質問 # 78
A business analyst anticipates receiving requirements changes. What should the business analyst do to avoid scope creep?
- A. Define requirements baseline and implement a change control process.
- B. Refer changes to the project manager.
- C. Meet with the stakeholder and discuss timeline impact.
- D. Implement only the original requirements.
正解:A
解説:
According to the PMI Professional in Business Analysis objectives and content, scope creep is the uncontrolled or unauthorized expansion of the project scope due to the addition or modification of requirements without proper approval or justification. Scope creep can negatively affect the project's quality, schedule, cost, and stakeholder satisfaction. To avoid scope creep, the business analyst should define a requirements baseline, which is a set of agreed-upon and approved requirements that serves as a reference for further development and testing activities. The business analyst should also implement a change control process, which is a formal and systematic procedure for managing and documenting any changes to the requirements or scope. The change control process should include steps such as identifying, analyzing, evaluating, approving, communicating, and implementing the changes, as well as updating the requirements baseline and traceability matrix accordingly. References:
* PMI Professional in Business Analysis objectives and content: PMI-PBA Certification
* PMI Professional in Business Analysis reference list: PBA Reference List
* PMI Professional in Business Analysis study guide: Study.com
質問 # 79
Which of the following best describes the function of the requirements baseline?
- A. Provides the basis for the development scope.
- B. Defines how the project will be scheduled.
- C. Controls the product development and evolution.
- D. Tracks the progress of requirements documentation.
正解:A
解説:
Explanation
The requirements baseline is a set of approved and prioritized requirements that are used as the basis for the development scope. The requirements baseline defines what the project or program will deliver and what the stakeholders expect to receive. The requirements baseline also serves as a reference point for managing changes and measuring progress. References: PMI Guide to Business Analysis, Chapter 9, Section 9.3.1; PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline, Domain IV: Traceability and
Monitoring, Task 1.
質問 # 80
A company wants to procure a tool to improve customer satisfaction and loyalty. Which of the following documents would provide basis for analyzing vendor products?
- A. Project charter
- B. Storyboard
- C. Survey
- D. Business case
正解:C
解説:
Explanation
A survey is a technique to collect information, opinions, or feedback from a large number of stakeholders, such as customers or users. A survey can help to measure the current level of customer satisfaction and loyalty, and to identify the needs and expectations of the customers for the tool. A survey can provide a basis for analyzing vendor products by comparing their features, benefits, and costs with the customer requirements.
The other options are not suitable for this purpose. A storyboard is a technique to visualize the user interface or user experience of a solution using sketches or mockups. A project charter is a document that authorizes the project and defines its objectives, scope, and stakeholders. A business case is a document that provides the justification for initiating a project based on its expected benefits, costs, and risks. References: PMI-PBA Examination Content Outline, page 11; PMI-PBA
Reference List, page 1, BABOK
Guide v3, page 50.
質問 # 81
A project team delivers a solution based on the approved requirements and is confident that it meets the defined acceptance criteria.
What should the business analyst do to obtain signoff?
- A. Contact the sponsor.
- B. Contact the stakeholder who provided the majority of requirements in the traceability matrix.
- C. Refer to the RACI matrix to identify who is responsible for signoff.
- D. No signoff is necessary.
正解:C
解説:
A RACI matrix is a tool that defines the roles and responsibilities of stakeholders in a project or a process. It clarifies who is Responsible, Accountable, Consulted, and Informed for each task or deliverable. The business analyst should refer to the RACI matrix to identify who is responsible for signoff, as this person has the authority and accountability to approve the solution and its testing results. Contacting the sponsor, the stakeholder who provided the majority of requirements, or the project manager may not be appropriate, as they may not be the designated person for signoff according to the RACI matrix. No signoff is necessary is incorrect, as signoff is an important step to confirm that the solution meets the requirements and acceptance criteria. References: PMI Professional in Business Analysis (PMI-PBA)Examination Content Outline1, page 13; Business Analysis for Practitioners: A Practice Guide2, page 77.
質問 # 82
A business analysis team has collected the main business requirements from the major stakeholders of a project. The team wants to be sure that each stakeholder has a clear understanding of the areas of analysis that will be in scope.
Which model should the team employ to ensure the most effective representation of analysis boundary?
- A. State diagram
- B. Entity relationship diagram
- C. Data flow diagram
- D. Context diagram
正解:D
解説:
Explanation
According to the PMI Guide to Business Analysis, a context diagram is a model that shows the boundaries of an area of analysis, such as a project, a system, a process, or an organization. A context diagram depicts the main entities or actors involved in the area of analysis, and the interactions or data flows between them. A context diagram can help to ensure the most effective representation of analysis boundary, as it provides a high-level overview of the scope and context of the area of analysis, and helps to identify the key stakeholders and their relationships. A context diagram can also help to communicate and validate the scope and context with the stakeholders, and to identify any assumptions or risks related to the area of analysis. A data flow diagram, a state diagram, and an entity relationship diagram are other models that can help to analyze an area of analysis, but they do not necessarily show the boundary or scope of it. References: PMI Guide to Business Analysis, page 158-159.
質問 # 83
In the middle of a project, a new requirement was added to the scope. The business analyst must determine if any impacts, dependencies, or risks are associated with the addition to the scope.
What task should the business analyst perform in order to identify these impacts?
- A. Manage requirements prioritization.
- B. Manage assumptions and constraints.
- C. Manage solution scope.
- D. Manage requirements traceability.
正解:C
質問 # 84
A stakeholder requests to add new critical requirements the day before the scheduled baseline requirements approval meeting The stakeholder insists that these requirements must be taken into account despite time and budget constraints.
What is the most effective way to manage this situation?
- A. Postpone the baseline approval meeting, analyze the impact, and schedule a new meeting to discuss dependencies and priorities with stakeholders.
- B. Ask for more resources to manage this change and justify these additional resources with the value the change will give to the company.
- C. Share the new requirements with all stakeholders and ask them to submit their comments before the meeting.
- D. Discuss the change with stakeholders during the baseline approval meeting and ask them to approve the new baseline.
正解:A
質問 # 85
A project team has 120 days to deliver a solution, but the stakeholders have too many requirements for the delivery window. What requirements prioritization technique should be used to determine which requirements will be delivered?
- A. Multivoting
- B. Time-boxing
- C. Budget analysis
- D. MoSCoW
正解:D
解説:
Explanation/Reference: https://www.modernanalyst.com/Resources/Articles/tabid/115/ID/3332/Techniques-to-Prioritize- Requirements.aspx
質問 # 86
A business analyst is planning the business analysis activities for a new payroll project. Due to a tight timeline, the analyst advises stakeholders that the requirements sessions should begin as soon as possible.
Which key factor drives the selection of business analyst activities to be included in the project?
- A. Payback period
- B. Return on investment (ROI)
- C. Project life cycle
- D. Communication plan
正解:C
質問 # 87
The besl way lo ensure Ihe integrity of requirements is to:
- A. use a requirements management tool, measure requirements volatility, and maintain a history of requirements changes
- B. implement version control, maintain a history of requirements changes, and track the status of each requirement
- C. establish a requirements baseline, establish a change control board, and label each requirement uniquely
- D. establish a change control board, track the status of each requirement, and use a requirements management tool
正解:B
質問 # 88
The requirements traceability matrix should primarily be used to:
- A. identify the risks associated with dependent requirements.
- B. define a convention to map the requirements to their sources.
- C. ensure that all requirements have been met.
- D. address the responsibility owner for each requirement.
正解:C
解説:
Explanation
A requirements traceability matrix (RTM) is a tool that helps to track the relationship between the requirements and the product features, test cases, and other artifacts. It can be used to ensure that all requirements have been met by verifying that each requirement has a corresponding feature, test case, and acceptance criterion. A RTM can also help to identify the risks associated with dependent requirements, but that is not its primary purpose. A RTM does not define a convention to map the requirements to their sources, but rather uses an existing convention or standard. A RTM does not address the responsibility owner for each requirement, but rather shows the status and priority of each requirement. References: PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline1, PMI Guide to Business Analysis2, Business Analysis for Practitioners: A Practice Guide
質問 # 89
A company has completed a major project within time. cost, and scope and satisfied high-level quality standards and marketing requests. However, the product was considered a complete failure by shareholders and the market due to low return on investment From the business analysis perspective, the main reason for this business failure was a failure to:
- A. gather the appropriate usability requirements
- B. set the product positioning
- C. review and evaluate market expectations
- D. establish measurable success criteria in the business case
正解:D
質問 # 90
The business analyst wishes to clarify the project's key business drivers and ensure that requirements can be prioritized to provide maximum business value. Which question should the business analyst ask of stakeholders to help obtain this clarification?
- A. How is the organizational chart structured?
- B. What is the business need?
- C. Which functional areas are impacted?
- D. Which stakeholders have the most influence?
正解:B
質問 # 91
What is a standardized, effective, and efficient way to manage changes to project documentation?
- A. A configuration verification and audit system
- B. A change control board
- C. A configuration management system
- D. A requirements traceability matrix
正解:C
解説:
Explanation
A configuration management system is a standardized, effective, and efficient way to manage changes to project documentation. A configuration management system is a set of tools and processes that help to track, control, and update the configuration items (CIs) of a project, such as documents, requirements, designs, code, tests, etc. A configuration management system helps to ensure that the project documentation is consistent, accurate, and up-to-date throughout the project life cycle. It also helps to maintain the traceability and auditability of the changes made to the project documentation. A configuration management system typically includes the following components:
A configuration management plan that defines the scope, roles, responsibilities, policies, procedures, and standards for configuration management.
A configuration management database (CMDB) that stores the information about the CIs, their attributes, relationships, versions, baselines, and changes.
A configuration identification process that assigns unique identifiers and names to the CIs and their versions.
A configuration control process that evaluates, approves, and implements changes to the CIs and their versions.
A configuration status accounting process that records and reports the status and history of the CIs and their versions.
A configuration verification and audit process that verifies and validates the CIs and their versions against the requirements and specifications.
References: = PMI Professional in Business Analysis (PMI-PBA)
Examination Content Outline, page 13.
質問 # 92
The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client's business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.
Which technique is being used?
- A. Brainstorming
- B. Idea and mind mapping
- C. Workshop sessions
- D. Delphi technique
正解:C
解説:
Workshop sessions are a technique to elicit, analyze, and prioritize requirements by bringing together a group of stakeholders, such as subject matter experts, to collaborate and reach a consensus. Workshop sessions can be used to identify and prioritize the requirements for a newly approved project. The other techniques are not suitable for this purpose. Delphi technique is a technique to obtain expert opinions anonymously and iteratively until a consensus is reached. Brainstorming is a technique to generate a large number of ideas or solutions in a short time. Idea and mind mapping is a technique to visually organize ideas or information using diagrams or graphs. References: PMI-PBAExamination Content Outline, page 10; PMI-PBA Reference List, page 1, BABOK Guide v3, page 50.