質問 # 154
Which is a purpose of the 'controlling a stage' process?

  • A. To produce a team plan for the work to be assigned to a team manager
  • B. To obtain approvals for products delivered in a work package
  • C. To update a project plan to incorporate the actuals from a stage plan
  • D. To select and implement actions that will resolve deviations from a plan within tolerance

正解:D

解説:
Explanation
Reference http://prince2.wiki/Controlling_a_Stage#Purpose


質問 # 155
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.

  • A. Processes
  • B. Themes
  • C. Techniques
  • D. Principles

正解:D


質問 # 156
Which is a benefit of using PRINCE2?

  • A. Is a method specifically designed for technical projects
  • B. Can be used to manage both projects and programmes
  • C. Provides for the efficient and economic use of management time
  • D. Includes many of the proven planning techniques, such as critical path analysis

正解:C

解説:
Section: Volume A


質問 # 157
Why is it crucial that the Project Product Description clearly defines acceptance methods?

  • A. Defines how all project products will be reviewed and approved
  • B. Enables Project Assurance to authorize quality activities
  • C. Defines how it will be proven that the completed project product meets the customer's expectations
  • D. Provides confirmation that all project products have met their quality criteria

正解:C

解説:
The Project Product Description in PRINCE2 should clearly define acceptance methods to ensure that there is a concrete plan for demonstrating that the final project product meets the customer's quality expectations.
This is crucial for aligning the project's outputs with the customer's needs and expectations. While it is part of broader quality control and assurance mechanisms, the specific role of defining acceptance methods is to make clear how compliance with quality expectations will be verified.References: PRINCE2 7 Foundation study guide and documents.


質問 # 158
Which is a Benefits Review Plan used to assess?

  • A. How the project's products have performed when in operational use
  • B. The effectiveness of the project strategies
  • C. The suitability of the project management team structure and membership
  • D. The progress of the project against its plans

正解:A


質問 # 159
Which should be funded by a change budget?

  • A. Initiation stage
  • B. Increase in agreed scope
  • C. Change Authority
  • D. Handover activities

正解:B


質問 # 160
Which is NOT obtained from a product's Product Description?

  • A. The development method to be used
  • B. The qualitymethod to be used
  • C. Who will approve the product
  • D. The product's quality criteria

正解:A


質問 # 161
What should be implemented using a risk budget?
1. A request for change
2. A contingent plan
3. Actions to avoid a risk from occurring
4. Responses to dis-benefits

  • A. 1 and 4
  • B. 1 and 2
  • C. 3 and 4
  • D. 2 and 3

正解:D

解説:
A risk budget should be used to implement contingency plans (2) and actions to avoid a risk from occurring (3). This budget is set aside to fund specific actions that are part of the project's risk management strategy, enabling proactive and reactive responses to identified risks, ensuring the project remains on track despite uncertainties.References: = PRINCE2 7 Foundation handbook and online resources


質問 # 162
Which is a purpose of the 'closing a project' process?

  • A. To establish mechanisms to judge whether the project is still viable
  • B. To confirm the project has nothing more to deliver
  • C. To provide the project board with information to judge the success of a stage
  • D. To establish mechanisms for forecasting project objectives

正解:B

解説:
Explanation/Reference:
Reference http://prince2.wiki/Closing_a_Project#Objective


質問 # 163
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

  • A. project management team
  • B. controls
  • C. products
  • D. stages

正解:C

解説:
The Quality theme in PRINCE2 ensures that the project's products meet the required standards and fulfill the business needs. This theme guides the management and control of quality throughout the project, emphasizing the importance of delivering products that align with the business's expectations. References:
PRINCE2 Foundation Training Manual; PRINCE2 2017 Foundation handbook.


質問 # 164
The project manager needs to record the impact assessment for a specific business opportunity.
In which management product should the project manager record this?

  • A. Quality register
  • B. Issue report
  • C. Risk register
  • D. Issue register

正解:B

解説:
The project manager should record the impact assessment for a specific business opportunity in an 'Issue Report'. This management product is used to detail particular issues that might affect the project, including opportunities (which are treated like positive risks), and provides a basis for decision-making regarding these issues.References: PRINCE2 7 Foundation materials on issue management and related documentation.


質問 # 165
Which should be funded by a change budget?

  • A. Initiation stage
  • B. Increase in agreed scope
  • C. Change Authority
  • D. Handover activities

正解:B


質問 # 166
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?

  • A. No specific documents related to benefits are necessary
  • B. Statements of actual versus forecast benefits at reviews
  • C. The management actions needed to ensure benefits are realized
  • D. The senior user's responsibilities for realizing benefits

正解:D


質問 # 167
Which of the following is the Business Case used for during the Managing a Stage Boundary process?

  • A. Enable the Project Board to decide whether or not to authorize the project
  • B. Justify the initiation of a project
  • C. Justify the continuing viability of the project
  • D. Enable the Project Board to decide whether or not to authorize project closure

正解:C


質問 # 168
Who should act as the communication channel between a project and corporate or programme
management?

  • A. Project Support
  • B. Project Manager
  • C. Project Board
  • D. Project Assurance

正解:C


質問 # 169
Which is a minimum requirement for applying the quality theme?

  • A. To use the prescribed approach to quality management
  • B. To use lessons to inform quality planning
  • C. To use external quality standards for quality control
  • D. To use user stories to inform the project product description

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Quality


質問 # 170
Which is an objective of the Controlling a Stage process?

  • A. Prepare a Stage Plan for the next stage
  • B. Prevent scope creep' by monitoring products for uncontrolled change
  • C. Obtain approvals for completed products
  • D. Make arrangements to address all open issues and risks, with follow-on action recommendations

正解:B


質問 # 171
Which product is used by the Project Manager to authorize work?

  • A. Team Plan
  • B. Product Description
  • C. Stage Plan
  • D. Work Package

正解:D


質問 # 172
Which is a purpose of the business case theme?

  • A. To establish a viable investment proposition
  • B. To identify which role is responsible for producing the business case
  • C. To establish the controls to manage changes that may impact the project benefits
  • D. To identify the project's outputs

正解:D

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case


質問 # 173
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.

  • A. a temporary
  • B. an external
  • C. a technical
  • D. a corporate

正解:A


質問 # 174
......


PRINCE2(プロジェクトINコントロール環境)は、世界中のさまざまな産業で使用されている広く認知されたプロジェクト管理手法です。PRINCE2ファウンデーション試験は、PRINCE2が提供する認定の最初のレベルです。この試験は、PRINCE2の手法、原則、テーマ、プロセスに関する候補者の知識と理解をテストするように設計されています。PRINCE2ファウンデーション試験は、プロジェクト管理のキャリアを開始したい個人や、既存のスキルを向上させたい人々にとって必須のステップです。

 

試験問題解答ブレーン問題集でPRINCE2Foundation試験問題集PDF問題:https://www.jpntest.com/shiken/PRINCE2Foundation-mondaishu

PRINCE2Foundationテスト準備トレーニング練習試験問題練習テスト:https://drive.google.com/open?id=1lGo6ZoScvg0Ubdk9mcRT5H_CniR-PEmy

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡