質問 # 53
In the "normal" schedule, excluding Activity 1000, what activity(s) are concurrent with Activity 3001?
- A. 2004.
- B. 2003 and 7001.
- C. 4001, 5001 and 6001.
- D. 4001 and 5001.
正解:D
質問 # 54
How could the structural steel drawing delay have been prevented?
- A. Allow adequate time for review and resubmittal in the baseline schedule.
- B. Switch to post-tensioned concrete construction.
- C. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
- D. Add a time buffer at the end of structural steel activities.
正解:D
質問 # 55
What is the remaining work duration of Active D?
- A. 3.
- B. 4.
- C. 8.
- D. 0
正解:B
質問 # 56
In a "crashed" schedule, which is a chain of activities that precede activity 2004?
- A. 1001, 2002, 2002, 2003, 3001
- B. 1001, 2001, 2002, 2003
- C. 2001, 2002, 2003, 2007
- D. 1001, 2002, 2003
正解:B
質問 # 57
What method would be the best way to determine the most likely as-built critical path of a project that is underway, and the schedule of which has been partially progressed?
- A. Interview the project personnel for their perceptions and opinions because the schedule is usually inadequate.
- B. Use the forward-looking critical path of the most current updates.
- C. Use the progressed portion of the critical path of the baseline schedule.
- D. Use the progressed portion of the critical path of all the updates previous to the current update.
正解:B
質問 # 58
Which letter of the alphabet best approximates the graphical shape of a project's cumulative cost baseline, or budgeted cost of work scheduled?
- A. W.
- B. S.
- C. C.
- D. B.
正解:B
質問 # 59
The sum of all budgets for work scheduled to be accomplished within a given time period is the
____________.
- A. Budgeted cost of work performed (BCWP)
- B. Budgeted cost of work scheduled (BCWS)
- C. Budget at completion (BAC)
- D. Estimate at completion (EAC)
正解:C
質問 # 60
In analyzing a logical chain of activities in a critical path method (CPM) schedule, what do differing total float values within that chain typically indicate?
- A. Different calendars are assigned to certain activities in the logical chain.
- B. The schedule has too much detail to reflect an accurate critical path.
- C. The schedule is projecting an "early completion".
- D. Certain activities in the critical path have no successors.
正解:D
質問 # 61
Which of the following will always describe the critical path? The path with
- A. Zero float.
- B. The longest duration through the network.
- C. The shortest duration and negative float.
- D. Negative float.
正解:A
質問 # 62
The work breakdown structure is used to organize
- A. "Smart activity ID codes" representing similar items of scheduled work
- B. Similar activity coding of schedule activities
- C. The smallest defined work packet
- D. The chart of accounts
正解:C
質問 # 63
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?
- A. 255 days
- B. 267 days
- C. 407 days
- D. 362 days
正解:C
質問 # 64
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?
- A. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
- B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
- C. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
正解:C
質問 # 65
Which statement is true?
- A. Where compensability cannot be established, excusability is assumed.
- B. Where compensability can be established, excusability is assumed.
- C. Where compensability can be established, excusabltity cannot be assumed.
- D. Where compensability cannot be established, excusability is a given.
正解:A
質問 # 66
Determine the correct formula and date for the late start for the Activity 11001:
- A. LF.10001 + 1 day -> 01-16-04.
- B. LF.11001 - Dur.11001 -> 01-16-04.
- C. LF.11001 - 27 days + 1 day -> 01-14- 04.
- D. LF.1001 + DUR.10001 -> 01-14-04.
正解:A
質問 # 67
Using the "normal" schedule, what is the early finish date of activity 10002 and its total float?
- A. 12-18-03 and 25 days of float
- B. 12-27-03 and 24 days of float
- C. 12-17-03 and 4 days of float
- D. 12-18-03 and 4 days of float
正解:C
質問 # 68
Is activity 7001 pictured correctly in the precedence diagram?
- A. Yes, the duration is 48 days.
- B. Yes, except the early finish date is not shown.
- C. No, the start-to-start and finish-to-finish relationships are backwards.
- D. No, the total float is not shown correctly.
正解:A
質問 # 69
A driving relationship is _____________________.
- A. The link between a predecessor and the activity whose dates it controls.
- B. The link between two related activities.
- C. A critical relationship.
- D. A finish-to-start relationship.
正解:A
質問 # 70
How much Total Float does drafting the product manual have?
- A. 15 workdays.
- B. 5 workdays.
- C. 0 workdays.
- D. 10 workdays.
正解:D
質問 # 71
Which of the following is NOT input data to the construction planning process?
- A. The contract
- B. Input from the contractor
- C. Input from the owner
- D. Bonding capacity of subcontractors
正解:D
質問 # 72
Which of the following are NOT normally included in the project scope statement, either directly or by reference?
- A. Project contract between the contractor and owner
- B. Project objectives in terms of cost, schedule and quality measures
- C. Project justification
- D. Project deliverables
正解:C
質問 # 73
Due to a testing delay, release of the product for manufacture is delayed by 5 workdays and the product manual misses its print window at the printer. If the printer is delayed by 10 workdays, what is the delay to produce release?
- A. 0 days.
- B. 5 days.
- C. 15 days.
- D. 10 days.
正解:B
質問 # 74
What owner action could have mitigated the late completion of the project?
- A. Prepare better structural steel drawings.
- B. Use a procurement agent to monitor and expedite equipment deliveries.
- C. Hire a more senior project manager.
- D. Self-perform more of the work.
正解:B