質問 # 117
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- A. Managing a Stage Boundary
- B. Directing a Project
- C. Starting up a Project
- D. Controlling a Stage
正解:D
質問 # 118
Why can PRINCE2 be applied to any type of project?
- A. Because it provides the project manager with procedures for managing project risks and issues
- B. Because it provides the project manager with a planning procedure to plan the project more effectively
- C. Because it allows each member of the project management team to fully understand their role and responsibilities
- D. Because it separates the management of the project from the specialist work needed to deliver the products
正解:C
解説:
Reference https://www.prince2.com/uk/prince2-methodology
質問 # 119
What is used to identify any organization or interested party who needs to be informed of project closure?
- A. Project management team structure
- B. Project Brief
- C. Configuration Management Strategy
- D. Communication Management Strategy
正解:D
質問 # 120
What product forms the contract' between the Project Board and the Project Manager?
- A. Project mandate
- B. Project Plan
- C. Project Brief
- D. Project Initiation Documentation
正解:D
質問 # 121
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
- A. Issue Register
- B. Follow-on action recommendations
- C. Off-specifications
- D. Risk Register
正解:B
解説:
Section: Volume A
質問 # 122
Which is an objective of the 'directing a project' process?
- A. To respond to the project mandate by starting up a project
- B. To tailor the project's products and roles so that the project suits the circumstances
- C. To ensure the stage products are delivered to the stated quality standards
- D. To provide an interface between the project and corporate management
正解:D
解説:
Section: Volume B
Explanation/Reference: https://www.greycampus.com/opencampus/prince-2-practitioner/purpose-of-directing-a-project- process-in-prince2
質問 # 123
Which is a minimum requirement for applying the change theme?
- A. To produce a breakdown of the products to be produced
- B. To tailor all changes to improve the quality of the project
- C. To ensure each change is managed as an exception
- D. To identify whether an issue affects the continuation of the project
正解:C
解説:
Section: Volume B
質問 # 124
Identify the missing words in the following sentence.
The project manager [ ? ] for day-to-day management of the project.
- A. has responsibility
- B. decides who is responsible
- C. and the project board are responsible
- D. and the team manager(s) are accountable
正解:A
解説:
Explanation
Reference http://prince2.wiki/Directing_a_Project
質問 # 125
Which is an objective of the Starting up a Project process?
- A. Confirm that there is a validmethod in place to measure the expected project benefits
- B. Prevent projects with unrealistic delivery dates from being initiated
- C. Obtain approval from corporate or programme management for the Communication
Management Strategy - D. Approve allProduct Descriptions prior to project initiation
正解:B
質問 # 126
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
- A. controls
- B. project management team
- C. stages
- D. products
正解:D
質問 # 127
Which risk response type is a recommended response to both an opportunity and a threat?
- A. Reduce
- B. Avoid
- C. Reject
- D. Share
正解:D
質問 # 128
Which is an objective of the Closing a Project process?
- A. Perform any post-project reviews
- B. Create a Benefits Review Plan
- C. Review the performance of the project against its baseline
- D. Review and approve the plan for project closure
正解:C
解説:
The objective of the Closing a Project process in PRINCE2 includes reviewing the performance of the project against its baseline. This ensures that all objectives have been achieved, the project has delivered the required products, and stakeholders are satisfied with the outcomes. It provides a formal closure to the project by ensuring all project work is completed and assessed. References: PRINCE2 Foundation manual, PRINCE2 official resources
質問 # 129
Identify the missing words in the following sentence. An objective of the Closing a Project process is to ensure that provision has been made to address [?] through follow-on action recommendations.
- A. open issues and risks
- B. the measurement of benefits NOT yet realized
- C. the release of resources
- D. the handover of products
正解:A
質問 # 130
Which is an objective of the Closing a Project process?
- A. Assess any benefits that have already been realized
- B. Produce a Benefits Review Plan to identify what benefits are expected
- C. Check that all benefits are realized before closing a project
- D. Prepare the plan for the next stage
正解:A
質問 # 131
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
- A. Executive
- B. Corporate group
- C. Project Board
- D. Project Assurance
正解:B
質問 # 132
Why is it necessary to apply the 'defined roles and responsibilities' principle?
- A. Because the project manager should represent all the stakeholders of the project
- B. Because the user and supplier interests should be involved on a need-to-know basis
- C. Because the people involved in a project should know what is expected of them
- D. Because the project management team should be cross-functional
正解:C
解説:
The 'defined roles and responsibilities' principle in PRINCE2 is essential because it ensures clarity and efficiency in project management. By clearly defining roles and responsibilities, everyone involved in the project understands their tasks, responsibilities, and reporting relationships. This clarity helps in reducing confusion and improving communication and accountability among project team members.References:
PRINCE2 Foundation Manual
質問 # 133
Which role is responsible for the quality of the specialist products delivered in the project?
- A. Executive
- B. Senior user
- C. Senior supplier
- D. Project assurance
正解:C
解説:
Explanation
Reference http://www.fmdconsultants.co.uk/p2_roles_and_responsibilities_v01.docx
質問 # 134
Identify the missing word(s) in the following sentence.
The 'controlling a stage' process is used to manage and control each [ ? ] of a project.
- A. benefit
- B. team plan
- C. delivery stage
- D. delivery step
正解:C
解説:
The 'Controlling a Stage' process in PRINCE2 is used to manage and control each 'delivery stage' of a project. This process focuses on the day-to-day management of the project stages, ensuring that the project remains within its agreed tolerances and effectively addressing issues as they arise.References: PRINCE2 Foundation Manual
質問 # 135
Which activity is part of the recommended risk management procedure?
- A. Sending information to stakeholders about risks to the projects
- B. Allocating a budget to investigate issues
- C. Reviewing risk management practices to ensure that they are performing effectively
- D. Resolving conflicts between the project and the programme board
正解:C
質問 # 136
Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
- A. project assurance
- B. senior user
- C. change authority
- D. project support
正解:D
解説:
Section: Volume B
Explanation
Explanation/Reference: http://prince2.wiki/Roles_and_responsibilities
質問 # 137
What must be produced to meet the minimum requirements for applying the change theme?
- A. Details of the status of all products being produced
- B. Details of the decisions taken on all issues
- C. Documentation on the corrective action for an issue
- D. Documentation on the version of each product
正解:B
解説:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Themes#Change_Theme
質問 # 138
Which should be funded from a change budget?
- A. The Starting up a Project process
- B. A change to a plan, within allocated tolerances, due to poor estimating
- C. A fallback plan
- D. An agreed change to the scope of a project
正解:D
質問 # 139
......