AACE Internationalは、コストエンジニアリングとプロジェクト管理の分野の専門家にリソースとサポートを提供する専門協会です。 AACE Internationalが提供する認定の1つは、Planning&Scheduling Professional(PSP)認定です。 PSP認定は、プロジェクトの計画とスケジューリングを専門とする専門家向けに設計されており、これらの分野の知識と専門知識のレベルを実証しています。

 

質問 # 46
When resource leveling craft labor for a critical path schedule, the scheduler

  • A. Need only consider the non-union crafts persons.
  • B. Can depend on the results of the resource leveling operation to reflect a useful realignment of all schedule activities without 'further analysis.
  • C. Must consider breaks in continuity of work for subcontractors, thereby possibly incurring additional subcontractor mobilization and demobilization costs.
  • D. Need not consider its effects, as it is a theoretical concept with limited application to construction projects.

正解:B


質問 # 47
Which of the following is NOT input data to the construction planning process?

  • A. Bonding capacity of subcontractors
  • B. Input from the owner
  • C. The contract
  • D. Input from the contractor

正解:A


質問 # 48
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?

  • A. W.
  • B. C.
  • C. S.
  • D. B.

正解:C


質問 # 49
An earned value-based project control system can use either of which two budgets as the basis of its calculations?

  • A. Direct or indirect cost.
  • B. Earned or budgeted cost yearly.
  • C. Labor hours or dollars.
  • D. Linear feet or dollars.

正解:B


質問 # 50
Determine the correct formula and date for the late finish for Activity 2001.

  • A. LS.2002- 1 day-> 08-29-01.
  • B. LS.2002 - 1 day -> 08-28-01.
  • C. LS.2002 + 1 day -> 08-30-01.
  • D. LF.2001 - 1 day -> 08-28-01.

正解:B


質問 # 51
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

  • A. Value engineering.
  • B. Interest rate of owner's construction bonds.
  • C. Consideration of all stakeholders.
  • D. Project variables.

正解:B


質問 # 52
How could the structural steel drawing delay have been prevented?

  • A. Allow adequate time for review and resubmittal in the baseline schedule.
  • B. Switch to post-tensioned concrete construction.
  • C. Add a time buffer at the end of structural steel activities.
  • D. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.

正解:C


質問 # 53
Time-scaled logic diagrams are

  • A. The same as a pure-logic diagram.
  • B. Logic networks that are drawn to match the calendar.
  • C. Only calculated using a computer.
  • D. Used to calculate the most probable activity duration.

正解:B


質問 # 54
Which of the following types of delay will NOT result in a time extension and additional compensation for a contractor?

  • A. Compensable delay
  • B. Excusable delay
  • C. Non-excusable delay
  • D. Non-compensable delay

正解:D


質問 # 55
Identify the minimum project duration.

  • A. 19 months.
  • B. 20 months.
  • C. 21 months.
  • D. 16 months.

正解:B


質問 # 56
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Installation phase.
  • B. Claims and disputes phase.
  • C. Turnover and start-up phase.
  • D. Planning and design phase.

正解:D


質問 # 57
In a "crashed" schedule, which is a chain of activities that precede activity 2004?

  • A. 1001, 2002, 2002, 2003, 3001
  • B. 1001, 2002, 2003
  • C. 1001, 2001, 2002, 2003
  • D. 2001, 2002, 2003, 2007

正解:C


質問 # 58
Which is NOT an industry-recognized methodology for quantifying critical delay?

  • A. Time Impact.
  • B. Gantt Chart.
  • C. Collapsed As-Built.
  • D. Periodic Windows.

正解:B


質問 # 59
Determine the correct formula and date for the late finish for Activity 2002.

  • A. LS.2003 + 1 day -> 10-07-01.
  • B. LS.2003 - 1 day -> 10-06-01.
  • C. LS.2003 - 1 day -> 11.06.01.
  • D. LS.2003 - 1 day -> 10-05-01.

正解:D


質問 # 60
What is the workweek period for this project?

  • A. Monday through Saturday
  • B. Monday through Friday
  • C. Sunday through Friday
  • D. Sunday through Saturday

正解:D


質問 # 61
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

  • A. 10 calendar days.
  • B. 0 calendar days.
  • C. -20 calendar days.
  • D. -14 calendar days.

正解:D


質問 # 62
When reconstructing a CPM schedule electronically from a hardcopy, which of the following is NOT required to determine the critical path?

  • A. Tabular listing of activities showing duration, calendar ID, early and late dates
  • B. Detailed listing of working days for each calendar used
  • C. Assigned party responsibility for each work task
  • D. Predecessor and successor listing with logic type and lag duration, preferably sorted by activity ID

正解:C


質問 # 63
What was the original planned duration for Activity A through Activity G?

  • A. 28.
  • B. 26.
  • C. 24.
  • D. 25.

正解:A


質問 # 64
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.

  • A. The project plans and specifications
  • B. The regulations published by the government aviation agency
  • C. The government's report on future high-clearance bridge projects
  • D. The project geotechnical report

正解:C


質問 # 65
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 2003.
  • B. 1001.
  • C. 7001.
  • D. 1000.

正解:C


質問 # 66
......

無料AACE-PSP別格な問題集をダウンロード:https://www.jpntest.com/shiken/AACE-PSP-mondaishu

AACE-PSP問題集で2024年最新のAACE International試験問題:https://drive.google.com/open?id=1Z6dO-KaYWRJuAtjTU1kxeBBxE0AMKDBF

弊社を連絡する

我々は12時間以内ですべてのお問い合わせを答えます。

オンラインサポート時間:( UTC+9 ) 9:00-24:00
月曜日から土曜日まで

サポート:現在連絡