質問 # 27
When resource leveling craft labor for a critical path schedule, the scheduler
- A. Need only consider the non-union crafts persons.
- B. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
- C. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
- D. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
正解:B
質問 # 28
What is the relationship depicted between Activity G and Activity H?
- A. Start-to-start.
- B. Finish-to-finish.
- C. You cannot tell with the supplied information.
- D. Finish-to-start.
正解:A
質問 # 29
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using
- A. Start-no-later constraint on the first activity
- B. Finish-no-earlier constraint on the first activity
- C. Finish-no-earlier constraint on the last activity
- D. Finish-no-later constraint on the last activity
正解:D
質問 # 30
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project contract between the contractor and owner
- B. Project deliverables
- C. Project justification
- D. Project objectives in terms of cost, schedule and quality measures
正解:C
質問 # 31
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.
- A. LS.11001 + 25 days.
- B. 02-19-04.
- C. EF.11001.
- D. EF.11001 + 1 day.
正解:B
質問 # 32
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?
- A. 5 lifts
- B. 80 lifts
- C. 50 lifts
- D. 20 lifts
正解:C
質問 # 33
Under which circumstance should one perform resource-leveling calculations?
- A. When the contract contains a provision for float-banking.
- B. When you believe that known resource limitations may override schedule logic.
- C. Never, unless required by the contract.
- D. When the schedule is resource-loaded.
正解:B
質問 # 34
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- B. The activities occur in series with a 15-day lag.
- C. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
- D. The activities run concurrently.
正解:B
質問 # 35
Time-scaled logic diagrams are
- A. The same as a pure-logic diagram.
- B. Used to calculate the most probable activity duration.
- C. Only calculated using a computer.
- D. Logic networks that are drawn to match the calendar.
正解:D
質問 # 36
Project delays are best analyzed
- A. By an expert after the project is finished when complete records are available and the impact is known.
- B. Late in the project.
- C. Contemporaneously with the delay.
- D. After either the contractor or the owner acknowledges ^responsibility for the delay.
正解:A
質問 # 37
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 0 days.
- B. 15 days.
- C. 10 days.
- D. 5 days.
正解:D
質問 # 38
Which statement is true?
- A. Where compensability can be established, excusabltity cannot be assumed.
- B. Where compensability cannot be established, excusability is a given.
- C. Where compensability cannot be established, excusability is assumed.
- D. Where compensability can be established, excusability is assumed.
正解:C
質問 # 39
What is a key first step in developing a critical path method schedule?
- A. Drawing a bar chart of the key phrases of the work.
- B. Defining the execution plan to meet the required scope of work.
- C. Drawing the logic diagram.
- D. Setting out the resource to be used and its limitations.
正解:C
質問 # 40
Which of the following is NOT required when performing weekly or monthly schedule updates?
- A. Actual finish of activities.
- B. Remaining duration of activities.
- C. Original duration of activities.
- D. Percent complete.
正解:B
質問 # 41
What does the heavy, vertical line at "X" represent?
- A. Delay fault line.
- B. International Date Line.
- C. Change-over limits.
- D. The status or data date.
正解:D
質問 # 42
Total float is defined as the amount of time an activity can be delayed without impacting
- A. The end of that activity
- B. The next activity
- C. The overall project completion
- D. The buoyancy of a successor activity
正解:C
質問 # 43
......