質問 # 270
If an informal issue is defined as a problem or concern, where should it first be recorded?

  • A. Issue Register
  • B. Daily Log
  • C. Exception Report
  • D. Risk Register

正解:B


質問 # 271
Which is a minimum requirement for applying the business case theme?

  • A. To monitor changes to the project plan to identify exceptions
  • B. To define the actions required to confirm the project's benefits are realized
  • C. To provide statements of actual benefits at benefits reviews
  • D. To report on project performance at project closure

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference https://www.whatisprince2.net/prince2-theme-business-case.php


質問 # 272
Who represents the three project interests on a project?

  • A. Project board
  • B. External project stakeholders
  • C. Project support
  • D. Project manager

正解:A

解説:
Explanation/Reference:
Reference http://prince2.wiki/Organization#Three_Project_Interests


質問 # 273
Which is a minimum requirement for applying the organization theme?

  • A. The roles of the project management team must be combined, wherever possible
  • B. The project manager must be appointed from the supplier organization
  • C. The frequency of communication to the project's stakeholders must be documented
  • D. Each member of the project management team must have a written role description

正解:C

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Themes#Organization_Theme


質問 # 274
When is the 'managing a stage boundary' process used?

  • A. Near the end of delivery stages
  • B. Immediately after the project board has authorized the next stage
  • C. Immediately alter the project board has authorized the previous stage
  • D. Near the end of each stage

正解:D

解説:
The 'Managing a Stage Boundary' process is used near the end of each stage of a project. This process includes the review of the current stage, preparation for the project board to authorize the next stage, updating a project plan, and, if necessary, updating the business case and project initiation documentation.
= PRINCE2 7 Foundation handbook and online resources


質問 # 275
Which statement describes the Implement' step within the recommended risk management procedure?

  • A. Assess the proximity of a risk
  • B. Identify the level of risks that can be tolerated by the project
  • C. Implement the responsibilities for risks defined in the Risk Management Strategy
  • D. Take planned action to respond to a risk

正解:D


質問 # 276
Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects,

  • A. setting up the required project controls
  • B. producing an achievable Project Plan
  • C. obtaining approval from all stakeholders
  • D. preventing poorly-conceived projects from ever being initiated

正解:D


質問 # 277
Which process is triggered towards the end of the final stage when all the assigned work has been completed?

  • A. Closing a Project
  • B. Managing Product Delivery
  • C. Managing a Stage Boundary
  • D. Controlling a Stage

正解:A

解説:
The Closing a Project process in PRINCE2 is triggered towards the end of the final stage when all assigned work has been completed. This process is designed to ensure that all project objectives have been achieved, all products have been delivered, and the project can be formally closed and evaluated for success and areas of improvement. References: PRINCE2 Foundation manual, PRINCE2 official resources


質問 # 278
Why is the 'learn from experience' principle applied to a project?

  • A. To enable the project team to develop a business case for the project
  • B. To enable the project team to repeat successes from previous projects
  • C. To allow the project to be divided into management stages
  • D. To enable the project team to use tolerances to delegate authority

正解:B

解説:
Explanation/Reference:
Reference https://link.springer.com/chapter/10.1007/978-3-319-23000-9_4


質問 # 279
Who represents the three project interests on a project?

  • A. Project board
  • B. External project stakeholders
  • C. Project support
  • D. Project manager

正解:A

解説:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Organization#Three_Project_Interests


質問 # 280
Which is a true statement about PRINCE2 event-driven controls.

  • A. Checkpoint Reports are event-driven controls
  • B. Event-driven controls take place at predefined periodicintervals
  • C. Event-driven controls are used for decision making
  • D. Event-driven controls are produced at the frequency defined in a Work Package

正解:C


質問 # 281
In what product should the quality criteria for a specialist product be recorded?

  • A. Quality Management Strategy
  • B. Product Description
  • C. Quality Register
  • D. Project Product Description

正解:B


質問 # 282
Which is a purpose of the business case theme?

  • A. To establish a viable investment proposition
  • B. To identify the project's outputs
  • C. To identify which role is responsible for producing the business case
  • D. To establish the controls to manage changes that may impact the project benefits

正解:A

解説:
The purpose of the Business Case theme in PRINCE2 is to establish a viable investment proposition. It justifies the investment in the project through an ongoing assessment of benefits, costs, and risks, ensuring that the project remains desirable, viable, and achievable throughout its life.
PRINCE2 7 Foundation Source: PRINCE2 Foundation handbook and online resources


質問 # 283
Which is a valid statement about the Project Support role?

  • A. Can be performed by the Project Manager
  • B. Is an optional role for a PRINCE2 project
  • C. Produces Checkpoint Reports for the Project Manager
  • D. Can be combined with the Project Assurance role

正解:A


質問 # 284
Which of the following statements about the Project Initiation Documentation are true?
1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project.
2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

  • A. Only 2 is true
  • B. Both 1 and 2 are true
  • C. Neither 1 or 2 are true
  • D. Only 1 is true

正解:B

解説:
Section: Volume A


質問 # 285
Which is a responsibility of a risk owner?

  • A. Identify risks to the project that might occur in their department
  • B. Manage, monitor and control all aspects of an assigned risk
  • C. Determine project risk appetite
  • D. Own and authorize the use of the risk budget to fund risk responses

正解:B

解説:
Section: Volume B


質問 # 286
Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

  • A. stage cost tolerance
  • B. Work Package cost tolerance
  • C. project cost tolerance
  • D. product cost tolerance

正解:B


質問 # 287
Which describes a risk effect?

  • A. The issue which is affecting the project and has resulted in a risk
  • B. The uncertainty expressed as a negative or favourable occurrence
  • C. The change in the statusof a risk in response to actions taken to control it
  • D. The impact(s) on the project objectives should the threat or opportunity occur

正解:D


質問 # 288
The project board is reviewing the project initiation documentation (PID) to decide whether the project should continue or close. What should the project board ensure the PID is aligned with?

  • A. The business objectives
  • B. The business' existing governance practices
  • C. The project's delivery method
  • D. The ways of working used on previous projects

正解:A

解説:
hen the project board reviews the Project Initiation Documentation (PID), it is essential to ensure that the PID is aligned with the business objectives. The PID should encapsulate the project's definition, including the reasons for undertaking the project, the benefits expected, and how it aligns with the broader business goals.
Ensuring this alignment helps validate that the project remains viable and worthwhile as it progresses.
References: (PRINCE27 Foundation Handbook, AXELOS)


質問 # 289
......

無料セールまもなく終了!100%有効なPRINCE2Foundation試験:https://www.jpntest.com/shiken/PRINCE2Foundation-mondaishu

検証済みPRINCE2Foundation試験解答合格確定させる:https://drive.google.com/open?id=1exeTu8phPuFx-u2ZoZhQO3rIg8jgaLxB

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡