質問 # 66
In its simplest form, what is the main drawback of critical path method scheduling?

  • A. It requires a backward pass to calculate late dates.
  • B. It assumes that resources are unlimited.
  • C. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
  • D. It doesn't account for interdependent between activities.

正解:B


質問 # 67
In order for a claimant to be entitled to an extension of contract time for a delay event (and further to be considered compensable):

  • A. The delay must affect the contractor's planned construction schedule.
  • B. The delay must be concurrent with the delay attributable to both parties.
  • C. The delay must affect the critical path.
  • D. The delay must not cause monetary harm to the defendant.

正解:C


質問 # 68
Why does activity 11001 not show successor activities?

  • A. The scheduler forgot to add the successor activities
  • B. It is the penultimate work required for the project
  • C. It is the final activity for the required work for the project
  • D. The early finish and late finish are circular

正解:C


質問 # 69
For the late finish for Activity 11001, select the most appropriate response for transitioning from the forward pass.

  • A. LS.11001 + 25 days.
  • B. EF.11001 + 1 day.
  • C. 02-19-04.
  • D. EF.11001.

正解:C


質問 # 70
Determine the correct formula and date for the late finish for Activity 9004.

  • A. LS.10002 - 1 day -> 11-27-03.
  • B. LS.10002 - Lag.7 - l day -> 11-20-03.
  • C. LS.10002^ Lag.7 + i day -> 11-20-03.
  • D. LS.10002 + 1 day -> 11-29-03.

正解:C


質問 # 71
If the administrative constraints for developing the precedence diagram, as provided in the contract documents, indicate that no individual construction activities shall have a longer duration of two months, how many activities in the "normal" schedule would be affected?

  • A. Cannot be determined.
  • B. 12.
  • C. 13.
  • D. 14.

正解:B


質問 # 72
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.

  • A. Budgeted cost of work performed (BCWP)
  • B. Budgeted cost of work scheduled (BCWS)
  • C. Estimate at completion (EAC)
  • D. Budget at completion (BAC)

正解:D


質問 # 73
Identify the late finish to develop plans and specs.

  • A. 8 months.
  • B. 10 months.
  • C. 7 months.
  • D. 9 months.

正解:D


質問 # 74
At the end of month one, did the delay to the parking structure foundation delay the project?

  • A. NO.
  • B. Yes, by 4 calendar days.
  • C. Yes, by 9 calendar days.
  • D. Yes, by 14 calendar days.

正解:B


質問 # 75
For which of these delays should an owner grant a time extension?

  • A. Structural steel shop drawings.
  • B. Differing site conditions at parking structure.
  • C. Differing site conditions and centrifuge delay.
  • D. Shop drawings and centrifuge delay.

正解:B


質問 # 76
What owner action could have mitigated the late completion of the project?

  • A. Self-perform more of the work.
  • B. Prepare better structural steel drawings.
  • C. Use a procurement agent to monitor and expedite equipment deliveries.
  • D. Hire a more senior project manager.

正解:C


質問 # 77
Using the "normal" schedule, and assuming you are billing on the last day of the month for previous month and for appropriate partial months, how many invoices will you have for this project?

  • A. 37.
  • B. 40.
  • C. 36.
  • D. 42.

正解:C


質問 # 78
An early start constraint dictates

  • A. The planned start of a successor activity
  • B. The actual start of an activity.
  • C. An activity's remaining duration.
  • D. The planned start of an activity.

正解:A


質問 # 79
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?

  • A. Start and finish constraints.
  • B. Multiple calendars.
  • C. Preferential logic.
  • D. Front end loading.

正解:D


質問 # 80
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity

  • A. It is on the critical path.
  • B. Has yet to be completed.
  • C. Was completed in the past.
  • D. Is a milestone.

正解:B


質問 # 81
Which of the following is NOT input data to the construction planning process?

  • A. Bonding capacity of subcontractors
  • B. Input from the owner
  • C. The contract
  • D. Input from the contractor

正解:A


質問 # 82
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

  • A. Predecessor is activity 4001, successor is activity 8001
  • B. Predecessor is activity 5001, successor is activity 8002
  • C. Predecessor is activity 9001, successor is activity 9002
  • D. Predecessor is activity 5001, successor is activity 8001

正解:D


質問 # 83
Resource planning must take all of the following into account except for

  • A. Cash flow (expenditure) limitations for completing work on the project.
  • B. Types of materials, equipment and labor skills required to complete the project.
  • C. Earned value techniques established for the project.
  • D. Time available to complete the project.

正解:C


質問 # 84
Identify the minimum project duration.

  • A. 21 months.
  • B. 20 months.
  • C. 19 months.
  • D. 16 months.

正解:B


質問 # 85
What is the result of a forward pass calculation?

  • A. Critical path
  • B. Value of total float for individual activities
  • C. Early start and early finish date for individual activities
  • D. Value of free float for individual activities

正解:C


質問 # 86
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The government's report on future high-clearance bridge projects
  • B. The project plans and specifications
  • C. The project geotechnical report
  • D. The regulations published by the government aviation agency

正解:A


質問 # 87
......


AACE Internationalは、コストエンジニアリング、プロジェクト管理、計画およびスケジューリングの専門家の専門協会です。協会は、AACE-PSP(計画&スケジューリング専門家)認定を含む、メンバーにさまざまな認定を提供しています。 AACE-PSP認定は、プロジェクトやプログラムの活動の計画とスケジューリングに関与している個人向けに設計されています。この認定プログラムは世界中で認識されており、専門家の計画とスケジューリングのベンチマークと見なされています。


AACE Internationalは、コストエンジニアリング、プロジェクト管理、計画・スケジューリングの専門家向けの世界的に認められたプロフェッショナル協会です。AACE Internationalは、さまざまな認定プログラムを提供しており、専門家の専門知識を認めています。AACE-PSP(計画・スケジューリングプロフェッショナル)は、AACE Internationalが提供する認定プログラムの1つです。

 

AACE International AACE-PSP問題集で一発合格できる問題を試そう!:https://www.jpntest.com/shiken/AACE-PSP-mondaishu

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡