質問 # 66
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?
- A. 193 days
- B. 168 days
- C. 91 days
- D. 183 days
正解:D
質問 # 67
Activity C is a
- A. Milestone.
- B. Contentious activity.
- C. Continuous activity.
- D. 1-day activity.
正解:A
質問 # 68
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?
- A. 7 work days
- B. 15 workdays
- C. 8 work days
- D. 18 work days
正解:C
質問 # 69
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
- A. LS.11001 + 25 days.
- B. EF.11001 + 1 day.
- C. 02-19-04.
- D. EF.11001.
正解:C
質問 # 70
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Direct or indirect cost.
- B. Labor hours or dollars.
- C. Linear feet or dollars.
- D. Earned or budgeted cost yearly.
正解:D
質問 # 71
The work breakdown structure is used to organize
- A. The smallest defined work packet
- B. The chart of accounts
- C. Similar activity coding of schedule activities
- D. "Smart activity ID codes" representing similar items of scheduled work
正解:A
質問 # 72
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that
- A. An out-of-sequence activity cannot resume until all predecessors are finished.
- B. There is no such thing.
- C. It is calculated using the original logic.
- D. It is calculated using logic reflecting out-of-sequence progress.
正解:C
質問 # 73
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?
- A. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
- B. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
- C. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
正解:C
質問 # 74
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. The schedule is projecting an "early completion".
- B. Different calendars are assigned to certain activities in the logical chain.
- C. The schedule has too much detail to reflect an accurate critical path.
- D. Certain activities in the critical path have no successors.
正解:D
質問 # 75
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 4001, 5001 and 6001.
- B. 4001 and 5001.
- C. 2004.
- D. 2003 and 7001.
正解:B
質問 # 76
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?
- A. 3.9% (1 : 25.708)
- B. 9.1% (1 : 11.000).
- C. 2.3% (1 : 43.501).
- D. 8.6% (1 : 11.591)
正解:C
質問 # 77
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Start and finish constraints.
- B. Multiple calendars.
- C. Preferential logic.
- D. Front end loading.
正解:D
質問 # 78
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
- A. Finish-no-earlier constraint on the last activity
- B. Finish-no-earlier constraint on the first activity
- C. Finish-no-later constraint on the last activity
- D. Start-no-later constraint on the first activity
正解:C
質問 # 79
The amount of time that an activity can be delayed from its early start date without delaying project completion is called
- A. Negative float.
- B. Total float.
- C. Free float.
- D. Interfering float.
正解:B
質問 # 80
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?
- A. Delay manufacturing by 5 days.
- B. Expedite printing by 5 days.
- C. Expedite packaging by 5 days.
- D. Delay product release by 5 days.
正解:D
質問 # 81
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- C. The activities run concurrently.
- D. The activities occur in series with a 15-day lag.
正解:D
質問 # 82
What is a key first step in developing a critical path method schedule?
- A. Drawing the logic diagram.
- B. Drawing a bar chart of the key phrases of the work.
- C. Setting out the resource to be used and its limitations.
- D. Defining the execution plan to meet the required scope of work.
正解:A
質問 # 83
A driving relationship is _____________________.
- A. A finish-to-start relationship.
- B. A critical relationship.
- C. The link between a predecessor and the activity whose dates it controls.
- D. The link between two related activities.
正解:C
質問 # 84
What is the result of a forward pass calculation?
- A. Critical path
- B. Value of total float for individual activities
- C. Early start and early finish date for individual activities
- D. Value of free float for individual activities
正解:C
質問 # 85
How much Total Float does drafting the product manual have?
- A. 5 workdays.
- B. 0 workdays.
- C. 10 workdays.
- D. 15 workdays.
正解:C
質問 # 86
What is the cycle time?
- A. 14 minutes
- B. 6 minutes
- C. 17 minutes
- D. 5 minutes
正解:C
質問 # 87
What is the free float for Activity F?
- A. 0months.
- B. 1months.
- C. 2month.
- D. 3 months.
正解:A
質問 # 88
What was the original planned duration for Activity A through Activity G?
- A. 24.
- B. 25.
- C. 28.
- D. 26.
正解:C
質問 # 89
When resource leveling craft labor for a critical path schedule, the scheduler
- A. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
- B. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
- C. Need only consider the non-union crafts persons.
- D. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
正解:D
質問 # 90
......