質問 # 48
An electronics firm was experiencing high rejections in their multiple connector manufacturing departments. "p" charts were introduced as part of a program to reduce defectives. Control limits were based on prior history, using the formula:

P' is the historical value of percent defective and n is the number of pieces inspected each week. After six weeks, the following record was accumulated

1,000 pieces were inspected each week in each department. Which department(s) exhibited a point or points out of control during this period (round off calculations to nearest tenth of a percentage point)?

  • A. Department 106.
  • B. All of the department.
  • C. Department 105.
  • D. Department 104.

正解:B


質問 # 49
The Shewhart or Deming cycle is often referred to as

  • A. Problem solving flow chart.
  • B. The affinity diagram.
  • C. Plan-do-check-act.
  • D. The cause and effect diagram.

正解:C

解説:
Explanation


質問 # 50
The maximum allowable percent defective for the process average is the

  • A. AQL
  • B. AOQL
  • C. LPTD
  • D. RQL

正解:A


質問 # 51
The risk priority number (RPN) is determined by the

  • A. product of reliability value, criticality number, and failure mode
  • B. product of frequency of the occurrence, severity, and detection ratings
  • C. sum of reliability value, criticality number, and failure mode
  • D. sum of frequency of the occurrence, severity, and detection ratings

正解:B

解説:
The Risk Priority Number (RPN) in FMEA is determined by the product of the frequency of occurrence, severity, and detection ratings. This multiplication helps in quantifying the risk associated with each potential failure mode, allowing for prioritization of corrective actions based on the highest risk areas.


質問 # 52

A in this drawing, the symbol is being used to indicate the

  • A. datum
  • B. feature
  • C. basic definition
  • D. reference plane

正解:A

解説:
In the provided drawing, the symbol marked "A" is being used to indicate a datum. A datum is a reference point, line, or surface used as a basis for measurement and to establish the location or orientation of other features. It serves as a starting point for dimensional control and ensures consistency in the manufacturing process.


質問 # 53
A two-way analysis of variance has r levels for one variable and c levels for the second variable with 2 observations per cell. The degree of freedom for interaction is

  • A. 2(r-1)(c-1)
  • B. 2(r)(c)
  • C. (r-1)(c-1)
  • D. rc-1

正解:C


質問 # 54
Which of the following nondestructive testing methods can be used to evaluate sub-surface discontinuities in aluminum bar stock?
I. Microwave.
II. Magnetic particle.
III. Pulse echo.
IV. Eddy current.

  • A. III and IV only
  • B. I, II and IV only
  • C. I and IV only
  • D. I and III only

正解:A


質問 # 55
A system was designed with 3 capacitors. When the system is first activated all capacitors are operating.
The system continues to operate as long as at least 1 capacitor is operating. This is an example of

  • A. A series system.
  • B. Redundancy.
  • C. An active parallel system.
  • D. A standby parallel system.

正解:C


質問 # 56
A company uses four components (W. X. Y. and Z) to create its final product. The source and time factors for these components are listed below. What is die critical path for this company's final product?
ComponentSourceAcquisition TimeInstallation TimePredecessor Steps
WInternaln/a4 weeksNone
XExternal5 weeks4 weeksNone
YInternaln/a4 weeksW.X.Z
ZInternaln/a6 weeksNone

  • A. 13 weeks
  • B. 9 weeks
  • C. 8 weeks
  • D. 6 weeks

正解:A

解説:
The critical path is the longest path through the project, determining the shortest time to complete the project.
The components and their dependencies are:
* W: Installation Time = 4 weeks
* X: Acquisition Time = 5 weeks + Installation Time = 4 weeks, Total = 9 weeks
* Y: Predecessors are W, X, Z. Therefore, Y cannot start until W, X, and Z are completed.
* Z: Installation Time = 6 weeks
To find the critical path:
* W: 4 weeks
* X: 9 weeks
* Z: 6 weeks
Y depends on W, X, and Z, so Y starts after the longest time among W, X, and Z, which is 9 weeks (X), and Y takes 4 weeks. Thus, the total time is 9 weeks + 4 weeks = 13 weeks.
References:
* Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
* PMBOK Guide (2017). Project Management Institute.


質問 # 57
Compute the upper control limit for an s chart, based on a sample size of 10, if the process is in control with a mean of 40 and a sample standard deviation of 7.

  • A. 0
  • B. 13.3
  • C. 11.7
  • D. 15.7

正解:C


質問 # 58
As a commonly used problem solving technique, which of the following would be the BEST application of a Pareto chart?
. To determine when to make proactive adjustments to a process.
. To differentiate between major and minor problem areas.
. To gather data and to design experimental controlled changes.
. To evaluate the results of other problem solving techniques upon the product or service.

  • A. II and III only
  • B. II and IV only
  • C. I, II, III and IV
  • D. I and II only

正解:B


質問 # 59
A company incurred the following quality costs last month.
Incoming material inspection$5,000
Process scrap$3,000
In-process reworkS450
Control engineering$450
Warranty$2,000
Customer complaints$6,000
Product liability$1,000
What is the total cost of external failures?

  • A. $8000
  • B. $6000
  • C. $9450
  • D. $9000

正解:D

解説:
The total cost of external failures includes warranty, customer complaints, and product liability. Summing these costs:
* Warranty: $2,000
* Customer complaints: $6,000
* Product liability: $1,000
Total external failure cost = $2,000 + $6,000 + $1,000 = $9,000


質問 # 60
A bin contains 40 pills with a weight of 3.1 gm. each, 30 pills weighing 3.2 gms each and 10 pills weighing 3.3 gms each. The weight of an average pill is found from

  • A. Option A
  • B. Option B
  • C. Option D
  • D. Option C

正解:C


質問 # 61
Which of the following are likely to be positive actions in obtaining a supplier's commitment to quality improvement?
I. Involving the supplier early in the product development stage.
II. Partially reimbursing the supplier, when the product is rejected.
III. Establishing a firm schedule of required product quantities and dates.
IV. Providing meaningful and timely quality performance feedback.

  • A. I, II and IV only
  • B. I, II, III and IV
  • C. I and IV only
  • D. I, III and IV only

正解:D


質問 # 62
Which of the following activities is a critical component of the closing meeting of an external audit?

  • A. Providing an explanation of the findings
  • B. Determining appropriate corrective actions to take
  • C. Establishing the date for a follow-up audit
  • D. Distributing the final audit report

正解:A

解説:
During the closing meeting of an external audit, a critical component is providing an explanation of the findings to ensure that all parties understand the audit results. This step is essential for clarity and sets the stage for discussing potential corrective actions and follow-up activities. Reference: "The ISO 19011:2018 Guidelines for Auditing Management Systems," which outlines the key components of audit closing meetings.


質問 # 63
......

CQE問題集には100%厳密検証された問題と解答で合格保証もしくは全額返金:https://www.jpntest.com/shiken/CQE-mondaishu

合格させるASQ CQE試験には練習テスト問題集豪華お試しセット:https://drive.google.com/open?id=10YKkjPDyOwaGWKUwy5HAVyV8suVvWOqw

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡