[2023年12月24日]AACE-PSP練習試験問題集で試験99%合格率があります [Q27-Q43]

Share

[2023年12月24日]AACE-PSP練習試験問題集で試験99%合格率があります

最新の検証済みAACE-PSP問題と解答、合格保証もしくは全額返金


PSP認定試験は、計画とスケジュールに経験があり、この分野の知識とスキルを検証したい個人を対象に設計されています。この認定は、グローバルに認められ、プロジェクト計画とスケジュールの専門家の熟練度を示します。

 

質問 # 27
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Need only consider the non-union crafts persons.
  • B. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
  • C. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.
  • D. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.

正解:B


質問 # 28
What is the relationship depicted between Activity G and Activity H?

  • A. Start-to-start.
  • B. Finish-to-finish.
  • C. You cannot tell with the supplied information.
  • D. Finish-to-start.

正解:A


質問 # 29
If someone wanted to constrain a project's end date so that any project slippage would cause negative float, they would do so by using

  • A. Start-no-later constraint on the first activity
  • B. Finish-no-earlier constraint on the first activity
  • C. Finish-no-earlier constraint on the last activity
  • D. Finish-no-later constraint on the last activity

正解:D


質問 # 30
Which of the following are NOT normally included in the project scope statement, either directly or by reference?

  • A. Project contract between the contractor and owner
  • B. Project deliverables
  • C. Project justification
  • D. Project objectives in terms of cost, schedule and quality measures

正解:C


質問 # 31
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. LS.11001 + 25 days.
  • B. 02-19-04.
  • C. EF.11001.
  • D. EF.11001 + 1 day.

正解:B


質問 # 32
Each column must be poured in one day. Each column requires 2,000 cubic feet of concrete. The lift bucket has a capacity of 40 cubic feet. How many lifts will be required per column pour?

  • A. 5 lifts
  • B. 80 lifts
  • C. 50 lifts
  • D. 20 lifts

正解:C


質問 # 33
Under which circumstance should one perform resource-leveling calculations?

  • A. When the contract contains a provision for float-banking.
  • B. When you believe that known resource limitations may override schedule logic.
  • C. Never, unless required by the contract.
  • D. When the schedule is resource-loaded.

正解:B


質問 # 34
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • B. The activities occur in series with a 15-day lag.
  • C. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
  • D. The activities run concurrently.

正解:B


質問 # 35
Time-scaled logic diagrams are

  • A. The same as a pure-logic diagram.
  • B. Used to calculate the most probable activity duration.
  • C. Only calculated using a computer.
  • D. Logic networks that are drawn to match the calendar.

正解:D


質問 # 36
Project delays are best analyzed

  • A. By an expert after the project is finished when complete records are available and the impact is known.
  • B. Late in the project.
  • C. Contemporaneously with the delay.
  • D. After either the contractor or the owner acknowledges ^responsibility for the delay.

正解:A


質問 # 37
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?

  • A. 0 days.
  • B. 15 days.
  • C. 10 days.
  • D. 5 days.

正解:D


質問 # 38
Which statement is true?

  • A. Where compensability can be established, excusabltity cannot be assumed.
  • B. Where compensability cannot be established, excusability is a given.
  • C. Where compensability cannot be established, excusability is assumed.
  • D. Where compensability can be established, excusability is assumed.

正解:C


質問 # 39
What is a key first step in developing a critical path method schedule?

  • A. Drawing a bar chart of the key phrases of the work.
  • B. Defining the execution plan to meet the required scope of work.
  • C. Drawing the logic diagram.
  • D. Setting out the resource to be used and its limitations.

正解:C


質問 # 40
Which of the following is NOT required when performing weekly or monthly schedule updates?

  • A. Actual finish of activities.
  • B. Remaining duration of activities.
  • C. Original duration of activities.
  • D. Percent complete.

正解:B


質問 # 41
What does the heavy, vertical line at "X" represent?

  • A. Delay fault line.
  • B. International Date Line.
  • C. Change-over limits.
  • D. The status or data date.

正解:D


質問 # 42
Total float is defined as the amount of time an activity can be delayed without impacting

  • A. The end of that activity
  • B. The next activity
  • C. The overall project completion
  • D. The buoyancy of a successor activity

正解:C


質問 # 43
......


AACE-PSP認定プログラムには、プロジェクト管理における一定水準の経験と、プロジェクト計画およびスケジュール技術の知識をテストする包括的な試験の完了が必要です。この試験は、プログラムで学んだ知識を実践的かつ挑戦的なシナリオに応用できるかどうかを評価するために設計されています。認定は5年間有効であり、その後、専門家は継続的な教育と専門的な開発活動によって資格を維持する必要があります。

 

AACE-PSPリアル有効かつ正確な問題集120問題と解答が待ってます:https://www.jpntest.com/shiken/AACE-PSP-mondaishu

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡