  • B. To understand whether the targets are achievable
  • C. To identify, assess and control any potential changes to the baseline
  • D. To assess and control uncertainty

正解:B

解説:
Explanation/Reference:
Reference http://prince2.wiki/Plans


質問 # 134
Why is the 'initiating a project' process used?

  • A. To produce the required work packages
  • B. To fully understand how the project objectives will be achieved before committing significant resources
  • C. To enable corporate or programme management to give authorization to deliver a project
  • D. To decide which project approach is suitable for the project

正解:B

解説:
The 'Initiating a Project' process in PRINCE2 is crucial for establishing a solid foundation for the project. This process is used to ensure that there is a shared understanding of the reasons for undertaking the project, the way its objectives will be achieved, and the related commitments of time and resources before substantial resources are committed. References: PRINCE27 Foundation Handbook and official training materials.


質問 # 135
Which product identifies how often stakeholders require information?

  • A. Benefits management approach
  • B. Lessons report
  • C. Configuration item record
  • D. Communication management approach

正解:D


質問 # 136
Which are objectives of the 'managing a stage boundary' process?
1. To control the link between the people managing the project and the people producing the products
2. To approve requests for change received during the completed stage
3. To provide information to the project board on the performance of the current stage
4. To review and, if necessary, update the project management team structure and role descriptions

  • A. 2 and 3
  • B. 1 and 2
  • C. 3 and 4
  • D. 1 and 4

正解:C

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Managing_a_Stage_Boundary#Objective


質問 # 137
Which principle helps to ensure that all changes to the outputs are agreed?

  • A. Learn from experience
  • B. Defined roles and responsibilities
  • C. Manage by exception
  • D. Focus on products

正解:D

解説:
he PRINCE2 principle of "Focus on products" helps to ensure that all changes to the outputs are agreed upon. This principle emphasizes defining and delivering products that meet specific requirements, ensuring that changes are controlled and agreed upon through the proper product descriptions and project management processes. It helps manage scope and quality by focusing on product delivery requirements.References:
PRINCE2 Foundation Manual


質問 # 138
In which step of the 'risk management technique should the organization's environment be considered?

  • A. Plan
  • B. Identify
  • C. Implement
  • D. Assess

正解:B

解説:
Similar to question 397, the correct answer for considering the organization's environment in the risk management technique is during the 'Identify' step. This initial phase of risk management involves recognizing and recording risks after considering various environmental factors that can influence the project.References: PRINCE2 7 Foundation guide on risk management.


質問 # 139
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

  • A. Closing a Project
  • B. Directing a Project
  • C. Controlling a Stage
  • D. Managing a Stage Boundary

正解:D


質問 # 140
What problem may occur if projects are not aligned with corporate business strategy?

  • A. The control of projects may be poor
  • B. The project management approaches used may differ
  • C. The outputs may be of poor quality
  • D. The objectives of different projects may overlap

正解:B


質問 # 141
What product is used to maintain a record of those who have an interest in the project and their information requirements?

  • A. Project Plan
  • B. Communication Management Strategy
  • C. Project Product Description
  • D. Project Brief

正解:B


質問 # 142
Which is a benefit of using PRINCE2?

  • A. Enables the management of projects as well as of 'business as usual' activities
  • B. Avoids the need to involve corporate or programme management
  • C. Can be tailored by leaving out elements of the method for some projects
  • D. Can be applied to any type of project

正解:D


質問 # 143
Which of the following statements about the Closing a Project process are true?
1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage.
2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  • A. Only 1 is true
  • B. Both 1 and 2 are true
  • C. Only 2 is true
  • D. Neither 1 or 2 are true

正解:C

解説:
Section: Volume A


質問 # 144
Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

  • A. project's cost tolerance
  • B. project's risk tolerance
  • C. project budget
  • D. change budget

正解:C


質問 # 145
Which is a purpose of the 'controlling a stage' process?

  • A. To select and implement actions that will resolve deviations from a plan within tolerance
  • B. To obtain approvals for products delivered in a work package
  • C. To update a project plan to incorporate the actuals from a stage plan
  • D. To produce a team plan for the work to be assigned to a team manager

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Controlling_a_Stage#Purpose


質問 # 146
......


試験は60の多肢選択問題から構成され、60分で解答しなければなりません。問題は、原則、テーマ、プロセス、および管理製品を含むPRINCE2手法の理解を候補者がテストするように設計されています。問題は、質問プールからランダムに選択され、2つの試験が同じにならないようになっています。

 

PRINCE2Foundation豪華セット学習ガイドにはオンライン試験エンジン:https://www.jpntest.com/shiken/PRINCE2Foundation-mondaishu

PRINCE2Foundationテスト準備トレーニング練習試験問題練習テスト:https://drive.google.com/open?id=1K2-fPzsXGG3hT2QfjL01QDUgokQtUeHl

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡