合格させるAACE-PSP試験問題で実際テストエンジンPDFには120問題あります [Q66-Q90]

Share

合格させるAACE-PSP試験問題で実際テストエンジンPDFには120問題あります

最新をゲットせよ!AACE-PSP認定練習テスト問題の試験問題集

質問 # 66
Using the "normal" schedule, theoretically construct a hammock for activities 2001 through 2004. What is the duration of the hammock?

  • A. 193 days
  • B. 168 days
  • C. 91 days
  • D. 183 days

正解:D


質問 # 67
Activity C is a

  • A. Milestone.
  • B. Contentious activity.
  • C. Continuous activity.
  • D. 1-day activity.

正解:A


質問 # 68
Assuming that you had only one crane capable of 30 lifts per day, 3 column pours requiring 28 lifts each, plus associated assorted work requiring an additional 150 lifts, what is the minimum planned working duration for this work?

  • A. 7 work days
  • B. 15 workdays
  • C. 8 work days
  • D. 18 work days

正解:C


質問 # 69
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. LS.11001 + 25 days.
  • B. EF.11001 + 1 day.
  • C. 02-19-04.
  • D. EF.11001.

正解:C


質問 # 70
An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  • A. Direct or indirect cost.
  • B. Labor hours or dollars.
  • C. Linear feet or dollars.
  • D. Earned or budgeted cost yearly.

正解:D


質問 # 71
The work breakdown structure is used to organize

  • A. The smallest defined work packet
  • B. The chart of accounts
  • C. Similar activity coding of schedule activities
  • D. "Smart activity ID codes" representing similar items of scheduled work

正解:A


質問 # 72
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. An out-of-sequence activity cannot resume until all predecessors are finished.
  • B. There is no such thing.
  • C. It is calculated using the original logic.
  • D. It is calculated using logic reflecting out-of-sequence progress.

正解:C


質問 # 73
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?

  • A. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
  • B. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
  • C. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.

正解:C


質問 # 74
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?

  • A. The schedule is projecting an "early completion".
  • B. Different calendars are assigned to certain activities in the logical chain.
  • C. The schedule has too much detail to reflect an accurate critical path.
  • D. Certain activities in the critical path have no successors.

正解:D


質問 # 75
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?

  • A. 4001, 5001 and 6001.
  • B. 4001 and 5001.
  • C. 2004.
  • D. 2003 and 7001.

正解:B


質問 # 76
Based on the stated costs, what percentage of the total cost comes from the 2000 series of activities?

  • A. 3.9% (1 : 25.708)
  • B. 9.1% (1 : 11.000).
  • C. 2.3% (1 : 43.501).
  • D. 8.6% (1 : 11.591)

正解:C


質問 # 77
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Start and finish constraints.
  • B. Multiple calendars.
  • C. Preferential logic.
  • D. Front end loading.

正解:D


質問 # 78
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

  • A. Finish-no-earlier constraint on the last activity
  • B. Finish-no-earlier constraint on the first activity
  • C. Finish-no-later constraint on the last activity
  • D. Start-no-later constraint on the first activity

正解:C


質問 # 79
The amount of time that an activity can be delayed from its early start date without delaying project completion is called

  • A. Negative float.
  • B. Total float.
  • C. Free float.
  • D. Interfering float.

正解:B


質問 # 80
During proofing of the product manual, a problem was discovered requiring 15 days additional time to effect a correction. How can the date of availability be maintained?

  • A. Delay manufacturing by 5 days.
  • B. Expedite printing by 5 days.
  • C. Expedite packaging by 5 days.
  • D. Delay product release by 5 days.

正解:D


質問 # 81
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • B. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • C. The activities run concurrently.
  • D. The activities occur in series with a 15-day lag.

正解:D


質問 # 82
What is a key first step in developing a critical path method schedule?

  • A. Drawing the logic diagram.
  • B. Drawing a bar chart of the key phrases of the work.
  • C. Setting out the resource to be used and its limitations.
  • D. Defining the execution plan to meet the required scope of work.

正解:A


質問 # 83
A driving relationship is _____________________.

  • A. A finish-to-start relationship.
  • B. A critical relationship.
  • C. The link between a predecessor and the activity whose dates it controls.
  • D. The link between two related activities.

正解:C


質問 # 84
What is the result of a forward pass calculation?

  • A. Critical path
  • B. Value of total float for individual activities
  • C. Early start and early finish date for individual activities
  • D. Value of free float for individual activities

正解:C


質問 # 85
How much Total Float does drafting the product manual have?

  • A. 5 workdays.
  • B. 0 workdays.
  • C. 10 workdays.
  • D. 15 workdays.

正解:C


質問 # 86
What is the cycle time?

  • A. 14 minutes
  • B. 6 minutes
  • C. 17 minutes
  • D. 5 minutes

正解:C


質問 # 87
What is the free float for Activity F?

  • A. 0months.
  • B. 1months.
  • C. 2month.
  • D. 3 months.

正解:A


質問 # 88
What was the original planned duration for Activity A through Activity G?

  • A. 24.
  • B. 25.
  • C. 28.
  • D. 26.

正解:C


質問 # 89
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
  • B. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
  • C. Need only consider the non-union crafts persons.
  • D. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.

正解:D


質問 # 90
......


AACE Internationalが提供するAACE-PSP(計画およびスケジューリングプロフェッショナル)認証は、プロジェクト計画とスケジューリングのドメインを専門とする専門家のための世界的に認められた認定です。この認定は、プロジェクトの効果的な計画とスケジューリングにおける候補者の知識と経験、およびプロジェクトデータを分析および解釈する能力を評価します。

 

AACE-PSP試験問題集でPDF問題とテストエンジン:https://www.jpntest.com/shiken/AACE-PSP-mondaishu

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡