質問 28
Determine the driving activity for Activity 10001.

  • A. Activity 10002.
  • B. Activity 11001.
  • C. Activity 9005.
  • D. There is no driving activity for Activity 10001 in the backward pass.

正解: A

 

質問 29
Time-scaled logic diagrams are

  • A. Used to calculate the most probable activity duration.
  • B. Logic networks that are drawn to match the calendar.
  • C. Only calculated using a computer.
  • D. The same as a pure-logic diagram.

正解: B

 

質問 30
Which of the following is NOT required when initially planning a project?

  • A. A schedule that identifies tasks required on a project.
  • B. Logical relationships between the tasks.
  • C. Resource Identification and leveling.
  • D. The duration of each task.

正解: D

 

質問 31
These are the activities on the critical path:

  • A. A, C, E, & H.
  • B. A, B, F, & J
  • C. A, D, & I.
  • D. A, B, G, & H.

正解: D

 

質問 32
What is the free float for Activity F?

  • A. 1months.
  • B. 0months.
  • C. 2month.
  • D. 3 months.

正解: B

 

質問 33
A driving relationship is _____________________.

  • A. A critical relationship.
  • B. The link between a predecessor and the activity whose dates it controls.
  • C. A finish-to-start relationship.
  • D. The link between two related activities.

正解: B

 

質問 34
What is a key first step in developing a critical path method schedule?

  • A. Defining the execution plan to meet the required scope of work.
  • B. Setting out the resource to be used and its limitations.
  • C. Drawing the logic diagram.
  • D. Drawing a bar chart of the key phrases of the work.

正解: C

 

質問 35
Which of the following are NOT considerations or constraints of the planning process for construction scheduling?

  • A. Value engineering.
  • B. Project variables.
  • C. Interest rate of owner's construction bonds.
  • D. Consideration of all stakeholders.

正解: C

 

質問 36
What is the remaining work duration of Active D?

  • A. 0
  • B. 4.
  • C. 8.
  • D. 3.

正解: B

 

質問 37
How many work days does it take to move the product from testing to sale?

  • A. 70.
  • B. 60.
  • C. 100.
  • D. 90.

正解: C

 

質問 38
If Activity E's duration changes to 4 months, what is the overall duration of the project.

  • A. 22 months.
  • B. 21 months.
  • C. 20 months.
  • D. 19 months.

正解: C

 

質問 39
Activity 1001 started on the scheduled date but has slipped 10 days. Activity 10002 will slip 35 days. All remaining activities retain their original duration. What is the revised completion date?

  • A. 03-20-04
  • B. 03-21-04
  • C. 02-19-04
  • D. 03-11-04

正解: D

 

質問 40
Which of the following is NOT a tool or technique used to perform scope planning?

  • A. Expert Judgment.
  • B. Schedule performance indexing.
  • C. Benefit cost analysis.
  • D. Alternatives identification.

正解: B

 

質問 41
As a change to the network for the current update, activity 6002 is required to begin ten days after the beginning of activity 6001. Which is the simplest logic organization?

  • A. A finish-to-start relationship with a ten-day lag assigned to activity 6002; activity 6001 will be dependent on activity 6002
  • B. A start-to-start to relationship for both activities 6001 and 6002 with a ten-day lag assigned to activity
    6002.
  • C. A start-to-start relationship with a ten-day lag assigned to activity 6001; activity 6002 will be dependent on activity 6001
  • D. A start-to-finish relationship with both activities 6001 and 6002 having a ten-day lag

正解: A

 

質問 42
What activities are concurrent to Activity 2001 in the "normal" schedule?

  • A. 1000.
  • B. 7001.
  • C. 1001.
  • D. 2003.

正解: B

 

質問 43
Is activity 7001 pictured correctly in the precedence diagram?

  • A. No, the start-to-start and finish-to-finish relationships are backwards.
  • B. Yes, the duration is 48 days.
  • C. Yes, except the early finish date is not shown.
  • D. No, the total float is not shown correctly.

正解: B

 